City of York Council
Audit and Governance Committee, Wednesday 16 September 2026 at 5.30pm

Contract management: major project delivery (17:47)

Noted Finance 4 papers

AI summaryThe Audit and Governance Committee noted progress on the audit response action plan, so members could be confident it was being delivered [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe committee noted progress on the audit response action plan [D].
MoneyNot stated
What happens nextNot stated
Who it affectsMajor project delivery [P2]Committee members sought confidence in plan delivery [D].

What was decided

The committee noted progress in delivering the action plan developed in response to the audit [D].

The action plan was provided as Annex A [P4]. Report P4

Why

To give members confidence that the action plan was being delivered [D].

Implications

  • Risk: The committee sought confidence that the audit response plan was being delivered [D].

Who and where

  • Audit and Governance Committee members

Timeline

  • Tuesday, 15 July 2025, 4.30 pm: Executive agenda [P3]. Report P3
  • Wednesday, 28 January 2026, 5.30 pm: Audit and Governance Committee agenda [P1]. Report P1
  • March 26: Audit and Governance Committee agenda [P2]. Report P2
  • 2026-09-16: Audit and Governance Committee considered the decision [D].

Plain English for the jargon

  • Action plan: The plan developed in response to the audit [D].
  • Assured: Members were satisfied that the plan was being delivered [D].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

i. Noted the progress in delivering the action plan developed in response to the audit. Reason: To enable members to be assured that the action plan is being delivered.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Audit and Governance Committee, 5 pages

Meeting: Audit and Governance Committee Meeting date: 16/09/2026 Report of: Director of City Development Portfolio of: Cllrs Lomas Executive Member for Finance, Performance, Major Projects, Human Rights, Equality and Inclusion

Audit and Governance Committee Report: Contract management: major project delivery Subject of Report 1. This report has been prepared to provide the committee with the updated action plan which resulted from the Contract management: major project delivery final audit report 2024/25.

Policy Basis

2. The work of internal audit is governed by the Accounts and Audit Regulations 2015, and the Global Internal Audit Standards in the UK Public Sector (GIAS UK Public Sector).

3. In accordance with these standards, outcomes from internal audit work are presented to the Audit and Governance Committee.

Recommendation and Reasons 4. The Audit & Governance Committee is asked to:

- Review the progress in delivering the action plan developed in response to the audit. Reason To enable members to be assured that the action plan is being delivered.

Page 1 of 5 Background

5. During 2024/25, Veritau commenced work on an audit of the council’s contract management arrangements for its major capital projects. Work continued into 2025/26, following a request for additional work from the Director of Finance and to allow the council’s Director of City Development to contribute to the audit.

6. On 16 January 2026, following discussions with senior management about the content of the report and actions to address identified weaknesses, the final audit report was issued.

7. A Limited Assurance opinion was reached. This means that Veritau has assessed there to be significant gaps, weaknesses or non-compliance. It also means that improvement is required to governance, risk management and control arrangements to effectively manage risks to the achievement of objectives in the area audited. 8. The purpose of the audit was to provide assurance that: a) there is a contract brief which clearly set out the work required

b) meetings are held with the contractor to manage delivery of the project

c) there is a verification process to confirm that work is completed to the required standard and within timescale

d) invoices received are accurate for the work that has been done.

9. In order to provide this assurance, Veritau reviewed the main construction contracts relating to three projects. These were York Station Gateway Package 2 ‘Highways Scheme’ (extant), Tadcaster Road (completed), and the Housing Delivery Programme (completed).

10. The focus of the audit was on how the main construction contracts for the three projects had been managed. However, in the case of York Station Gateway, we also evaluated officers’ own review into the circumstances relating to the significant overspend and delays with the project. This was the additional work requested by the Director of Finance, mentioned in paragraph 5.

Page 2 of 5 11. A total of four findings were made in the report. The key finding, and the one the led to the Limited Assurance opinion being reached, relates to York Station Gateway. Veritau assessed this finding as ‘critical’, meaning that it represents a fundamental system weakness, which presents unacceptable risk to the system objectives and requires urgent attention by management.

12. The York Station Gateway finding is made up of separate but interrelated parts, as follows:

a) entering the construction contract ‘at risk’, before legal agreements with statutory undertakers had been sufficiently progressed

b) costs incurred as a result of changes during project delivery

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Action PlanAppendix A 11 pages Download
PDF
Contract management: major project delivery (17:47)Report 5 pages DownloadRead as text
PDF
View as HTML (22./2) 116 KBAppendix 116 KB Copy on its way
PDF
View item 22. as HTML 34 KBReport 34 KB Copy on its way

At this meeting

Whole meeting

Who was there

8 of 10 attended
AH
Councillor Andrew HollyerChair, present
JR
Councillor Jason RoseVice-Chair, present
JB
Councillor Jane BurtonCommittee Member, present
TF
Councillor Tony FisherCommittee Member, present
JC
Councillor Jo ColesCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
MB
Myles BinneyIndependent Person, present
MW
Matt WilliamsIndependent Person, present
PL
Patrick LookerOfficer, expected
MP
Councillor Michael PavlovicCommittee Member, expected

On this subject at York

Search all
  1. Contract management: major project delivery (17:47)This decision
  2. Financial Close for the Long Term Waste Management Service ContractAgreed
  3. Award of Long Term Waste Management Service ContractAgreed
  4. Supplier & Contract Management System (SCMS)Noted
  5. Supplier & Contract Management System (SCMS)Deferred

More from York Audit and Governance Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 Exclusion of Press and Public (17:38)That the press and public be excluded from the meeting during consideration of Annexes 2-8 to Agenda Item 11, Interna... Decided Open
21 Oct 2026 Minutes & Action Log (17:39)That the minutes of the meeting held on 22 July 2026 be approved and the minutes of the meeting held on 16 September ... Approved Open
21 Oct 2026 Auditor Progress Report (17:42)i. Noted the matters set out in the Audit Progress report presented by the external auditor. Reasons: To ensure the p... Noted Open
21 Oct 2026 Treasury Management 2026/27 Mid-Year (Quarter 2) report and review of Prudential Indicators (17:54)i. Noted the Treasury Management Mid-Year Report and Review of Prudential Indicators 2026/27 at Annex 1. Reason: That... Noted Open
21 Oct 2026 Suggested Constitutional Changes - Revised Article 13 (18:09)i. Endorsed the adoption of the changes to Article 13 of the Constitution and recommended to Full Council for approva... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies