The Joint Strategic Committee noted the progress made by the Joint Officer and Member Board in relation to governance arrangements for overseeing the Community Infrastructure Levy (CIL); agreed the Infrastructure Investment Plan (IIP) which set out the priorities of infrastructure projects to receive CIL funding over the next three years; and agreed the formal revised draft CIL Charging Schedule prior to undertaking a public consultation exercise. Call In: The call-in deadline for this decision will be 5.00pm on 19 June 2020.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
Worthing Borough Council has introduced a Community Infrastructure Levy (CIL) to allow funds to be raised from developers to pay for infrastructure that is needed to support growth. The Council adopted the Charging Schedule for CIL in February 2015 and implementation of the levy commenced in October 2015. The Council has overarching responsibility for the allocation of CIL monies and reporting the amount of money collected and spent. This report provides an update on progress made by the Joint Officer and Member Board (JOMB) for CIL Governance and:
❏ provides an update on the current level of CIL funding collected; ❏ sets out the Infrastructure Investment Plan (formerly called the Infrastructure Business Plan) which will set out priorities for the spending of CIL; ❏ sets out the need for a formal review of the CIL charging schedule based on the recent recommendations of the Council’s Consultants. 2. Recommendations
2.1The Committee is recommended to:
● Note the progress made by the Joint Officer and Member Board in relation to governance arrangements for overseeing the Community Infrastructure Levy (CIL); ● Agree the Infrastructure Investment Plan (IIP) which will set out the priorities of infrastructure projects to receive CIL funding over the next three years. ● Agree to the formal revised draft CIL Charging Schedule prior to undertaking a public consultation exercise.
3. Context
3.1The CIL Regulations 2010 (as amended), allow local planning authorities to set a CIL charge on some developments in order to contribute toward the cost of the infrastructure required to support the cumulative impact of growth and development in an area. Worthing Borough Council (WBC) adopted its CIL charging schedule in February 2015, with implementation of the levy commencing in October 2015.
3.2The charging schedule must strike an appropriate balance between the desirability of funding infrastructure and the potential effects on the viability of development. It is generally considered that a review of a charging schedule should be considered within 5 years of implementation, to reflect changes to key government policy and guidance, as well as changing market conditions.
3.3CIL is now the main way in which WBC collects contributions from developers for infrastructure provision in Worthing. There is, however, still a role for the use of S106 planning obligations, particularly for securing affordable housing provision and some site specific requirements.
3.4As charging authority, Worthing BC has the responsibility for managing, monitoring and reporting on CIL. Although the CIL ‘pot’ is growing, it is accepted that CIL will not generate enough funds to completely cover the cost of new infrastructure needed to fully support the planned growth. It is clear that there will be many competing demands on CIL funds which means that it is important that a clear and justified process for the spend and prioritisation of CIL is established. 3.5 To oversee this process, a Joint Officer and Member Board (JOMB) has been established (see JSC report 01/02/2018). JOMB oversees the governance around the spend of CIL which includes the development of the Infrastructure Investment Plan (previously referred to as the Infrastructure Business Plan) which sets out the priority of infrastructure delivery over a next three year period.
3.6Although CIL has been in place in Worthing since 2015, funds are only now starting to grow as payment becomes due on commencement of liable development. To date, a total of £812k has been collected through CIL. The table below sets out CIL income receipts at the end of March 2020 and how the money has been split in line with the CIL Regulations and governance arrangements previously agreed by JOMB and JSC:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.