Decision Agreed: (a) to note the report; and (b) that, in light of advice provided in regard to slow progress of land acquisition at Soroba, and other project slippage identified in the report, a sum of £20,000 be earmarked for the progression of airport services at Oban Airport. (c) that completion of all outstanding projects be accelerated as much as is practicable. (Ref: Progress report as at 20 September 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ALLOCATION OF AREA FUNDING - OBAN, LORN & THE ISLES AREA COMMITTEE
PROGRESS REPORT AS AT 20 SEPTEMBER 2002
Reference Service Budget Holder Project Est.Cost Est.Cost Expenditure Narrative Capital Revenue 20.09.02
10.1T&PS (Transportation) Neil Brown Luing Vehicular Ferry £ 4,000 £ 4,000.00 Complete
10.2DES (Amenity) Iain Welsh Muckairn cemetery, Taynuilt - Drainage improvements £ 12,000 £ 3,577.00 Main works completed. Some further planting work to be carried out in October. Site to be assessed by well pump engineers.
10.3T&PS (Transportation) Neil Brown B845 Taynuilt/Kilchrenan/Barnaline - Road Drainage £ 8,000 £ 5,500.00 Work in progress - to be completed by end of October.
11.1DES (Amenity) Iain Welsh Community Playing Field, Dunollie £ 17,000 £ 250.00 Soil sample taken for analysis. Initial ground and drainage works programmed for October. Project completion February 2003.
11.2DES (Amenity) Iain Welsh Oban Beach Cleaning / Improvements £ 7,000 £ 680.00 Regular cleaning taking place. Test deliveries of sand during November.
12.1/ 14.2 T&PS (Transportation) Neil Brown Airds Crescent, Oban - Enhancement Scheme Phase I £ 18,000 Land acquisition in progress. Subject of separate report.
12.2DES (Amenity) Iain Welsh McCaigs Tower, Oban - Installation of safety grid along barrier on viewing platform & some arches £ 3,000 Application for Listed Building Consent submitted.Anticipate project completion by December 2002.
12.3DES (Amenity) Iain Welsh McCaigs Tower, Oban - Clearance of scrub vegetation and trees in front of viewing platform £ 3,000 £ 290.00 Clearance work in progress. Completion by end of October.
12.4DES (Amenity) Iain Welsh Dungallan Park 'Temple' - Paint and secure building £ 2,000 £ 700.00 Complete. Balance available for reallocation.
12.5T&PS (Property) Derek White Street Signage £ 2,000 Awaiting approval of proposed design. Orders to be placed in early October for installation by January 2003.
12.6DES (Amenity) Iain Welsh Jacob's Ladder - Environmental improvements £ 2,000 £ 250.00 Complete. Alternative funding identified and utilised. Balance available for reallocation.
13.1CLS (Legal) Donald Kelly Soroba - Acquisition of ground £ 22,000 Subject of separate report.
13.2ED Carol Walker Fence / Footpath - Oban High School £ 2,000 Tenders issued. Instruct contractors early October. Work to be completed mid November.
14.1T&PS (Transportation) Neil Brown Kerrera Slip - Formation of turning area £ 6,000 £ 6,000.00 Complete.
14.3T&PS (Transportation) Neil Brown Kirk Road, Dunbeg - Additional road lighting £ 4,000 Work programmed for February 2003.
14.4T&PS (Transportation) Neil Brown B844 Achnasaul - Renew filter drain £ 9,000 To be carried out along with bridge strengthening works. Completion in March 2003.
15.1T&PS (Transportation) Neil Brown Shore Road, Connel - Improvements £ 12,000 £ 12,000.00 Complete
15.2T&PS (Transportation) Neil Brown Benderloch / Tralee straight - Provision of passing place £ 6,000 Work programmed for February 2003.
15.3T&PS (Transportation) Neil Brown Bonawe Footpath £ 6,000 Awaiting Community Council proposals
16.1T&PS (Transportation) Neil Brown Tobermory Seawall - Repaint railings £ 12,000 Work in progress. To be invoiced on completion.
16.2DES (Amenity) Iain Welsh Kilmore Cemetery, Dervaig - Construction of new access road £ 12,000 Work in progress.Anticipate project completion October 2002.
17.1ED David Craig Grant to An Talla (Tiree Community Hall) towards new hall £ 13,000 £ 13,000.00 Complete
17.2T&PS (Transportation) Neil Brown Tiree and Coll Roads Improvements £ 11,000 Programmed for October completion.
OLI.2 T&PS (Transportation) Neil Brown Signage throughout Oban, Lorn & the Isles area £ 7,000 Priorities to be identified by mid October to allow work to be completed by end November.
TOTAL FOR OBAN, LORN & THE ISLES AREA £ 100,000 £ 100,000 £ 46,247.00
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.