Bus Priority in York City Centre: The Rougier Route

Approved Executive 11 papers

AI summaryCity of York Council Executive allocated £2m of BSIP1 funding and £350k of YNYMCA Bus Grant funding for an experimental Rougier Route, with initial exemptions for buses, emergency services, Blue Badge holders and Hackney Carriages. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedJourney time and reliability improvements; benefits and disbenefits fully evaluated. [D]
Money£2m and £350k [D]BSIP1 funding and YNYMCA Bus Grant funding. [D]
What happens nextImplement route experimentally [D]Authority is delegated for implementation and traffic order changes. [D]
Who it affectsBus users and exemptions [D]Buses, emergency services, Blue Badge holders and Hackney Carriages. [D]

What was decided

The Executive allocated £2m of BSIP1 funding and £350k of YNYMCA Bus Grant funding to implement the Rougier Route on an experimental basis.

It delegated authority to the Director of City Development to implement the proposals experimentally and amend associated Traffic Regulation Orders during the trial if required. Initial exemptions are for buses, emergency services, Blue Badge holders and Hackney Carriages.

The Executive noted the petition and approved the City of York Council Parking and Moving Traffic Offences Enforcement Policy.

Why

The experimental approach is intended to deliver bus journey time and reliability improvements and allow the potential benefits and disbenefits to be fully evaluated before a permanent decision.

The delegation was intended to ensure prompt delivery. Delegating order changes allows Traffic Regulation Orders to adapt to evidence gathered during the trial.

The petition was noted so petitioners' views could be considered. The policy update was to reflect the powers the Council now holds.

What happens next

The Director of City Development will implement the Rougier Route proposals experimentally, initially allowing exemptions for buses, emergency services, Blue Badge holders and Hackney Carriages.

The Director of City Development may amend the conditions of associated Traffic Regulation Orders during the trial if required.

The trial will deliver bus journey time and reliability improvements and evaluate potential benefits and disbenefits before a permanent decision is made.

The money

  • £2m BSIP1 funding for experimental Rougier Route implementation
  • £350k YNYMCA Bus Grant funding for experimental Rougier Route implementation

Options considered

  • Chosen: Implement the Rougier Route on an experimental basis. It is intended to improve bus journey time and reliability and allow the potential benefits and disbenefits to be fully evaluated before a permanent decision.

Implications

  • Financial: The experimental route is allocated £2m of BSIP1 funding and £350k of YNYMCA Bus Grant funding.
  • Legal: The Director of City Development may implement the proposals and amend associated Traffic Regulation Orders during the trial if required.
  • Risk: Potential benefits and disbenefits will be fully evaluated before a permanent decision is made.
  • Other: The initial exemptions cover buses, emergency services, Blue Badge holders and Hackney Carriages.
  • Other: The trial is intended to improve bus journey time and reliability.
  • Legal: The approved enforcement policy is updated to reflect the Council's current powers.
  • Other: The Executive has noted the petition.

Who and where

  • Bus users
  • Emergency services
  • Blue Badge holders
  • Hackney Carriages
  • Petitioners

Timeline

  • 2026-07-07: The Executive made the Rougier Route funding, delegation, petition and policy decisions.
  • Initially: Exemptions apply to buses, emergency services, Blue Badge holders and Hackney Carriages.
  • During the trial period: The Director of City Development may amend associated Traffic Regulation Orders if required.
  • Prior to a permanent decision: The trial will evaluate the potential benefits and disbenefits.

Plain English for the jargon

  • BSIP1: Funding allocated for experimental Rougier Route implementation. [D]
  • YNYMCA Bus Grant: Funding allocated for experimental Rougier Route implementation. [D]
  • Traffic Regulation Orders: Orders associated with the route whose trial conditions may be amended if required. [D]
  • Blue Badge holders: People initially exempt from the route proposals. [D]
  • Hackney Carriages: Vehicles initially exempt from the route proposals. [D]
  • Rougier Route: The experimental bus priority route approved for implementation. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

Resolved (unanimously): That Executive a) Allocates £2m of BSIP1 funding and £350k of YNYMCA Bus Grant funding to implement the Rougier Route on an experimental basis. Reason: To deliver bus journey time and reliability improvements and to enable the potential benefits and disbenefits to be fully evaluated prior to a permanent decision being made. b) Delegates authority to the Director of City Development to implement the Rougier Route Proposals on an experimental basis allowing exemptions initially for buses, emergency services, Blue Badge holders and Hackney Carriages. Reason: To ensure expedient delivery of the project. c) Delegates authority to the Director of City Development to amend the conditions of the Traffic Regulation Orders associated with the Rougier Route project during the trial period if required. Reason: To allow the Traffic Regulation Orders to adapt to evidence gathered during the trial period. d) Notes the contents of the petition. Reason: To consider the views of petitioners when making a decision on the Rougier Route project. e) Approves the City of York Council Parking and Moving Traffic Offences Enforcement Policy. Reason: To update the policy in line with the powers the Council now holds.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 20 pages

Meeting: Executive Meeting date: 7 July 2026 Report of: Garry Taylor, Director of City Development Portfolio of: Councillor Kate Ravilious, Executive Member for Transport

Bus Priority in York City Centre: The Rougier Route Subject of Report 1. The report presents the results of the public consultation into bus priority in York City Centre and requests approval to deliver bus priority on George Hudson Street and Micklegate (between the Micklegate / George Hudson Street and Micklegate / Skeldergate / North Street / Ouse Bridge junctions) on an experimental basis. The report also responds to a petition requesting that Rougier Street and Ouse Bridge remain open to vehicles.

2. The report includes an update to the Council’s Parking and Moving Traffic Offences Enforcement Policy. The policy has been updated to reflect the moving traffic offence powers that the Council now holds.

Benefits and Challenges 3. The key benefit the project seeks to achieve is to reduce bus journey times and improve service reliability. Reliability of buses is a critical factor in passenger satisfaction and directly impacts how competitive buses are compared to driving a car. If a bus route is not sufficiently reliable then people either catch earlier buses than they would optimally like to or choose to travel in different ways. 69% of applicable respondents told us that they have had to catch an earlier bus than they needed to because they were worried they might be late. 4. Recent research commissioned by the Confederation for Passenger Transport1 confirms that in bus journey time is a significant influence on patronage. They conclude that bus patronage can be expected to rise by 1.3% for every minute saved in journey time. A further benefit of reducing bus journey times and improving reliability is that the time saved can be invested in network improvements – expanded routes or better frequency of service.

5. Service 4 real time bus performance data between Clifford Street and the Rail Station has been analysed to understand current journeys times and potential time savings suggest almost six minutes could be saved Monday to Thursday and nearly 11 minutes on Friday. A reliable route through the main City Centre bus corridor will provide journey time savings and reliability benefits for passengers on the 1070 buses that operate on the proposed route.

6. The project will complement other existing bus-based initiatives. Extended Park and Ride hours, overnight parking at Park and Ride sites, the £1 bus fare for under 19s, All York Family ticket price reductions and marketing work will all achieve more if more buses run on time and journey times are shorter. It is important to be able to help the bus industry get into the positive spiral of more reliable buses, shorter journey times, reduced operating cost, more passengers and consequently more investment rather than the negative alternative.

7. The primary concern that has been expressed during the consultation is traffic displacement. A traffic modelling exercise has been undertaken using the Council’s strategic transport model to help inform whether the trial should be recommended for progression. There are some limitations with the strategic model but it provides a good general indication of whether any significant issues would likely occur. A report is included at Annex C outlining the results of the modelling work.

8. The modelling shows that, across the city, 92% of journeys in the morning peak were in practical terms unchanged with the project in place – within 30 seconds quicker or slower than their existing time. In the afternoon this is true for 71% of trips. In the morning

1 The Case for Faster Buses peak only 3% of trips in the city are expected to increase by more than a minute and in the afternoon 9%.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bus Priority in York City Centre: The Rougier RouteReport 20 pages DownloadRead as text
PDF
Item 10: Bus Priority in York City Centre: The Rougier Route: Annex AAppendix 1 pages Download
PDF
Item 10: Bus Priority in York City Centre: The Rougier Route: Annex BAppendix 58 pages Download
PDF
Item 10: Bus Priority in York City Centre: The Rougier Route: Annex CAppendix 25 pages Download
PDF
Item 10: Bus Priority in York City Centre: The Rougier Route: Annex DAppendix 28 pages Download
PDF
Item 10: Bus Priority in York City Centre: The Rougier Route: Annex EAppendix 16 pages Download
PDF
View as HTML (19./3) 135 KBAppendix 135 KB Copy on its way
PDF
View as HTML (19./4) 130 KBAppendix 130 KB Copy on its way
PDF
View as HTML (19./5) 201 KBAppendix 201 KB Copy on its way
PDF
View as HTML (19./6) 88 KBAppendix 88 KB Copy on its way
PDF
View item 19. as HTML 124 KBReport 124 KB Copy on its way

At this meeting

Whole meeting

Who was there

7 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneCommittee Member, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, apologies
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbVice-Chair, present

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open