AI summaryCity of York Council's Place Scrutiny Committee endorsed the remit, objectives and timeframe for a Task and Finish Group review of Section 106 process improvements, with a final report planned for September 2026. [D][P23][P16]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThe Task and Finish Group can begin work. [D][P24]
MoneyNot stated
What happens nextFinal report planned: September 2026 [P16]Work runs over spring and summer 2026. [P16]
Who it affectsAll City of York wards [P27]Section 106 planning agreements across the city. [P2]

What was decided

The Place Scrutiny Committee endorsed the proposed remit, objectives and timeframe for the Section 106 process review. [D][P23] Report P23

The agreed review structure is a Task and Finish Group reporting to the Place Scrutiny Committee. [P4][D] Report P4

Work will take place over spring and summer 2026, with a final report planned for September 2026. [P16][D] Report P16

Why

The endorsement enables the Task and Finish Group to begin work towards the planning process motion agreed by Council in September 2025. [D][P24] Report P24

The group will share details of the existing review of outstanding Section 106 money and spending plans, minimise the risk of returning money to developers, and improve responses to enquiries, including from the NHS. [P6][P7] Report P6, P7

The review will create a system for ward members to identify discretionary contribution priorities, strengthen monitoring and swift action on breaches, and support prompt spending with clear monitoring. [P8][P9][P10] Report P8, P9, P10

What happens next

The group will use existing documents and consult relevant Council officers, including from the Planning and Finance teams. [P14] Report P14

Further consultation will ensure the review complements Veritau's audit and avoids duplicated work. [P12][P13] Report P12, P13

The group will identify relevant implications, include identified risks in the draft final report, and plan to present that report in September 2026. [P16][P21][P22] Report P16, P21, P22

Options considered

  • Chosen: Endorse the proposed remit, objectives and timeframe. Council had already approved establishing the group. Report P17
  • Rejected: Suggest amendments to the proposed remit Report P17

Implications

  • Legal: Section 106 agreements are legally binding planning agreements between the Council and a property owner, used to mitigate new development impacts. [P2] Report P2
  • Financial: The review will consider how to minimise the risk that outstanding Section 106 money must be returned to developers. [P6] Report P6
  • Financial: Veritau's current audit covers safeguards for developer contributions, records management, appropriate spending and transparent reporting of held funds. [P12] Report P12
  • Risk: Any risks associated with the review findings will be included in the draft final report. [P22] Report P22
  • Other: There are no direct implications to address at this stage, and the group will identify relevant implications during its review. [P21] Report P21
  • Other: The review is relevant to all seven Council key priorities because Section 106 agreements can support services and infrastructure. [P19][P20] Report P19, P20
  • Other: The review will complement Veritau's audit and avoid duplicated work. [P13] Report P13

Who and where

  • City of York Council, which manages and monitors all active Section 106 agreements in its area. Report P2
  • Property owners entering Section 106 agreements and people affected by new development. Report P2
  • Developers whose contributions or outstanding money are subject to Section 106 agreements. Report P6, P12
  • Section 106 consultees, including the NHS. Report P7
  • Ward members identifying priorities for discretionary Section 106 contributions. Report P8
  • Relevant Council officers and Veritau are involved in consultation and audit coordination. Report P12, P13, P14
  • All City of York wards. Report P27
  • Services and infrastructure supported through Section 106 contributions. Report P19, P20

Timeline

  • 18 September 2025: Full Council agreed a Motion on Notice on Planning Process Improvements, which called for the review group. Report P2, P29
  • 11 May 2026: The officer report was dated and marked approved. Report P26
  • spring and summer 2026: The Task and Finish Group's work is proposed for this period. Report P16
  • September 2026: A final report is planned for the committee. Report P16

Plain English for the jargon

  • Section 106 agreement: A legally binding planning agreement between the local planning authority and a property owner, used to mitigate the impacts of new development. [P2]
  • Task and Finish Group: The group reviewing Section 106 process improvements and reporting to the Place Scrutiny Committee. [P4][D]
  • Consultee: An organisation asked to respond to Section 106 enquiries. [P7]
  • Ward member: A member identifying priorities within a ward for Section 106 contribution categories where there is discretion. [P8]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38

Resolved

i. The Committee endorsed the proposed remit, objectives, and timeframe for a Task and Finish Group review into Section 106 Agreements Process Improvements. Reason: To enable the Task and Finish Group to proceed with work on the agreed review, towards fulfilment of the motion agreed by Council in September 2025 on Planning Process Improvements.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Place Scrutiny Committee, 4 pages

Summary

1. This report seeks the Committee’s agreement to the proposed remit (Annex A) of a Task and Finish Group review into process improvements in relation to Section 106 Agreements.

Background

2. Section 106 agreements are legally binding agreements entered into between a local planning authority and a property owner as part of the planning process in order to mitigate the impacts of new development and to make development acceptable which would otherwise be unacceptable in planning terms. City of York Council is responsible for managing and monitoring all active Section 106 agreements within its administrative area. 3. At the September 2025 meeting of Full Council, a Motion on Notice on Planning Process Improvements, moved by Cllr Steward and incorporating an amendment moved by Cllr B Burton, was agreed.

4. The Motion called for a cross-party group to be set up to look at improvements to the Section 106 process, including five specific objectives as detailed below.

5. It is proposed that this group should take the form of a Task and Finish Group reporting to the Place Scrutiny Committee.

Aim and Objectives

6. The agreed Council motion specified five objectives for the Group as below:  Share details and discuss the existing review of outstanding S106 money and the plans to spend it (and absolutely ensure any risk of it needing to return it to developers is minimised)

 Improving the process of ensuring all consultees respond to S106 enquiries (noting for example a notable number of large applications which have received no NHS response)

 Creating a system for ward members to identify their ward priorities in the different categories of s106 contributions (in which there is discretion i.e. not education, early years places etc) to inform officers when drafting s106 agreements;

 Ensuring the monitoring of S106 agreements is rigorous and breaches are swiftly acted upon.

 Ensuring that the monies received are spent as promptly as possible to deliver the mitigations / benefits they are for, and that there is a clear monitoring system for this.

Consultation and Methods

7. Consultation has taken place with the Council’s internal auditor, Veritau. Veritau is currently undertaking an audit of the controls in place around Section 106 Agreements, including around ensuring there are appropriate safeguards to the Council in the use of developer contributions; a cohesive framework and records management; that Section 106 contributions are appropriately drawn down for spending; and transparency in reporting on funds held against Section 106 obligations.

8. Further consultation will take place with a view to ensuring the Task and Finish Group review is complementary to this audit and avoids any duplication of work.

9. Methods will include desk-based work and consultation with relevant Council officers, including from the Planning and Finance teams.

Timeframe

10. It is proposed that the Group’s work is carried out over spring and summer 2026, with a view to presenting a final report to the Committee in September 2026. Options and Analysis

11. As establishing the group has already been approved by Council, the options available for Members at this stage are either endorse or suggest amendments to the proposed remit of the Task and Finish Group.

Council Plan

12. As Section 106 agreements can be used to support the provision of services and infrastructure, the proposed work has relevance for all seven of the Council’s key priorities, as set out in the Council Plan 2023- 27 (One City, for all).

Implications

13. There are no direct implications to be addressed at this stage in the process. Any relevant implications will be identified by the Task and Finish Group during their review.

Risk management

11. Any identified risks associated with the findings from this review will be included in the draft final report arising from this review.

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Task and Finish Group Proposal: Section 106 Agreements Process Improvements (18:22)Report 4 pages DownloadRead as text
PDF
Task and Finish Proposal s106Report 2 pages Download
PDF
View as HTML (38./2) 14 KBReport 14 KB Copy on its way
PDF
View item 38. as HTML 33 KBReport 33 KB Copy on its way

At this meeting

Whole meeting
36Minutes (17:37)Decided 37Neighbourhood Caretakers Development and Update (17:37)Decided
38Task and Finish Group Proposal: Section 106 Agreements Process Improvements (18:22)This decision
39Work Plan (18:33)Noted

Who was there

10 of 10 attended
DM
Councillor Danny MyersChair, present
PH
Councillor Paul HealeyVice-Chair, present
SF
Councillor Stephen FentonCommittee Member, present
AH
Councillor Anne HookCommittee Member, present
TC
Councillor Tony ClarkeCommittee Member, present
KT
Councillor Kallum TaylorCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
MW
Councillor Margaret WellsCommittee Member, present
CW
Councillor Conrad WhitcroftCommittee Member, apologies, sent representative
AB
Councillor Anna BaxterCommittee Member, present as substitute

On this subject at York

Search all
  1. Task and Finish Group Proposal: Section 106 Agreements Process Improvements (18:22)This decision
  2. Task and Finish Group Review into Housing Repairs (6:57pm)Agreed
  3. Report of the Budget and Medium-Term Financial Strategy Task and Finish GroupDecided
  4. Draft Report of the Budget and Medium-Term Financial Strategy Task and Finish Group (5.33 pm)Approved
  5. Budget and Medium-Term Financial Strategy Scrutiny, Task and Finish Group (6.29 pm)Decided
  6. Boundary Commission Electoral Review - Council Size, Task and Finish Group (6.52 pm)Approved

More from York Place Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Jul 2026 Minutes (17:50)That the minutes of the Place Scrutiny Committee on 16 June 2026 be signed as a correct record of the meeting. Decided Open
21 Jul 2026 York Central Mayoral Development Zone (17:54)i. To recommend that the Council request that York ... view the full minutes text for item 13. Decided Open
21 Jul 2026 Work Plan (20:38)i. Noted the Committee work plan. Reason: To ensure the Committee maintains a programme of work. Noted Open
16 Jun 2026 Minutes (17:32)That the minutes of the Place Scrutiny Committee on 24 March 2026 and 19 May 2026 be signed as a correct record of th... Decided Open
16 Jun 2026 Work Plan (19:47)i. Noted that the Committee work plan. Reason: To ensure the Committee maintains a programme of work. Noted Open