Report by Area Transportation Manager in regard to Works Programme 2002/2003

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Wednesday 8 May 2002. Below is the council's own wording, with the papers it was decided on.

Item6a

Resolved

Decision Agreed: (a) the proposed programme set out in appendix A to the report; (b) to approve the proposals in Appendix B for utilising the additional £180,000 received from the Scottish Executive; (c) to note the routine and winter allocations in Appendix C; and (d) to continue consideration of the proposed utilisation of the possible surplus in the car parking operation to a future meeting when Area Strategy funding is being discussed. Arising from this it was agreed that the Area Transportation Manager submit a report to a future meeting in regard to the 2001/2002 winter maintenance expenditure. (Ref: Report by the Area Transportation Manager, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Summary

This report gives details of the proposed Road Maintenance Work Programme for 2002/03 including proposals for using the Oban Lorn and Isles share of additional funding provided for roads maintenance by the Scottish Executive, and preliminary proposals for spending the anticipated surplus in the car parking operation.

Recommendations

2.1That the Committee agree the proposed programme in Appendix A.

2.2That the Committee approves the proposals in Appendix B for utilising the additional £180,000 received from the Scottish Executive.

2.3That the Committee notes the routine and winter allocations in Appendix B.

2.4That the Committee approves in principle the proposals in 3.3.1 for utilising the possible surplus in the car parking operation.

Background

3.1On April, 3 2002 I presented to the Committee my proposed Road Maintenance Works Programme. As no decision had been taken on how most of the additional Scottish Executive funding was to be apportioned the programme included only proposals for only £90,000 of this funding to be used for surface dressing. It has now been confirmed that this Area’s allocation is £180,000 and full proposals for utilising this are shown in Appendix B.

3.2Much of the routine and winter maintenance is reactive, i.e. we react to potholes, floods or snow. The figures given in Appendix C allow for an average year with some additional funds for patching, ditching and scrub clearance.

3.3.1 On 6 February 2002 the Committee agreed that initial proposals for utilising the Area parking surplus should be considered in early summer. Proposals are given in Appendix C. It should be noted that these are rough budget estimates only as a significant amount of design work will have to be carried out before accurate estimates can be produced. If Members approve the proposals in principle, design work will be carried out and more detailed estimates calculated. As we do not yet know what the surplus will be the projects are listed in order of priority.

The proposed projects are:- Airds Crescent, Oban – traffic management and streetscape £20,000 Crossapol, Tiree – upgrade traffic calming £20,000 Benderloch Car Park – resurface £30,000 3.3.2 Traffic calming measures installed some years ago in Crossapol, Isle of Tiree are effective but unsightly. Now that they have operated for a number of years I propose to upgrade them so that they enhance rather than reduce amenity.

3.3.3 Traffic management works in Airds Crescent will complement other proposals to repair the retaining wall and to improve road safety and amenity. They will include the introduction of on street charging which will help to repay this investment.

3.3.4 The car park and bus turning circle in Benderloch were constructed with unbound surfaces not to be adopted by the Roads Authority. Maintenance responsibility was accepted by the Planning Department of the former District Council. The problems anticipated from unbound surfaces have occurred with numerous complaints resulting. I propose to upgrade the area to a standard suitable for adoption and thereafter to manage and maintain the car park along with my Department’s other car parks.

3.4At the April meeting the Member for Tiree and Coll expressed concern at the absence of proposals for his Ward. As explained at that meeting mobilisation costs on Coll and Tiree are high. Therefore major maintenance works can only be cost effectively carried out on Tiree by carrying out a large programme every few years. Members should note that I plan to bring forward surface dressing proposals for next year.

For further information or clarification of any matter contained within this report please contact Neil Brown on 01631 562125

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report by Area Transportation Manager in regard to Works Programme 2002/2003Report 13 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 34 attended
AM
Councillor Alistair MacDougallVice-Chair, expected
AM
Councillor Allan MacaskillMember, expected
CC
Councillor Campbell CameronMember, expected
DW
Councillor David WebsterChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksMember, expected
DC
David CraigOfficer, expected
SM
Stewart McGregorOfficer, expected
HB
Hugh BlakeOfficer, expected
JB
Jillian BrownSecretary, expected
NB
Neil BrownOfficer, expected
SC
Sandra CampbellSecretary, expected

All 34 on the meeting page

On this subject at Argyll and Bute

Search all
  1. Report by Area Transportation Manager in regard to Works Programme 2002/2003This decision
  2. Report by Area Transportation Manager in regard to extension of car parking chargesDecided
  3. Report by Area Transportation Manager in regard to parking incomeNoted
  4. Report by Area Transportation Manager in regard to Parking IncomeAgreed
  5. Report by Area Transportation Manager in regard to additional funding for road network repairsAgreed
  6. Report by Area Transportation Manager in regard to Road Resurfacing WorksAgreed

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies