Executive, Thursday 16 June 2022 at 5.30pm

Introduction of Community Infrastructure Levy (6:51 pm)

Approved Executive 2 papers

Executive approved this item on Thursday 16 June 2022. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

(i) That approval be given to move forward with the preparation of a Community Infrastructure Levy (CIL) for York. Reason: To enable the collection of funding from landowners/developers to help support delivery and mitigate infrastructure impacts of the development envisaged in the emerging Local Plan. (ii) That it be noted that a Draft CIL Charging Schedule setting out proposed rates will be presented to Executive for agreement prior to formal consultation later in 2022, because before CIL can be published and charged, a Draft Charging Schedule must be formally consulted on in line with the CIL Regulations 2010 (as amended 2019). (iii) That the recommendation of the Local Plan Working Group to seek input from the Economy and Place Policy & Scrutiny Committee on the approach to be taken to neighbourhood funding, prior to making a decision regarding the policy on this, be accepted. Reason: In accordance with the scrutiny work programme, and to ensure that this aspect of the CIL is properly considered and consulted upon. (i) That approval be given to move forward with the preparation of a Community Infrastructure Levy (CIL) for York. Reason: To enable the collection of funding from landowners/developers to help support delivery and mitigate infrastructure impacts of the development envisaged in the emerging Local Plan. (ii) That it be noted that a Draft CIL Charging Schedule setting out proposed rates will be presented to Executive for agreement prior to formal consultation later in 2022, because before CIL can be published and charged, a Draft Charging Schedule must be formally consulted on in line with the CIL Regulations 2010 (as amended 2019). (iii) That the recommendation of the Local Plan Working Group to seek input from the Economy and Place Policy & Scrutiny Committee on the approach to be taken to neighbourhood funding, prior to making a decision regarding the policy on this, be accepted. Reason: In accordance with the scrutiny work programme, and to ensure that this aspect of the CIL is properly considered and consulted upon.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 10 pages

Summary

1. Since 2010, authorities in England and Wales have also been empowered to establish a Community Infrastructure Levy (CIL) to help pay for infrastructure to support development such as schools, green infrastructure and sustainable transport. This report seeks agreement to introduce a CIL in York to support the implementation of the Local Plan (“the Plan”). It will help ensure infrastructure to support development envisaged is delivered in the right time and in the right place. Subject to views of Executive, a CIL Draft Charging Schedule setting out the proposed charges for consultation can be prepared for approval and then formal consultation in Autumn 2022.

Recommendations

2. The Executive is asked to:

1) Agree to move forward with the preparation of a Community Infrastructure Levy (CIL) for York.

Reason: To enable collection of funding from landowners/developers to help support delivery and mitigate infrastructure impacts of the development envisaged in the emerging Local Plan.

2) To note that a Draft CIL Charging Schedule setting out proposed rates will be presented to Executive for agreement prior to formal consultation later in 2022.

Reason: Before CIL can be published and charged, a Draft Charging Schedule must be formally consulted on in line with the CIL Regulations 2010 (as amended 2019). Background

3. As York moves a step closer to its first adopted Plan, there is an opportunity to consider how the Council can use other planning tools and processes to support its implementation, from Supplementary Planning Documents to support policy implementation to targeted and evidence led use of Article 4 Directions to ensure Plan delivery. The Council’s approach to securing developer contributions presents a particular opportunity to enable delivery of Plan policies.

4. Planning obligations (frequently referred to as ‘Section 106 agreements’ or S106) are negotiated between the Council and landowners/developers to mitigate the impact of a development or to secure certain requirements/obligations as part of a development. They are currently the only mechanism used in York to secure landowner/developer financial contributions. They can include: • Requirements for parts of a development to be used in certain ways, for example, for a percentage of home to be affordable housing;

• Requirements for certain works to be undertaken or for other requirements and/or restrictions on the form of the development, for example requiring certain works to the highway;

• Financial contributions to address the impacts of development – usually limited to those cases where it is not feasible to meet policy requirements on site and/or to mitigate specific development impacts, such as the provision of open space. 5. S106 can only be used where the legal tests set out in the CIL Regulations 2010 (as amended) are met. That is S106 must be: • Necessary to make the development acceptable in planning terms;

• Directly related to the development; and

• Fairly and reasonably related in scale and kind to the development.

6. Since 2010, authorities in England and Wales have been empowered to establish a Community Infrastructure Levy (CIL) to help pay for infrastructure to support development. This charge on the development can operate alongside S106, which can continue to be used for affordable housing and other on-site infrastructure. 7. CIL is a fixed, non-negotiable, charge per square metres on most development of 100 square metres or more, or a new dwelling of any size. It is calculated using standard formulae set out in the CIL Regulations. There are exceptions and reliefs from payment of CIL provided for in the Regulations, and available by application; this applies to affordable housing, most charitable developments, self-build homes and residential annexes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Introduction of Community Infrastructure Levy (6:51 pm)Report 10 pages DownloadRead as text
PDF
View item 9. as HTML 62 KBReport 62 KB Copy on its way

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies