Joint Strategic Committee, Tuesday 9 June 2020 at 6.30pm

Buckingham Multi-Storey Car Park Regeneration Scheme

Agreed Committee 1 paper

Joint Strategic Committee agreed this item on Tuesday 9 June 2020. Below is the council's own wording, with the papers it was decided on.

ItemJSC1620-21

Resolved

The Joint Strategic Committee agreed a budget virement of £800,000 from the capital allocation for High Street MSCP to the Buckingham MSCP project budget. This would enable the regenerative benefits and improvement options identified, to be incorporated into the Buckingham MSCP scheme. Call In: The call-in deadline for this decision will be 5.00pm on 19 June 2020.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1. Purpose ● To request that Members agree to the recommended virement to enable the re-profiling of the programme of works for Buckingham and High Street Multi-Storey Car Park refurbishment projects, allowing capital funds of £800,000 to be brought forward for use into the 2020/21 budget year.

2. Recommendations ● The Joint Strategic Committee is recommended to agree a budget virement of £800,000 from the capital allocation for High Street MSCP to the Buckingham MSCP project budget. This will enable the regenerative benefits and improvement options identified, to be incorporated into the Buckingham scheme. 3. Context

3.1Grafton multi-storey car park will be demolished as part of proposed redevelopment plans for the whole site. This has an indicative timescale of between 2 to 4 years. When Grafton is demolished there will be a need for a quality parking offering closeby to serve Worthing town centre.

3.2The Joint Strategic Committee on 6 November 2018 authorised the retention and refurbishment of High Street and Buckingham Road multi-storey car parks.

3.3The retention and refurbishment of Buckingham Road MSCP will fulfil the Council's aims and contribute to Worthing’s economic regeneration programme as set out in the Worthing Core Strategy, Worthing Investment Prospectus, the Platforms for our Places document and Capital Investment Programme for Worthing Borough Council and the Joint Strategic Committee.

4.0Issues for consideration

4.1The upcoming closure of Grafton multi-storey car park and loss of approximately 430 spaces will place more importance on the need for the Council to provide a quality parking offering closeby in the town centre.

4.2This project will enable important structural and health and safety improvement works to be carried out which do not form part of the routine maintenance schedule.

4.3Buckingham MSCP needs capital investment if the lifespan and value of the asset is to be extended.

4.4The Council is responsible for the health and safety of all users of its car parks. Improving the condition of Buckingham Road MSCP will deliver an enhanced customer experience and result in a greatly improved, quality parking offering to residents, businesses and visitors.

4.5The project is overseen by an officer project board comprising representatives of the Major Projects & Investment Team, Parking, Technical Services and Finance. The board considered a number of options including doing the minimum works required for health & safety and structural reasons; doing a smaller refurbishment project to improve customer experience; and a third maximum version which included cladding and a more extensive refurbishment to greatly improve the customer experience.

4.6The western end of the town centre has a programme of works that will tie together to make a significant change to the wider environment and experience for visitors. The redevelopment of Grafton car park site will provide new commercial and residential units along Montague Street, while the proposed pedestrianisation of Portland Place will provide an opportunity for a new food and beverage destination similar to how Warwick Street anchors the eastern end of the town centre. Furthermore, Buckingham Road car park will likely become more popular when the Grafton car park is demolished, becoming the main short-term car park serving the western side of the town centre. Given these considerations, it is critical that the chosen option reflects the long term aspirations for regeneration of this part of Worthing Town Centre and that the scheme will act to reinforce these other interventions to improve the area. It is therefore considered that the preferred option should include a form of cladding to improve the character and appearance of the area, and contribute to the wider programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Buckingham Multi-Storey Car Park Regeneration SchemeReport 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
NT
Neil TerrySecretary, expected
DH
Councillor Daniel HumphreysWorthing Chairman, present
NP
Councillor Neil ParkinAdur Chair, present
AD
Councillor Angus DunnAdur Vice-Chair, present
KJ
Councillor Kevin JenkinsWorthing Vice-Chair, present
CA
Councillor Carson AlburyAdur Member, present
BB
Councillor Brian BoggisAdur Member, present
EC
Councillor Edward CrouchWorthing Member, present
EE
Councillor Emma EvansAdur Member, present
DH
Councillor Dr Heather MercerWorthing Member, present
DS
Councillor David SimmonsAdur Member, present
ES
Councillor Elizabeth SparkesWorthing Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Buckingham Multi-Storey Car Park Regeneration SchemeThis decision
  2. Governance Processes and Buckingham Road Multi-Storey Car Park RefurbishmentNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies