That the Joint Strategic Committee 1. Noted the work undertaken since the emergency closure of Grafton multi-storey car park; 2. Noted that a detailed report had been commissioned which would inform the feasibility and cost of making the current structure safe for re-opening to the public. This report would be key to informing the next steps in determining the future of the site and the associated timescales. 3. That In parallel to the commissioning of the report at paragraph 2.3 above, and given the need to progress a solution to the Grafton issues as quickly as possible, delegated authority to the Director for Economy, Regeneration & Climate to:- a) Proceed with the relaunch of the marketing of Grafton Multi-Storey car park and adjoining council-owned properties as detailed in this report set out at paragraphs 4 & 5; b) Sign off and approve the terms of the Marketing Brochure in consultation with the Worthing Cabinet Member for Regeneration. 4. Noted that a further updating report would be presented to the Joint Strategic Committee on the findings of the feasibility report and the outcome of the marketing process.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. To provide the committee with an update following the emergency closure of Grafton in terms of:
1.1.1. The works completed to close the carpark to the public 1.1.2. Engagement with stakeholders, including Knightsbridge House residents and the provision of alternative parking 1.1.3. Measures to mitigate the impact of the temporary closure of High Street multi-storey car park to accommodate the Worthing Heat Network works 1.1.4. Progress on the redevelopment of Grafton multi-storey car park.
2. Recommendations
2.1. The Committee is asked to:-
2.2. Note the work undertaken since the emergency closure of Grafton multi-storey car park; 2.3. Note that a detailed report has been commissioned which will inform the feasibility and cost of making the current structure safe for re-opening to the public. This report will be key to informing the next steps in determining the future of the site and the associated timescales.
2.4. In parallel to the commissioning of the report at paragraph 2.3 above, and given the need to progress a solution to the Grafton issues as quickly as possible, members are asked to delegate authority to the Director for Economy, Regeneration & Climate to:-
a) Proceed with the relaunch of the marketing of Grafton Multi-Storey car park and adjoining council-owned properties as detailed in this report set out at paragraphs 4 & 5;
b) Sign off and approve the terms of the Marketing Brochure in consultation with the Worthing Cabinet Member for Regeneration.
2.5Members are asked to also note that a further updating report will be presented to the Joint Strategic Committee on the findings of the feasibility report and the outcome of the marketing process. 3. Context
3.1 On 2 June 2025 a report was presented to this committee which advised members of the emergency closure of Grafton multi-storey car park on 16th May. The recommendations in the report were that:
3.1.1 The committee be asked to note the emergency closure and asked to agree to continue with the closure for the reasons set out in the report;
3.1.2 The committee noted the actions taken to secure the site, urgently investigate the issues, and provide alternative arrangements for those that required access;
3.1.3 To recommend that the committee receive a report at this July meeting outlining the plans and recommendations to progress the regeneration of the Grafton site.
3.2 This is the follow on report which sets out the actions taken since the closure of the site and the progress on the plans to redevelop the site. 4. Progress on making site safe and mitigations
4.1 Since the emergency closure of the Grafton on Friday 16th May 2025, officers have been progressing a number of workstreams:
4.1.1 Physically making the site secure and safe whilst it is closed pending further investigation work. It is anticipated that the site will have to be closed for at least several months. These works comprise improved fencing to prevent unauthorised access and placing safety netting and scaffolding in areas which still require limited accessibility.
4.1.2 Commissioning HOP Consulting (civil engineers) and MacConvilles (structural surveyors) to carry out a more detailed assessment of the work that would be required to make the car park safe to enable it to be reopened, and the associated cost. This will inform whether the site can be put back into use before it is redeveloped. Their report is anticipated the week commencing July 21st 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.