Agreed to approve the additional expenditure required to complete the necessary modifications to the Eilean Dhiura Ferry. 6. To request that a report by brought to the Council on 7 February 2002 with details of the re-profiling of the Transportation Capital Budget for 2002/3 in light of 5 above. (Ref: Report by Director of Finance dated 15 January 2002, report by Director of Transportation and Property Services dated 24 January 2002, submitted and report by Director of Transportation and Property Services dated 31 January 2002, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
A capital programme monitoring report has been prepared as at 30 November 2001, The projected outturn expenditure on the capital programme is expected to exceed available consent by f576,005 or 3.87%. The level of committed expenditure is El 1,996,861, which is 80.70% of the current estimated consent available. There are a number of variances to departments planned expenditure, which require noting or approval. Details of these are contained in the attached appendices.
Recommendations
2.1In order to maximise the capital consent available the committee hstruct all Directors to ensure that budgets are expended within their departments in accordance with the overall spending programme.
2.2Project accelerated from future years as detailed in Appendix 2 is noted.
2.3Approval is given to projects detailed in Appendix 3, which were not originally included in the capital programme.
2.4Area Committees note the sums available from sales of assets for future spending and consider detailed projects when the level of sums available are sufficient to justify capital projects i.e. over &6,000
3. DETAILS
3.1A capital programme monitoring report has been prepared as at 30 November 2001. A financial statement is attached at Appendix 1 which outlines for each programme area the year to date expenditure, expenditure that is legally committed and projected outturn expenditure for the full year. The report also outlines year to date and full year budget provision. Projected outturn expenditure is also compared to available capital consent.
3.2Year to date expenditure is &7,180,431, which is &2,244,004below year to date budget of &9,424,435.This represents 48.3% of the projected consent available for 2001/2002. Expenditure to 30 November 2000 amounted to &5,726,685and this represented 44.97% of the projected consent of &12,734,917available for 2000/2001.
3.3The level of committed expenditure is E1 1,996,861. This is 80.70% of the estimated available consent. 70 3.4 Projected expenditure is $15,442,042 compared to approved budget of E16,886,000. Outturn expenditure is expected to exceed available capital consent by 2576,005 or 3.87%. The approved programme assumes an over ~
commitment of f1,401,000 or 9.05%.
3.5The main areas of under expenditure relate to Administrative Buildings & Depots, Information Technology, Roads and Amenity Services. Amenity Services are working to a revised spending programme for 2001/02. However, a considerable level of expenditure on Roads is required for the last 3 months of the financial year. The Directors of Transportation & Property and the Joint Heads of Service for Information Technology should ensure that detailed plans are in place to ensure that the budget available is utilised.
3.6Slippage of 662,000 has been identified in the Cycleways Helensburgh & Lomond project, however this slippage is matched by a reduction in the ring-fenced consent.
3.7There is one project that has been accelerated from future years and details are shown in appendix 2. e 3.8 There are seven projects that were not included in the original programme. These are detailed in Appendix 3 for noting. 3.9 The income from asset sales at 30 November 2001 is $427,450. A further receipt of 64,800 has been received in December 2001 increasing the total to &432,250. Receipts totalling &23,250have been received since the 20 September 2001 when it was agreed that each area committee should receive an equal allocation of 50% of all capital receipts from the sale of assets. Therefore the sum of &2,906.25is currently available to each area committee. The asset sales are detailed in Appendix 4 for noting.
4 CONCLUSIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.