Area Funding Progress Report

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Wednesday 4 December 2002. Below is the council's own wording, with the papers it was decided on.

Item3b

Resolved

Decision Agreed: (a) to note the report; and (b) that the £7,000 (£2,450 capital and £4,550 revenue) available for reallocation be used for general scrub cutting, drainage and sight line improvements. (Ref: Progress report as at 22 November 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

ALLOCATION OF AREA FUNDING - OBAN, LORN & THE ISLES AREA COMMITTEE

PROGRESS REPORT AS AT 22 NOVEMBER 2002

Reference Service Budget Holder Project Est.Cost Est.Cost Expenditure Narrative Capital Revenue 20.09.02

10.1T&PS (Transportation) Neil Brown Luing Vehicular Ferry £ 4,000 £ 4,000 Complete

10.2DES (Amenity) Iain Welsh Muckairn cemetery, Taynuilt - Drainage improvements £ 8,000 £ 4,302 Main works completed. Waterlogged turf to be replaced. Completion anticipated by end of November.

10.3T&PS (Transportation) Neil Brown B845 Taynuilt/Kilchrenan/Barnaline - Road Drainage £ 8,000 £ 8,000 Complete

10.4T&PS (Transportation) Neil Brown Kilchrenan / Dalavich - Sight line improvements £ 4,000 Programmed for December.

11.1DES (Amenity) Iain Welsh Community Playing Field, Dunollie £ 17,000 £ 3,709 Soil sample taken for analysis. Further funding secured. Initial ground and drainage works ongoing. Project completion February 2003.

11.2DES (Amenity) Iain Welsh Oban Beach Cleaning / Improvements £ 7,000 £ 2,344 Regular cleaning taking place. Test deliveries of sand during November. Completion anticipated after high tides during March.

12.1/ 14.2 T&PS (Transportation) Neil Brown Airds Crescent, Oban - Enhancement Scheme Phase I £ 18,000 Land acquisition in progress.

12.2DES (Amenity) Iain Welsh McCaigs Tower, Oban - Installation of safety grid along barrier on viewing platform & some arches £ 3,000 Application for Listed Building Consent submitted.

12.3DES (Amenity) Iain Welsh McCaigs Tower, Oban - Clearance of scrub vegetation and trees in front of viewing platform £ 3,000 £ 615 Clearance work in progress. Planting undertaken. Treework to complete November.

12.4DES (Amenity) Iain Welsh Dungallan Park 'Temple' - Paint and secure building £ 2,000 £ 700 Complete. £1300 available for reallocation.

12.5T&PS (Property) Derek White Street Signage £ 2,000 Delivery of signs expected on 9 December. Installation by January 2003 following consultation with local Members.

12.6DES (Amenity) Iain Welsh Jacob's Ladder - Environmental improvements £ 2,000 £ 250 Complete. Alternative funding identified and utilised. £1750 available for reallocation.

13.1CLS (Legal) Donald Kelly Soroba - Acquisition of ground (initial legal costs) £ 2,000

13.2ED Carol Walker Fence / Footpath - Oban High School £ 2,000 Work progressing on site.

14.1T&PS (Transportation) Neil Brown Kerrera Slip - Formation of turning area £ 6,000 £ 6,000 Complete.

14.3T&PS (Transportation) Neil Brown Kirk Road, Dunbeg - Additional road lighting £ 4,000 £ 4,000 Complete.

14.4T&PS (Transportation) Neil Brown B844 Achnasaul - Renew filter drain £ 9,000 To be carried out along with bridge strengthening works. Completion in March 2003.

15.1T&PS (Transportation) Neil Brown Shore Road, Connel - Improvements £ 12,000 £ 12,000 Complete

15.2T&PS (Transportation) Neil Brown Benderloch / Tralee straight - Provision of passing place £ 6,000 Work programmed for February 2003.

15.3T&PS (Transportation) Neil Brown Bonawe Footpath £ 6,000 Awaiting Community Council proposals

16.1T&PS (Transportation) Neil Brown Tobermory Seawall - Repaint railings £ 12,000 Repairs completed. Painting work in progress. To be invoiced on completion.

16.2DES (Amenity) Iain Welsh Kilmore Cemetery, Dervaig - Construction of new access road £ 12,000 £ 12,000 Complete.

17.1ED David Craig Grant to An Talla (Tiree Community Hall) towards new hall £ 13,000 £ 13,000 Complete

17.2T&PS (Transportation) Neil Brown Tiree and Coll Roads Improvements £ 11,000 £ 11,000 Complete.

OLI.2 T&PS (Transportation) Neil Brown Signage throughout Oban, Lorn & the Isles area £ 7,000 Installation programmed for January 2003.

OLI.3 DES (Econ.Development) Seamus Lalor Oban Air Services Project £ 20,000 £ 11,550

TOTAL FOR OBAN, LORN & THE ISLES AREA £ 100,000 £ 100,000 £ 93,470

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Area Funding Progress ReportReport 55 KB DownloadRead as text

At this meeting

Whole meeting
3aMinute of meeting of the Area Committee held on 6 November 2002On the agenda
3bArea Funding Progress ReportThis decision
3cReport by Head of Accounting in regard to Capital Receipts raised from sale of assetsAgreed 3dConsider letter dated 7 October 2002 from the Radio Authority in regard to local radio licence - ObanOn the agenda 4aList of Building Warrants approved by the Director of Development & Environment Services since the last meetingOn the agenda 4bList of Delegated Decisions issued by the Director of Development and Environment Services since the last meetingOn the agenda 4cApplications for Planning Permission for consideration by the CommitteeAgreed 4dReport by Head of Building Control in regard to feedback on customer satisfaction regarding development and building control exit questionnairesOn the agenda 4eReport by Director of Development & Environment Services in regard to appeal to Scottish Executive Inquiry Reporter's Unit - Ref. 02/00160/DET - Proposed culverting of burn at Lataska, Polvinister Road, ObanAgreed 4fApplications for financial assistance under the Leisure Development Grants SchemeDecided 5aReport by Head of Early and Primary Education in regard to School Holidays and In Service Days: 2003/2004On the agenda 6aReport by Public Transport Officer in regard to Rural Transportation Grant Expenduture 2003/2004Agreed 7ROYAL MAIL SORTING OFFICE, OBAN - LOCAL MAIL ARRANGEMENTSAgreed 8PUBLIC QUESTION TIMEAgreed 23The Committee resolved in terms of Section 50A(4) of theOn the agenda 9NORTH PIER, OBANAgreed

Who was there

0 of 30 attended
AM
Councillor Alistair MacDougallVice-Chair, expected
AM
Councillor Allan MacaskillMember, expected
CC
Councillor Campbell CameronMember, expected
DW
Councillor David WebsterChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksMember, expected
DC
David CraigOfficer, expected
LM
Lorna MacKinnonSecretary, expected
JB
Jillian BrownSecretary, expected
NB
Neil BrownOfficer, expected
SC
Sandra CampbellOfficer, expected
CE
Carol EvansOfficer, expected

All 30 on the meeting page

On this subject at Argyll and Bute

Search all
  1. Area Funding Progress ReportThis decision
  2. Area Capital Receipt Funding Update: Halls within Helensburgh and Lomond AreaAgreed
  3. Report by Area Roads & Amenity Services Manager in regard to utilisation of additional fundingAgreed
  4. Area Capital Funding - Progress ReportAgreed
  5. Area Capital Funding - Progress reportAgreed
  6. Area capital funding progress reportAgreed

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies