That the Joint Strategic Committee 1. Noted the progress on the Phase 1 Capital Maintenance Project; 2. Noted the inclusion of the Worthing Borough Council contribution of £200k included in the current Capital Programme as match-funding for the project and agreed its release at the appropriate time. 3. Agreed an increased contribution of £100k up to £200k from the Community Infrastructure Levy (CIL) ‘other agencies’ pot funding in support of the project and approved an increase in the capital budget for the additional CIL £100k contribution and its release to the Environment Agency at the appropriate time. 4. Delegated authority to the Assistant Director of Place and Economy, in consultation with the Executive Member for Environmental Services, to enter into any necessary contract, grant funding agreement, or make any required investment under the council’s Treasury Management Policy to the Environment Agency, to enable the interventions specified in this report, providing the spend does not exceed the council budget contribution summarised under 8.2.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. This report provides an update to members on the progress made on the Environment Agency (EA) led Phase 1 Capital Maintenance Project to repair and extend the life of existing timber groynes in the town centre area, as part of a long-term coastal defence plan.
1.2. To acknowledge the importance of this work in relation to Worthing Borough Council’s wider commitment to supporting and developing the seafront and town centre.
2. Recommendations
2.1. The Joint Strategic Committee is asked to:
2.1.1. Note the progress on the Phase 1 Capital Maintenance Project. 2.1.2. Note the inclusion of the Worthing Borough Council contribution of £200k included in the current Capital Programme as match-funding for the project and agree its release at the appropriate time.
2.1.3. Agree an increased contribution from £100k to up to £200k from the Community Infrastructure Levy (CIL) ‘other agencies’ pot funding in support of the project and approve an increase in the capital budget for the additional CIL £100k contribution. Agree its release to the EA at the appropriate time.
2.1.4. Agree to delegate authority to the Assistant Director of Place and Economy, in consultation with the Executive Member for Environmental Services, to enter into any necessary contract, grant funding agreement, or make any required investment under the council’s Treasury Management Policy to the Environment Agency, to enable the interventions specified in this report, providing the spend does not exceed the council budget contribution summarised under 8.2.
3. Context
3.1 Worthing Borough Council (WBC) is the Coastal Protection Authority under the Coast Protection Act 1949 for the Worthing frontage. In its simplest terms, WBC has the responsibility for managing flooding and coastal erosion from the sea. The legislation does not make it a statutory requirement to defend the coast but most coastal authorities choose to be active in coastal protection.
3.2 In the Shoreline Management Plan (SMP - covered in three units, Shoreham Harbour to Worthing 4D15, Worthing to Goring-by-Sea 4D16 & Ferring/ Kingston 4D17), the strategic approach for managing the risk from coastal flooding and erosion over the short to long term for Worthing is to ‘Hold the Line’. ‘Holding the line’ means maintaining and upgrading the coastal defences to prevent erosion and flooding. The ‘line’ is the southern edge of the promenade and coastal footpaths. 3.3 Worthing’s frontage is 7.8km long from Sea Lane in Ferring in the west to Western Road in the east and features 144 timber groynes, 11 rock groynes, 3 rock revetments and a number of splash walls.
3.4 The Department for Environment, Food & Rural Affairs (Defra) has overall national responsibility for policy on Flood and Coastal Erosion Risk Management (FCERM) in England. Defra provides funding through FCREM grants (Grant in Aid - GiA).
3.5 The EA supervises and works with other organisations to manage the risk of flooding and coastal erosion in England. The EA manages the FCERM GiA funding distribution.
3.6 A joint collaboration between the EA and WBC was agreed to progress a two-phased approach for the Worthing frontage. Phase 1 is a capital maintenance project to extend the life of the timber groyne field between Seaview Road and Brooklands for a further ten years and Phase 2 (following the delivery of Phase 1) is to work in partnership with the EA to develop a long-term strategy for the whole Worthing frontage. This paper substantively relates to Phase 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.