ROADS CAPITAL RECONSTRUCTION PROGRAMME 2026-27

Agreed Committee 2 papers

AI summaryArgyll and Bute's EDI Committee endorsed a £12M roads capital reconstruction programme for 2026-27, with five named funding pots and a £900K allocation to be finalised in June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFive allocations agreed, £900K to be confirmed later
Money£12M totalSplit across five budget lines for 2026-27
What happens nextJune 2026 EDI Committee meetingFinal list of unallocated £900K schemes due
Who it affectsRoad users across Argyll and ButeAll four council administrative areas

What was decided

The committee endorsed the 2026-27 capital works programme totalling £12M and approved specific allocations: £2.1M strategic schemes, £2M surface dressing, £1M vehicle safety fencing, £100K signage and £6.8M area resurfacing and drainage. Report P1, P4, P5, P7, P10

Officers will consult Elected Members on the unallocated £900K for accelerated carriageway deterioration, with a final scheme list to return to the June 2026 committee meeting. Report P9

Area Committee capital works details will be sent to individual Elected Members, and officers will consult members in Q3 of 2026-27 on the 2027-28 programme.

Why

The report sets out options for distributing the £12M roads reconstruction budget across strategic sites, safety-related treatments, and area-level resurfacing and drainage works. Report P1, P2, P10

Funding is split across four administrative areas (MAKI, OLI, B&C, H&L) on a proportional basis, with named site-specific schemes in each. Report P3, P6, P8, P11, P14, P16, P18

What happens next

Officers to engage with Elected Members on the unallocated £900K, with a final list considered at the June 2026 EDI Committee meeting. Report P9

Area Committee capital works details from Appendix 2 of the report to be forwarded to individual Elected Members.

Officers to consult members in Q3 of 2026-27 on the 2027-28 roads reconstruction programme, now that budget has been agreed.

The money

  • £12M Total capital works programme 2026-27 Report P10
  • £2.1M Strategic Schemes: A819, Islay, A8003, A817 Report P1
  • £2M Strategic Network Surface Dressing Treatment Schemes Report P3, P4
  • £1M Vehicle Safety Fencing (timber post replacement) Report P5, P6
  • £100k Road signage improvements (poles, bollards) Report P7, P8
  • £6.8M Area Resurfacing and Drainage schemes (£5.9M network + £900K accelerated deterioration) Report P9, P10
  • £900K Unallocated accelerated carriageway deterioration budget, to be confirmed at June 2026 meeting Report P9

Options considered

  • Chosen: Allocate £2.1M to strategic site-specific schemes. Completes long-running widening, drainage and surfacing schemes on A819, Islay, A8003 and A817 Report P1
  • Chosen: Allocate £2M to surface dressing across all four areas. Includes 2026-27 dressing and pre-surface dressing for 27/28 Report P3, P4
  • Chosen: Allocate £1M to vehicle safety fencing and £100K to signage. Proportionally split across four administrative areas Report P5, P6, P7, P8
  • Chosen: Allocate £6.8M to area resurfacing and drainage. Includes £5.9M network programme and £900K to be finalised after member engagement Report P9, P10

Implications

  • Financial: Total £12M capital budget endorsed for 2026-27, with £900K pending member input and final sign-off in June 2026. Report P9
  • Other: Schemes include work classed as 'Climate Change Drainage': verge clearance, ditch re-profiling and enlarged-capacity culvert replacement across all four areas. Report P11, P14, P18
  • Risk: Surface dressing allocation is split between 2026-27 and 2027-28 pre-surface dressing, tying future budget to this programme. Report P3, P4
  • Other: Islay scheme is described as 'Special Measures' addressing ferry delay and disruption 2022-2025, involving barge delivery of 5,000 tonnes of set macadam. Report P1

Who and where

  • Road users in Mid-Argyll, Kintyre and the Islands (MAKI), 31% area share Report P3, P6, P8, P11, P12, P13
  • Road users in Oban, Lorn and the Isles (OLI), 35% area share Report P3, P6, P8, P14, P15
  • Road users in Bute and Cowal (B&C), 20% area share Report P3, P6, P8, P16, P17
  • Road users in Helensburgh and Lomond (H&L), 14% area share Report P3, P6, P8, P18
  • Elected Members across all four areas, who will receive Area Committee capital works details

Timeline

  • 2026-03-19: EDI Committee endorsed £12M roads capital programme for 2026-27
  • June 2026: Final list of unallocated £900K schemes to be considered at EDI Committee Report P9
  • Q3 of 2026-27: Officers to consult members on 2027-28 roads reconstruction programme

Plain English for the jargon

  • SCRIM: Sideway-force Coefficient Routine Investigation Machine, used to measure road skid resistance
  • Surface Dressing: A road maintenance treatment spraying bitumen and laying chippings to seal and restore road surface
  • Pre-Surface Dressing (Pre SD): Preparatory patching or treatment carried out before surface dressing is applied
  • Deferred Set Macadam: A bitumen macadam mix designed to be stockpiled and laid later, used here for Islay barge delivery
  • VSF (Vehicle Safety Fencing): Vehicle safety barriers; here, replacement of timber posts on existing fences
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

Decision The Environment, Development and Infrastructure Committee: 1. endorsed the proposed capital works programme 2026-27 totalling £12M. 2. agreed to allocate: a) £2.1M Strategic Schemes; b) £2M Strategic Network Surface Dressing Treatment Schemes; c) £1M for Vehicles Safety Fencing; d) £100k Road signage improvements; and e) £6.8M Area Resurfacing and Drainage schemes. 3. requested that officers engage with Elected Members regarding the unallocated £900K and that a final list of schemes within the overall budget and programme of works for 2026/27 be considered at the June 2026 meeting of the Committee.; 4. agreed that details of each Area Committee’s Capital Works in Appendix 2 of the submitted report would be forwarded to individual Elected Members; and 5. noted that now a budget for roads reconstruction has been agreed for 2027-28, officers will carry out consultation with members in the third quarter of 2026-27 in respect of the 2027-28 programme. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated 10 March 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

2026-27 ROADS RECONSTRUCTION - CAPITAL BUDGET OPTIONS APPENDIX - 1 Part 1 STRATEGIC SCHEMES - SPECIFIC WORKS LOCATIONS £2,100,000 A819 Electric Cottage Phase 6- Completion of widening and drainage 2022-2026 , final surfacing Mid-Argyll PH6 - Final surfacing Overlay (1700m) - Lining & Signs 11,220 sq.m. £350,000 £350,000 ISLAY SPECIAL MEASURES - Ferry delay and disruption 2022-2025 Islay DEFERRED SET MACADAM by barge 5 - 6nr (5,000 Tonnes) Supply £750,000 Surfacing / laying operations - 20 full days . 44,000 sq.m. £350,000 £1,100,000 A8003 Tighnabruaich Road -Phase 9 - Completion of widening and drainge 2023-2025, Final surfacing Cowal PH9 - Full Reg & Overlay (800m) - Lining & Signs 2,500 sq.m. £300,000 £300,000 A817 Haul Road Accident Black Spot / Low SCRIM Lomond A817 From A83 JCT West12906 + 12907 + SCRIM 17,500 sq.m. £350,000 £350,000

Part 2 SAFETY RELATED STRATEGIC NETWORK TREATMENT PROGRAMME

A/ £ 2,000,000 Surface Dressing - 2026-27 £1m + £1m Pre Sd for 26/27 & 27/28 MAKI = 31% £ 620,000 Split 33/33/34 15% Mid-Argyll B8025 Moss 15,000 sq.m. £100,000 35% Kintryre Low Askomil 7,500 sq.m. £50,000 Glenbarr Loop 7,500 sq.m. £50,000 B843 Stewarton - Machrihanish ph 1 15,000 sq.m. £110,000 50% Pre SD Pre Sd 27/28 MAKI 15,500 sq.m. £310,000 £620,000 OLI = 35% £ 700,000 split 55/45 27% Oban & Lorn A819 - A85 JCT 27,000 sq.m. £189,000 23% Isles (Mull) C46 Glenbellert / Glen Aros 23,000 sq.m. £161,000 50% Pre SD Pre Sd 27/28 OLI 17,500 sq.m. £350,000 £700,000 B&C = 20% £ 400,000 split 70/30 35% Cowal B836 Glen Lean 20,000 sq.m. £140,000 15% Bute A844 TBC 8,500 sq.m. £60,000 50% Pre SD Pre SD 27/28 10,000 sq.m. £200,000 £400,000 H & L = 14% £ 280,000 Lomond 50% Lomond A814 Rhu Road Lower Glasgow - Pier Road 20,000 sq.m. £140,000 50% Pre SD Pre SD 27/28 7,000 sq.m. £140,000 £280,000

A/ Surface dressing and Pre-Surface Dressing Treatments total £2,000,000

B/ £ 1,000,000 AREA - Proportional distribution - Replacement of Timber Post - Vehicle Safety fencing (VSF)

MAKI = 31% £ 310,000 Value VSF Timber Post replacement - Vehicle Safety Fencing 1,550 lin.m. £310,000 OLI = 35% £ 350,000 VSF Timber Post replacement - Vehicle Safety Fencing 1,750 lin.m. £350,000 BC = 20% £ 200,000 VSF Timber Post replacement - Vehicle Safety Fencing 1,000 lin.m. £200,000 HL = 14% £ 140,000 VSF Timber Post replacement - Vehicle Safety Fencing 700 lin.m. £140,000 B/ VSF total £1,000,000

C/ £ 100,000 AREA - Proportional distribution - Road Sign upgrades.

MAKI = 31% £ 31,000 Value Signs Traffic Signs , Poles & Bollard - Upgrade and replacements 8 nr £31,000 OLI = 35% £ 35,000 Signs Traffic Signs , Poles & Bollard - Upgrade and replacements 9 nr £35,000 BC = 20% £ 20,000 Signs Traffic Signs , Poles & Bollard - Upgrade and replacements 6 nr £20,000 HL = 14% £ 14,000 Signs Traffic Signs , Poles & Bollard - Upgrade and replacements 4 nr £14,000 C/ Signs total £100,000 A/+ B/ + C/ SAFETY RELATED STRATEGIC NETWORK TREATMENT PROGRAMME £3,100,000

Part 3 £ 900,000 AREA - Proportional distribution - Accelerated Carriageway Deterioration post - April MAKI = 31% £ 279,000 Value Carriageway Accelerated Carrigeway deterioration treatment 13,950 sq.m. £279,000 OLI = 35% £ 315,000 Carriageway Accelerated Carrigeway deterioration treatment 15,750 sq.m. £315,000 BC = 20% £ 180,000 Carriageway Accelerated Carrigeway deterioration treatment 9,000 sq.m. £180,000 HL = 14% £ 126,000 Carriageway Accelerated Carrigeway deterioration treatment 6,300 sq.m. £126,000 POST APRIL - ACCELERATED CARRIAGEWAY DETERIORATION PROGRAMME £900,000 Further information to be reported to June 2026 EDI.

Part 4 £ 5,900,000 DISTRICT - Proportional distribution of Drainage and Surfacing works programme Schemes with Green background - WDM Scheme data.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices: Capital ProgrammeReport 185 KB DownloadRead as text
PDF
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2026-27Report 232 KB Download

At this meeting

Whole meeting

Who was there

15 of 20 attended
IP
Councillor Iain PatersonMember, present
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, present
GH
Councillor Graham HardieMember, apologies
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
JL
Councillor Jim LynchMember, present
TM
Councillor Tommy MacPhersonMember, present
IM
Councillor Ian MacQuireMember, present

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ROADS CAPITAL RECONSTRUCTION PROGRAMME 2026-27This decision
  2. Roads capital reconstruction programme 2026-27 - update reportAgreed
  3. Roads capital reconstruction programme - 2025/26Agreed
  4. Roads capital reconstruction programme 2024/25 - update reportAgreed
  5. Roads capital reconstruction programme 2024/25Agreed
  6. Roads Capital Reconstruction Programme 2024/25Noted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies