Oban Lorn & The Isles Area Committee, Wednesday 15 April 2015 at 10.30am

Report by Executive Director of Development and Infrastructure Services

Approved Committee 1 paper

Oban Lorn & The Isles Area Committee approved this item on Wednesday 15 April 2015. Below is the council's own wording, with the papers it was decided on.

Item12a

Resolved

Decision The Committee: 1. Unanimously recommended that the Policy and Resources Committee approve the drawdown of borrowing for a total of up to £560K for the development of a full Business Case for Lorn Arc Project 5 – Oban North Pier Extension. These resources will be held in a defined budget and managed as detailed in the Lorn Arc Programme PID; and 2. Noted that the full Business Case for Project 5 will be reported to a future OLI Area Committee and subsequent Policy and Resources Committee before moving to the implementation stage. (Ref: Report by Oban Regeneration Project Manager dated 15 th April 2015, submitted). The Chair agreed to take further questions: Kieran Green read the Committee a question from the Chair of Oban Community Council, which was in relation to the observation on the grant applications in listening to the scoring of these. The Chair of the Community Council advised that it seems more money is granted to groups who have assistance from professional people who know how to tick the relevant boxes but there are other groups run by volunteers who do not have the knowledge to make their application score high enough to receive higher grants. She asked for more information and feedback on this. The Chair agreed to get the relevant council officer to respond to [name removed]. [name removed] presented the Committee with a poster designed to help tackle dog fouling in the Oban, Lorn and the Isles area. The Chair agreed to publicise this poster and thanked Ken for his hard work in bringing this forward. [name removed] also stated he was disappointed that members of the press and public did not stay for further questions as he feels that this subject affects everybody in Oban and the Chair agreed with him.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The Full Business Case for the Lorn Arc Tax Incremental Financing (TIF) programme outlines the proposals for delivering a £18.89 million package of infrastructure improvements including access to the Scottish Association for Marine Science (SAMS) / European Marine Science Park, measures to improve Port and Marine facilities within the Lorn Arc area and other business related infrastructure which will support the delivery of the Local Development Plan and assist population and economic growth through the generation of new employment opportunities.

1.2TIF arrangements will allow Argyll and Bute Council to retain and use additional Non Domestic Rates (NDR) generated once borrowing has been repaid, within an agreed boundary over a 25 year period.

1.3Project 5 - Oban North Pier Extension, within the Lorn Arc programme business case approved by Scottish Government should now be taken forward.

1.4This report provides the following information:

• Additional detail relating to the projected startup costs associated with bringing this project to Full Business Case (FBC) stage; and

• An outline of the background for Project Number 5 to be taken to Full Business Case.

1.5Preparatory works are required to inform the FBC and will include marine and land based surveys, design and engineering work, preparation of planning applications and other statutory consents, environmental and economic impact assessments, full business case report production and preparation of procurement documentation costs. These costs form part of the £18.89m TIF funded borrowing potential.

1.6At present the OLI Area Committee is only being requested to recommend to the Policy and Resources Committee that a start up budget be approved to take this project to full business case. Consideration as to whether this project should be implemented is determinate on the outcome of the full business case and subsequent consideration by Members. The Full Business Case is currently expected to be presented to the Oban, Lorn and the Isles Area Committee on 9th December, 2015 and then the Policy and Resources Committee on 17th December 2015. This timetable is based on the assumption that tender invitations can be issued by 8th May for the design work and 3rd July for the Economic Impact Assessment and FBC report.

Recommendation

1.8That Members: • Recommend that the Policy and Resources Committee approve the drawdown of borrowing for a total of up to £560k for the development of a Full Business Case for Lorn Arc Project 5 – North Pier extension. These resources will be held in a defined budget and managed as detailed in the Lorn Arc Programme PID. • Note that the Full Business Case for Project 5 will be reported to a future OLI Area Committee and subsequent Policy and Resources Committee before moving to the implementation stage. ARGYLL AND BUTE COUNCIL Oban, Lorn and the Isles

DEVELOPMENT & INFRASTRUCTURE 15th April, 2015 SERVICES

LORN ARC TAX INCREMENTAL FINANCING (TIF) ASSET PROJECT 5 - OBAN NORTH PIER EXTENSION START UP REPORT

2.0INTRODUCTION

2.1This report provides the following information:-

a. Additional detail relating to the projected start up costs associated with bringing this project to Full Business Case stage. b. An outline of the background for Project 5 – Oban North Pier extension – to be taken to full business case.

Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report by Executive Director of Development and Infrastructure ServicesReport 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 14 attended
DC
Donald CampbellPublic, expected
MD
Councillor Mary-Jean DevonMember, present
DF
Danielle FinlaySecretary, expected
GF
Graeme ForresterClerk, expected
SL
Sally LoudonOfficer, expected
IM
Councillor Iain MacDonaldMember, present
AM
Councillor Alistair MacDougallMember, present
DM
Councillor Duncan MacIntyreMember, apologies
NM
Councillor Neil MacIntyreMember, present
IM
Councillor Iain MacLeanMember, present
SM
Shirley MacLeodOfficer, expected
RM
Councillor Roderick McCuishChair, present

All 14 on the meeting page

On this subject at Argyll and Bute

Search all
  1. Report by Executive Director of Development and Infrastructure ServicesThis decision
  2. Report by Executive Director with responsibility for Legal and Regulatory SupportNoted
  3. Report by Executive Director responsible for Legal and Regulatory SupportNoted
  4. Report by Executive Director with responsibilities for Legal and Regulatory SupportAgreed
  5. Report by Executive Director with responsibility for Legal and Regulatory SupportAgreed
  6. Report by Executive Director with responsibility for Commercial Services (public)Noted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies