The Joint Strategic Committee 1. Noted the financial paragraphs in the report and approved an increase of the capital budget for the project by £574,690 to enable completion of the project. 2. Delegated authority to the Assistant Director for Place & Economy in consultation with the Cabinet Member for Regeneration, Leader of Worthing Borough Council and Chief Financial Officer to agree to any reasonable costs within the available budget to ensure the development contract is completed. 3. Noted that a fully detailed project review report will be presented to the appropriate committee for project scrutiny as soon as practicable following the conclusion of all contract agreements and Worthing Integrated Care Centre occupation.
Word for word from the decision Adur & Worthing published for this meeting.Source: democracy.adur-worthing.gov.uk
1.1. To update the committee on progress towards tenant occupation of the Worthing Integrated Care Centre, and the technical work to resolve outstanding issues that have prevented occupation, in particular issues with the water management system and the presence of legionella.
1.2. To set out the additional costs being borne by the Council as a result of the delay to occupation, and request the release of the necessary capital and revenue funds, including contingency.
1.3. This report follows on from the report raised at the Joint Strategic Committee on 3 Apr 2025, focussing on the work needed and anticipated to open the building and close out the project.
2. Recommendations
2.1. Recommendation One
2.1.1. To note the financial paragraphs in this report and to approve an increase of the capital budget for the project by £574,690 to enable completion of the project. 2.1.2. To delegate authority to the Assistant Director for Place & Economy in consultation with the Cabinet Member for Regeneration, Leader of Worthing Borough Council and Chief Financial Officer to agree to any reasonable costs within the available budget to ensure the development contract is completed.
2.1.3. As reported previously - To note that a fully detailed project review report will be presented to the appropriate committee for project scrutiny as soon as practicable following the conclusion of all contract agreements and Worthing Integrated Care Centre occupation.
1. Background
1.1. The last report was taken to the Worthing Joint Strategic Committee on 3 Apr 2025. That report provided Members with details surrounding the WICC’s issues with the water system and the actions to resolve this, and the funding required to meet remaining delivery requirements.
1.2. As set out in the April report, whilst the building was signed off as ready for occupation on 3rd December 2024, having achieved negative tests for legionella, a sample taken on December 9th proved positive, leading to tenants withdrawing their agreement to enter into leases and to occupy.
1.3. During January and February, specialist consultants were commissioned via Savills (Worthing Borough Council’s appointed managing agent) to investigate the issues with the water management system and provide their findings and recommendations. At the council’s cost, this expert investigation identified concerns with water temperatures being observed and also areas of unlagged pipework leading to heat transfer between hot and cold systems. A further challenge in this period related to the building being unoccupied and therefore not being in normal operating conditions.
1.4. In March 2025, the then Director for Sustainability & Resources took leadership on the WICC project, supported by Estates, Major Projects and Legal colleagues. Urgent meetings were held with Sussex Community NHS Foundation Trust (SCFT) and Sussex Partnership NHS Foundation Trust (SPFT) to understand the issues from their perspectives.
1.5. Refreshed project governance was established in March, including
1.5.1. Water Quality & Operations Group (WBC, WSWL, tenants, contractors) 1.5.2. Defects Management Group (WBC, WSWL, tenants, contractors) 1.5.3. An Oversight Group (WBC and tenants)
1.6. With new project governance established, negotiations took place with SCFT and SPFT regarding entering into leases, and this was achieved on 31st March when leases were signed, with payment agreed to start (without conditions) after a reasonable remediation period, i.e. from July 1st 2025. This has significantly mitigated the ongoing financial exposure of Worthing Borough Council while the issues are resolved, albeit a significant element of the additional costs identified in this report pertain to the “rent free period”, April-June.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.