Resolved
Decision Agreed the revised options for achieving revenue savings and noted the effect on the revenue budget, capital programme and vehicle and plant fund. (Ref: Report by Director of Finance dated 9 September 2002, submitted)
Strategic Policy Committee agreed this item on Thursday 12 December 2002. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Agreed the revised options for achieving revenue savings and noted the effect on the revenue budget, capital programme and vehicle and plant fund. (Ref: Report by Director of Finance dated 9 September 2002, submitted)
1.1It is no longer possible to capitalise the £600,000 of roads revenue expenditure approved in August 2001. Alternative proposals have been brought forward
RECOMMENDATIONS 2 2.1 To consider the revised options for achieving revenue savings and note the effect on the revenue budget, capital programme and vehicle and Plant Fund
3 DETAIL
3.1In August 2001 the Council agreed to capitalise £600,000 from its revenue budget. At that time it was planned to capitalise expenditure from roads revenue budget. The balance of expenditure remaining in roads revenue budget does not meet the definition of capital expenditure and cannot be charged to capital.
3.2Discussions with Transportation and Property have identified the following proposal for capitalisation. Expenditure on this proposal is currently planned to be charged to the revenue budget. Charging this expenditure to capital will allow savings to be made in the revenue budget
Proposal Cost Revenue Saving
Street Lighting £50,000 £50,000
3.3The revenue budget monitoring report shows a projected surplus of £810,000 after adjustment for Education services and national insurance reductions. It also assumes the full £600,000 of capitalisation. The action outlined in 3.2 above will achieve a saving of £50,000. This change will reduce the surplus to £260,000
3.4The current capital programme projections do not include the £600,000 capitalisation. This proposal will increase projected capital expenditure by £50,000. 3.5 The proposal outlined in paragraph 3.2 above amounts to a capitalisation and revenue savings of £50,000. This is £550,000 short of the required sum of £600,000. One further option is available to partially address this gap.
3.6There is an option to utilise the Vehicle and Plant Renewal and Repair Fund. Vehicles could be purchased at £300,000 in place of being leased. Whilst this will not produce a revenue saving this year of £300,000 it will over the course of 5 years produce revenue saving of £300,000 (5 years at £60,000 per year). These are approximate figures. The annual savings of £60,000 would be reductions in Fleet Management budget for lease premium (this would be passed on to the vehicle user departments) for the years 2003/04 to 2007/08. This reduction in revenue budget would be used to make an annual contribution to the Vehicle and Plant Renewal & Repair Fund of £60,000 per annum. In 2002/03 £300,000 would be drawn from the Fund as a contribution to vehicle maintenance costs. It would be reinstated by the annual contributions of £60,000 in the years 2003/04 to 2007/08.
3.7The table below seeks to summarise this option;
Vehicle & Plant Fund General Fund Transaction Balance V&P Savings in Net Effect Contribution Fleet £000 £000 £000 Leasing £000 Costs £000 2002-03 (300) 29 300 300 2003-04 60 89 (60) 60 0 2004-05 60 149 (60) 60 0 2005-06 60 209 (60) 60 0 2006-07 60 269 (60) 60 0 2007-08 60 329 (60) 60 0
3.8The current balance on the Vehicle and Plant Renewal and Repair Fund is £329,000. The contribution to the General Fund in 2002/03 would reduce this to £29,000 however it would increase at the rate of £60,000 per annum until 2007/08 when it would amount to £329,000.
3.9In summary the savings achieved in 2002-03 by capitalising street lighting expenditure (£50,000) and delivering a contribution from the vehicle and Plant Renewal and Repair Fund (£300,000) is £350,000. This is £250,00 less than agreed in August 2001 4 CONCLUSION
4.1This report outlines the alternative proposal to meet £350,000 of the £600,000 revenue savings to be achieved through capitalisation agreed in August 2001. The proposals outline measures to achieve a reduction in General Fund expenditure of £350,000 compared to £600,000 agreed in August 2001. This will reduce the General Fund surplus projected by £250,000.
5 IMPLICATION
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITALISATION OF £600,000Report | 66 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.