ROADS CAPITAL RECONSTRUCTION PROGRAMME 2026-27 - UPDATE REPORT
AgreedCommittee1 paper
AI summaryArgyll and Bute Council's Environment, Development and Infrastructure Committee has held back £0.900m of unallocated roads funding as a contingency to cover cost increases on existing 2026-27 road reconstruction schemes linked to the war in Iran.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed£0.900m retained for existing schemes
Money£0.900mSet aside as cost pressure contingency
What happens nextMonitor and report backOfficers to scrutinise cost claims monthly
Who it affectsExisting 2026-27 road schemesFunds diverted from new local schemes
What was decided
The committee agreed that the remaining £0.900m is not allocated to new schemes and is held as a contingency for existing schemes facing cost increases linked to the war in Iran. Report P7, P14
Any unspent contingency can be considered as part of the 2027-28 budget if not fully needed. Report 4.4
Why
Contractors have reported cost pressures on materials, fuel and supplies because of the ongoing crisis in the Gulf, with potential increases of around 10 percent and more than £1 million added to the programme. Report 1.5, 4.1
The council has its largest capital roads budget for many years and wants to deliver current schemes for communities, including more than £1 million of surfacing and drainage works on Islay. Report 4.2
Officers and the Procurement Team will hold monthly update and monitoring meetings to scrutinise contractor cost claims and secure best value.
What happens next
Officers will hold monthly meetings with the Procurement Team to monitor contractor cost claims.
Members will be told whether the £0.900m contingency is sufficient as cost pressures become clearer. Report 6.2
Any unused contingency will be considered as part of the 2027-28 budget. Report 4.4
£12M Total capital programme for 2026-27 endorsed in March 2026 Report 1.1, 1.2
£11.1M Allocated to strategic schemes, vehicle safety fencing and road signage Report 1.2
£6.8M Allocated within that to Area Resurfacing and Drainage Schemes Report 1.2
£1M Road surfacing and drainage works planned for Islay this year Report 4.2
more than £1 million Potential cost increase to the programme from 10 percent price rises Report 1.5
Options considered
Rejected: Allocate the £0.900m to new schemes identified by Elected Members. Uncertainty over Gulf crisis cost pressures means money should be held back to protect the existing programme Report 1.4, 1.5
Chosen: Retain £0.900m as a contingency for existing schemes facing cost increases Report P7, P14, 4.4
Implications
Financial: The £0.900m is set aside as contingency across existing schemes with cost rises linked to the war in Iran; it is not yet known if this will be enough. Report 6.2
Risk: Completing works should reduce the need for repairs and slow carriageway and footway deterioration. Report 6.6
Other: Works will be assessed and delivered under the current Roads Asset Management Plan. Report 6.1
Other: Customers should see an overall improvement in road surfaces and journey quality. Report 6.5
Who and where
Communities served by the 2026-27 capital roads reconstruction programme Report 1.1, 4.2
Residents of Islay, where more than £1 million of surfacing and drainage works are planned Report 4.2
Elected Members who put forward suggested local schemes for the unallocated £0.900m Report 1.4
External contractors delivering the roads programme Report 1.5, 4.1
Timeline
March 2026: EDI Committee endorsed £12M capital programme and allocated £11.1M, leaving £0.900m unallocated Report 1.1, 1.2, 1.3
8 April 2026: Members' Seminar held on the capital programme and the unallocated budget Report 1.4
2026-27: Current financial year, with road surfacing and drainage works delivered, including on Islay Report 4.2
18 June 2026: EDI Committee meeting at which this decision was taken Report P9, P35
2027-28: Any unused contingency may be considered as part of next year's budget Report 4.4
Plain English for the jargon
EDI Committee: Environment, Development and Infrastructure Committee of Argyll and Bute Council
Capital Reconstruction Programme: The council's planned spending on rebuilding and upgrading roads assets
Gulf crisis / war in Iran: Ongoing conflict referenced in the report and decision as the cause of contractor cost pressures on materials and fuel
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decision The Environment, Development and Infrastructure Committee agreed that the remaining £0.900m is not allocated to new schemes and is retained as a contingency for allocating to existing schemes in the current programme that are experiencing cost increases related to the war in Iran. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The Roads Reconstruction Programme was presented to the March 2026 Environment, Development and Infrastructure (EDI) Committee. It focused on arresting the rate of decline and providing an overall improvement in the condition of our Roads assets. The Committee endorsed the Capital Programme for 2026-27 totalling £12M.
1.2Within the funding awards for 2026-27 and 2027-28 of £12M per annum, the March EDI Committee agreed to allocate £11.1M to strategic schemes, vehicle safety fencing and road signage, with £6.8M of this budget allocated to the Area Resurfacing and Drainage Schemes.
1.3The March EDI Committee also requested that officers engage with Elected Members regarding the unallocated £0.900m and that a final list of schemes within the overall budget and programme of works for 2026/27 be considered at the June 2026 meeting of the EDI Committee.
1.4Officers from Roads and Infrastructure Services held a Members’ Seminar on 8 April 2026 and presented a slide show outlining how officers managed the Capital Programme. At that meeting, Elected Members were asked to provide details on any local schemes which they would like progressed on behalf of their communities. Several Elected Members have fed back various requests to officers on suggested spends for this unallocated budget.
1.5In the meantime, Roads and Infrastructure Services have received correspondence from many of its contractors indicating that the ongoing crisis in the Gulf is creating significant cost pressures for materials, fuel, and related supplies. While officers are currently unable to fully quantify the financial impact, a medium-term continuation of the conflict could result in cost increases of around 10%. This may, in turn, lead to an increase of more than £1 million in the Capital Road Programme. 1.6 Given the current uncertainty in the Gulf, officers recommend that the remaining £0.900m should not be allocated to new schemes but should be retained as a contingency and allocated to the schemes in the current programme where cost pressures are being experienced in order to deliver the schemes already agreed in the programme. Should the full £0.900m not be required any remaining funding can be considered as part of the 2027-28 budget.
Recommendation
It is recommended that the Environment, Development and Infrastructure Committee –
Agree that the remaining £0.900m is not allocated to new schemes and is retained as a contingency for allocating to existing schemes in the current programme that are experiencing cost increases related to the war in Iran. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 18th JUNE 2026 SERVICES
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2026-27 – UPDATE REPORT
2.0INTRODUCTION
2.1This report provides details of the proposed delay to the use of £0.900m unallocated funding for the Capital Reconstruction programme for 2026-27. This is specifically related to predicted increase in costs due to the ongoing Gulf Crisis.
2.2The March 2026 EDI Committee requested that officers engage with Elected Members regarding the unallocated £0.900m and that a final list of schemes within the overall budget and programme of works for 2026/27 be considered at the June 2026 meeting of the EDI Committee.
3.1It is recommended that the Environment, Development and Infrastructure Committee –
Agree that the remaining £0.900m is not allocated to new schemes and is retained as a contingency for allocating to existing schemes in the current programme that are experiencing cost increases related to the war in Iran
4.0DETAIL
4.1Due to the ongoing Gulf Crisis, officers from Roads and Infrastructure Services have received several requests from external contractors indicating an increase in their costs for fuel and other materials and requiring increases to their current contracts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.