Agreed that consideration of this application be continued to allow a site inspection to be held. 9 02/00418/DET [name removed] – Detailed application – erection of a dwelling house – Land adjacent to Beechwood, Barcaldine. Approved subject to (a) conditions 1-3 as set out in the report dated 5 April 2002 by the Head of Development & Building Control and (b) condition 4, subject to the amendment of ‘including’ to ‘included’. 10 01/00422/DET Mr & [name removed] – Detailed application – Erection of a dwelling house – Garden ground of Sheridan, Polvinister Road, Oban. Approved subject to the conditions set out in the supplementary report No.1 dated 24 April 2002 by the Head of Development and Building Control. 11 01/01926/DET Julie and Paul Campbell-Roberts – Detailed app;ication – Erection of a dwelling house – Land south of Cuil Right, North Connel, by Oban. Approved, subject to (a) the conditions set out in the supplementary report No.2 dated 19 April 2001 by the Head of Development & Building Control; and (b) a Section 75 Agreement to cover the points set out in the aforementioned report.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
DEVELOPMENT AND ENVIRONMENT SERVICES Local Member - Cllr MacIntyre PLANNING APPLICATION REPORT Date of Validity - 30.1.02 OBAN, LORN AND THE ISLES Committee Date - 8.5.02
10.4.02
Reference Number: 02/00118/COU Applicants Name: Alan G Walker Application Type: Change of Use Application Application Description: Change of use of play area to residential garden ground Location: Tramway Cottages, Ellenabeich, Isle of Seil
(A ) THE APPLICATION
Development Requiring Express Planning Permission.
• Change of use of existing play area to garden ground.
(B ) RECOMMENDATION
It is recommended that planning permission be granted as a justified minor departure to policy PU 7A of the Lorn Local Plan subject to the standard condition.
Members should note that the existing Section 50 agreement requires to be revoked. The applicant will be advised not to implement this consent until the Section 50 agreement has been revoked and advised of the requirement to submit a written request to this effect.
(C ) DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
Planning Permission (ref. no. 01-93-0772) was granted for the erection of 8 houses on the edge of Ellenabeich. This permission included a play area on the approved plans and was subject to a section 50 agreement which ensures the provision and maintenance of a play area within the development. Condition 7 attached to this permission required the submission of full details of the play equipment to be provided and details of the surfacing of the play area.
This level of play space provision accords with policy PU 7a of the Lorn Local Plan. This policy states that the Council will require the provision of play areas and public open spaces within new housing estate developments. However, no guidance is given on what constitutes a housing estate development in terms of number of houses within the Lorn Local Plan. The replacement local plans for Bute and Cowal address this lack of clarity and specify that play space be provided for developments in excess of 25 houses.
Statutory Plans have advised that the new Argyll and Bute Local Plan is expected to develop the existing policy on play space, and will seek to introduce a consistent approach to the threshold upon which the provision of play space will be required (ie above a specific number of houses). It is unlikely that the new local plan will require play space provision for housing developments of 8 houses.
The existing play area contains no purpose built play equipment. The only features within the site are a row of upturned logs, which gradually increase in height, and a rope tyre swing suspended from the branch of a tree. The area is grassed and contains no play area specific safety surfaces. The Play Area appears un-maintained and neglected.
This proposal to change the use of the existing play area required by condition of planning permission no. 01-93-772 and revoke the existing Section 50 agreement represents a departure from policy PU 7a of the Lorn Local Plan. However, the current condition of the play area, the support of this proposal by the residents of this development, the fact that there is alternative play space available adjacent to F:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000245\M00000712\AI00003005\ALLANWALKER0.DOC 1 the village hall, along with the emerging new local plan policy, are considered to represent justification for departure from policy PU 7a.
(D) REASONED JUSTIFICATION The proposals can be treated as a minor justified departure from Policy PU 7A of the Lorn Local Plan for the following reasons:
• The existing adopted local plan is in need of review and update; • The play area is underused and its loss is supported by residents of the development. • Alternative play space is available elsewhere in the village. • The proposal is unlikely to conflict with or be prejudicial to policy within the emerging District Wide Local Plan.
(E) INFORMAL PUBLIC HEARING IN TERMS OF PAN 41
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.