The Joint Strategic Committee authorised the Director for the Economy to undertake the procurement for the remediation contractor and to award that contract and any recommended contracts arising from the works as necessary to support and enable the remediation works at Decoy Farm, the costs for which, shall be met from the budgets set out in the report. Call In: The call-in deadline for this decision will be 5.00pm on 19 June 2020.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
● To authorise the Director for the Economy to undertake the procurement for the remediation contractor and to award that contract and any recommended contracts arising from the works as necessary to support and enable the remediation works at Decoy Farm, the costs for which shall be met from the budgets set out below. 3. Context
3.1At over 7ha, Decoy Farm is the most significant opportunity to deliver new employment floorspace for Worthing and one of the last remaining large-scale development opportunities in Coastal West Sussex. Our planning framework has always highlighted Decoy Farm’s potential as an opportunity for economic growth, but has been equally clear on the need to address some key constraints:
“The land was formerly a landfill area and there is clear evidence of existing contamination and flooding problems. Due to these constraints and poor accessibility, this site has remained undeveloped and is in need of significant investment to realise its full potential.” (pg 70, Adopted Core Strategy, April 2011).
3.2Made possible by the funding from the Coast to Capital Local Enterprise Partnership, the Council have made significant progress towards the start of on site remediation works, which will finally unlock this site for development 40 years after lying dormant.
4. Issues for consideration
4.1Resolving historic contamination.
4.2The Decoy Farm project is progressing at pace. With our focus on remediation, our team have undertaken the following:
● Completion of the Preliminary Ecological Appraisal and associated surveys. This has informed detailed discussions and reached the conclusion that the remediation of the landfill plateaus does not constitute Environmental Impact Assessment (EIA) development. A Screening Request has been submitted to the LPA for their consideration, however, we are continuing with the ecological surveys. ● The preliminary archaeological assessment and topographical surveys have been completed and the Ground Investigations (GI) team are now on site. As well as updating the GI data from 2014 they are also installing continuous gas monitoring. This information will be used directly as part of the work information for the remediation contractor. ● Applications have been made to the EA for flood modelling and we have liaised with the Sompting Estate as they have more recent modelling. We are working with WSCC to assist the transport assessment, modelling and travel planning. 4.3 Timetable.
4.4The remediation works are timetabled to commence on site in August 2020. In order for this to take place we shall be continuing with the preparatory works. A high level programme is attached at Appendix 1. Over the next year a significant amount of work will take place to get to the point of a remediation site suitable for industrial development. This includes:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.