Report by Director of Development & Environment Services in regard to Building Control Performance Monitoring Council wide and Decentralised Area Teams
AgreedCommittee1 paper
Oban Lorn & The Isles Area Committee agreed this item on Wednesday 8 May 2002. Below is the council's own wording, with the papers it was decided on.
Decision Agreed to note the contents of the report and, in particular, the continuous improvement in building control performance over the past 3 years. (Ref: Report dated 15 April 2002 by the Director of Development and Environment Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper outlines my department’s Building Control performance with respect to processing building warrant and completion certificate applications in accordance with the requirements of the Accounts Commission.
1.2The paper also compares and contrasts the performance of the Council’s four area offices for the years 2000/2001 and 2001/2002.
Recommendation
2.1Members note the content of the report and in particular the continuous improvement in building control performance over the past 3 years.
2.2The business unit service delivery plan for the years 1999/2002 set targets for dealing with Building Warrants of 10 days to respond to a request for a building warrant and 6 days on average to issue a building warrant after receipt of all necessary information, an accumulated average of 16 days. Similarly targets of 5 days and 2 days were set for completion certificates. Both of these targets have been exceeded. The figures for 2001/2002 being 12 days and 4 days respectively.
Background
3.1Members are aware that performance indicators were first introduced for Building Control in financial year 1997/98.
3.2Building Control performance is measured by calculating the average times for dealing with requests for building warrants and completion certificates, as follows:-
A) The average time taken to respond to a request for
(1) A building warrant (2) A completion certificate
B) The average time taken to issue:-
(1) A building warrant or otherwise determine an application. (2) A completion certificate or otherwise determine an application.
C) The number of building warrants and completion certificates issued in the reporting year.
3.3Attached as Appendix 1, members will find the definitions appropriate to the Accounts Commission performance indicator requirements.
3.4In the Accounts Commission performance audit of indicators for regulatory services for the year 1999/2000 the above indicators have been combined in Table 3a to show the numbers of building warrants issued and the average time to respond to a request for, and to issue, a building warrant, and similarly at table 3b for completion certificates.
TABLE 3(a) FOR ARGYLL AND BUTE f:\moderngov\data\published\intranet\c00000245\m00000712\ai00003018\reportonbuildingcontrolperformancemonitoringacw12.04.020.doc No of Building Warrants issued Average number of days taken to respond to and issue a building warrant
No of Completion Certificates issued Average number of days taken to respond to and issue a Completion Certificate 2001/2002 2000/2001 1999/2000 2001/2002 2000/2001 1999/2000 1998/1999 1997/1998 922 939 918 4 4 5 7 9
3.5Members will note from the above table that since the introduction of performance indicators in 1997/98 the average times taken to process both building warrants and completion certificates have been consistently reduced.
3.6The all-Scotland averages for the year 1999/2000 were, average number of days to respond to a request for and to issue a building warrant 20 days, and to respond to a request for and issue a completion certificate 7 days. For the year 2000/2001 Appendices 2 and 3 give an indication of the relative response position of Scottish Councils to applications for Building Warrants and Completion Certificates.
3.7Improvements to the format and systems of reporting for the Building Control system have enabled quicker and more accurate reporting for the Authority as a whole but has also enabled a comparison between the four administrative areas.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report by Director of Development & Environment Services in regard to Building Control Performance Monitoring Council wide and Decentralised Area TeamsReport
4eReport by Director of Development & Environment Services in regard to Building Control Performance Monitoring Council wide and Decentralised Area TeamsThis decision
Report by Director of Development & Environment Services in regard to Building Control Performance Monitoring Council wide and Decentralised Area TeamsThis decision
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.