The Joint Strategic Committee i. agreed to WBC taking on the project management and delivery responsibility of Portland Road Public Realm work, supported by WSCC (both financially and by it’s officer time); ii. delegated authority to the Director for the Economy to approve a direct award under the Eastern Shires Purchasing Organisation (ESPO) framework to award a contract to Project Centre Consultants, to act as the project manager for WBC to deliver the public realm works at Portland Road on behalf of the Growth Board; iii. delegated authority to the Director for the Economy, in consultation with the Executive Member for Regeneration and WSCC, to approve and award a contract for the construction work required to deliver the public realm project subject to the development of a procurement strategy and the outcome of a compliant procurement process; iv. delegated authority to the Director for the Economy to enter into the C2C Funding Agreement; and v. approved the creation of a budget of £3.697m (to include the WSCC funding and the C2C funding) within the capital programme fully funded by external grants and contributions. Call In: The call-in deadline for this decision will be 5.00pm on 19 June 2020.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1The purpose of this report is to update Members on the Portland Road scheme and authorise Worthing Borough Council (WBC) to act as the lead authority for West Sussex County Council (WSCC) and the delivery body for Coast to Capital LEP (C2C) on the terms set out in this report.
1.2To present the rationale for WBC delivering the project and the parallel approach being undertaken by WSCC in order for the monies to be used by WBC for the purposes of Portland Road.
1.3Confirm that WSCC will continue to design and deliver the public realm works at Railway Approach (Teville Gate) in consultation with WBC.
1.4Confirm WBC has been offered external funding through Local Growth Funding (LGF) of £697,000 from the Coast to Capital LEP (C2C) to support the costs of the Portland Road scheme. 2. Recommendations
2.1To agree to WBC taking on the project management and delivery responsibility of Portland Road Public Realm work, supported by WSCC (both financially and by it’s officer time).
2.2To provide delegated authority to the Director for the Economy to approve a direct award under the Eastern Shires Purchasing Organisation (ESPO) framework to award a contract to Project Centre Consultants, to act as the project manager for WBC to deliver the public realm works at Portland Road on behalf of the Growth Board.
2.3To delegate authority to the Director for the Economy, in consultation with the Executive Member for Regeneration and WSCC, the authority to approve and award a contract for the construction work required to deliver the public realm project subject to the development of a procurement strategy and the outcome of a compliant procurement process.
2.4To delegate to the Director for the Economy the authority to enter into the C2C Funding Agreement.
2.5To approve the creation of a budget of £3.697m (to include the WSCC funding and the C2C funding) within the capital programme fully funded by external grants and contributions.
3. Background and Context
3.1The Adur and Worthing Growth (A&WG) Deal signed in March 2017 identified up to 8 public realm schemes aimed at supporting the regeneration of Worthing town centre. The agreed programme included initial funding from WSCC Capital Programme (£5m) with the remainder being sourced through developer contributions, to include Community Infrastructure Levy (CIL); planning obligations (Section 106) and grants to support delivery of later phases of the programme.
3.2The delivery of the Worthing Public Realm programme if overseen by a joint Member Board, namely the Public Realm Board. The Public Realm Board is a joint WBC and WSCC Board with Member representation from both parties. The Board is supported by Officers from both parties. 3.3 The Worthing Public Realm programme provides a significant opportunity to revitalise the public spaces through a people-centred design approach. The Portland Road scheme, and schemes thereafter, have a number of social and economic benefits:
● Establishing new destinations and arrival zones ● Alignment and enhancement of routes to create town centre circuits ● Ability to design inclusive and welcoming spaces ● Improves and enhances sustainable travel options ● Responds to key stakeholders through direct consultation
3.4The Worthing Public Realm Board examined all 8 public realm schemes to identify a prioritisation matrix. Based on former evidence (including the Worthing Investment Prospectus in 2016) Portland Road and Railway Approach (Teville Gate) were highlighted as key interventions to support and deliver economic growth for Worthing town centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.