AI summaryCity of York Council adopted the Community Infrastructure Levy for 1 February 2026 [D], with projected receipts of £19m [P37] and a future Executive report on spending [D].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedImplementation set for 1 February 2026 [D]
MoneyProjected receipts of £19m [P37]Previously estimated at c.£40m [P12]
What happens nextExecutive to consider CIL spending [D]A further report will go to a future Executive [D]
Who it affectsNot stated
What was decided
Council accepted the independent Examiner's conclusions and the proposed modifications. Report P3, P41
It adopted the Charging Schedule in Annex A as modified by Annex B, for implementation on 1 February 2026. Report P42
The Director of City Development may review the instalment policy, make minor editorial changes and change the implementation date if necessary. The Director for Environment and Regulatory Services may agree publication and necessary documentation. Report P44, P45
Why
Independent examination found the draft Charging Schedule compliant with the Act, Regulations and national policy, subject to modifications. Report P3, P80, P88
The changes reflect updated viability evidence, including higher build costs, and are intended to keep rates proportionate and viable. Report P9, P10, P60
Implementation on 1 February 2026 allows time for systems, staff, communications and the statutory challenge period. Report P91, P92
What happens next
The Director of City Development will review the instalment policy and may make minor editorial changes or change the implementation date if necessary. Report P44
The Director for Environment and Regulatory Services will agree publication and necessary documentation for the introduction of CIL. Report P45
A future Executive will receive a further report on spending the CIL receipts. Report P47
The money
£19m Projected CIL receipts over the Plan Period Report P37
c.£40m Earlier projected receipts before the Examiner modifications Report P12
£75 per sqm Revised residential rate, reduced from £150 per sqm Report P9
£150 per sqm Accepted rate for purpose built student accommodation Report P9
5% Administration fee in the spending schedule Report P39
in the region of £1m Estimated administration fee income over the period Report P95
c.£460m Funding gap for strategic infrastructure Report P13
Options considered
Chosen: Accept the Examiner's conclusions and proposed modifications. The Examiner found the approach sound subject to modifications, and the modifications are required for legal adoption. Report P88, P98
Chosen: Adopt the Charging Schedule. Adoption would provide a new developer contribution method and allow collection from a broader range of residential applications. Report P89
Chosen: Implement from 1 February 2026. The date allows time to prepare systems, communications and administration, and to complete the statutory challenge period. Report P91, P92
Chosen: Delegate instalment review to the Director of City Development and publication to the Director for Environment and Regulatory Services. This permits responsive operational decisions and review of payment triggers and timescales. Report P46, P93, P94
Rejected: Do not accept the Examiner's conclusions or modifications. Not accepting the report would prevent adoption and leave the Council with Section 106 contributions only. Report P90
Rejected: Do not adopt the Charging Schedule. Not adopting the schedule would conflict with the June 2022 decision and retain the existing contribution approach. Report P90
Rejected: Implement immediately after the Council decision. The shorter period was considered infeasible and risked inadequate preparation, reduced public confidence, errors, appeals and complications. Report P92
Rejected: Agree alternative delegations for implementation. The Council used the two specified delegations in options vii and viii. Report P86, P93
Implications
Financial: Projected receipts are £19m over the Plan Period, while a c.£460m strategic infrastructure funding gap remains. Report P13, P37
Financial: Administrative work will create additional costs, with up to 5% of the levy available to cover them. Report P95
Legal: The Council can adopt only with the modifications needed to remedy the failure identified by the Examiner. A 6 week judicial review period will allow a challenge to implementation. Report P81, P98
Risk: Without suitable software and trained staff, rollout may cause administrative errors, delays or noncompliance. Report P110
Staffing: There are no immediate HR implications, but monitoring, governance and delivery may require additional resources. Report P96
Equalities: The full EIA identifies positive impacts from funded healthcare, education, transport and green infrastructure. Report P104
Climate: CIL funds may support district heating schemes, parks and open spaces. Report P102
Other: CIL may fund health facilities, schools, parks, roads and community facilities, reducing the burden on existing residents. Report P101, P103
Who and where
Developers whose planning permission is granted after the Charging Schedule takes effect Report P64
Most developments over 100 sqm or any new dwelling Report P5
All wards Report P111
Neighbourhoods eligible for the Neighbourhood Fund Report P16, P17
Council planning, finance, legal and technical services Report P91, P95, P96
Qualifying affordable and charitable developments seeking relief Report P26, P27, P34
Existing residents Report P103
Timeline
16 June 2022: Executive agreed to proceed with preparing a CIL. Report P74
18 July 2025: The CIL Draft Charging Schedule and supporting evidence were submitted for independent examination. Report P56, P74
22 October 2025: The Examiner's Report was received and published. Report P3, P80
4 November 2025: The Executive meeting on proceeding took place before Council considered adoption. Report P4
6 November 2025: Council adopted the modified Charging Schedule.
6 weeks after the Council decision: The statutory judicial review period allowed a challenge to implementation. Report P81
1 February 2026: Planned implementation of the adopted CIL. Report P42
Plain English for the jargon
Community Infrastructure Levy: A fixed charge per square metre on most development of 100 square metres or more, or a new dwelling of any size. [P49]
Charging Schedule: The document that sets CIL rates and the date from which it takes effect. [P19] [P21]
Examiner: An independent person who checks legal compliance, consultation and development viability. [P56]
Section 106 agreement: A planning obligation used for infrastructure at the development and for affordable housing. [P48]
Instalment Policy: A published policy setting when CIL payments can be made in phases. [P28]
Neighbourhood Fund: The part of CIL receipts that must be spent in the local area. [P16] [P17]
Commencement Notice: A required notice for retaining relief; failure to submit it may lead to a surcharge. [P50]
Judicial review: A High Court challenge to an Examiner's conclusions, based on procedural unfairness, irrationality or illegality. [P11]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61
Resolved
Resolved – That Council i) Accepts the outcomes of the independent Examiner’s Report (Annex B to the report), including modifications proposed by the Examiner to ensure the and proposed Charging Schedule can be soundly implemented. ii) Adopts the (Annex A to the report), as proposed to be modified (Annex B to the report), for implementation on 1 February 2026. Reason: To allow the CIL Schedule to be legally adopted and implemented effectively, in line with the recommendations of the independent Examiner and national planning guidance. iii) Delegates authority to the Director of City Development to review the instalment policy and make any necessary further minor editorial changes to the Charging Schedule or a change to the implementation date, if necessary. iv) Delegates authority to the Director for Environment and Regulatory Services to agree publishing and necessary documentation for the introduction of CIL. Reason: To enable timely and efficient progression of the CIL adoption process, ensuring operational readiness, sound implementation and regular monitoring. v) To note that a further report regarding the spending of CIL will be brought to a future Executive for consideration. Reason: To allow Executive to consider how to spend the CIL monies received. (The meeting then adjourned at 8.45pm and reconvened at 9.00pm.)
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting: Council Meeting date: 6 November 2025 Report of: Garry Taylor, Director of City Development Portfolio of: Councillor Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equality and Inclusion
Decision Report: Community Infrastructure Levy Subject of Report 1. Executive in Summer 2022 resolved to proceed with a Community Infrastructure Levy (CIL) as a charging mechanism for the delivery of associated infrastructure resulting from development. Subsequently, a number of consultations on the CIL Draft Charging Schedule have taken place with the final draft version submitted for independent Examination on 18 July 2025.
2. Examination concluded on 22 October 2025 with receipt of the Examiner’s Report, wherein it concluded that “the draft City of York Community Infrastructure Levy Charging Schedule, subject to the making of the modifications… satisfies the drafting requirements and I therefore recommend that the draft Charging Schedule be approved.”
3. Subject to the decision of the Executive to be taken on 4 November 2025, this report recommends adoption of the Community Infrastructure Levy inclusive of the proposed modifications recommended by the Examiner.
Benefits and Challenges 4. CIL provides a consistent, non-negotiable charge per square metre on most developments over 100 sqm or any new dwelling. This will capture developments that currently do not contribute to infrastructure delivery where they are either ineligible for making Section 106 contributions or are not sufficiently meaningful to deliver an infrastructure project. It is the cumulative impact of these sites that have a consequential impact on the city’s social, health and transport infrastructure, which CIL can address through capturing funding contributions toward essential infrastructure improvements.
5. The introduction of a CIL Charging Schedule provides a predictable and transparent approach for developers by being clear and upfront in relation to what they will be expected to pay. It should lead to early discussions in relation to ensuring scheme viability as well as simplifying the process.
6. For the Council, it also means that we can plan infrastructure investment more effectively with a clearer understanding of future income. CIL funds can be allocated to strategic or local infrastructure priorities without being tied to the development site, supporting delivery of the Council’s long-term growth and infrastructure planning. Unlike Section 106 agreements, CIL enables the Council to pool contributions and fund infrastructure across the city, rather than being limited to site-specific mitigation.
7. The CIL will continue to operate alongside Section 106 agreements but should streamline the process of complex negotiations. Section 106 agreements will focus on on-site or site-specific mitigation (particularly for the large strategic sites and/or where affordable housing is necessary) tied to the development, while CIL handles broader infrastructure needs.
8. The CIL Examination has provided an independent review of the process undertaken and found that, subject to proposed modifications, the schedule is proportionate and a viable approach by which to proceed. The Examiner accepted the levy rate for purpose-built student accommodation (PBSA) at £150 per sqm for but has proposed two modifications to the draft Schedule: £0 rating all strategic sites Reducing the residential rate from £150 to £75 per sqm.
9. The revised draft CIL Charging Schedule proposed by the Examiner reflects his consideration of the updated viability evidence, including consideration of a general uplift in build costs, and evidence presented at Examination. The modifications are seen as necessary to set rate charges that are proportionate and viable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update to Pay Policy Statement 2026/2027That Council approves the updated Pay Policy Statement for 2026 – 2027. Reason: In order to fulfil the requirements o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.