Resolved
Decision 1. To note the budget monitoring report. 2. To instruct departments to contain expenditure within the amended budget. (Reference – Report by Director of Finance dated 5 November 2002, submitted)
Strategic Policy Committee noted this item on Thursday 12 December 2002. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision 1. To note the budget monitoring report. 2. To instruct departments to contain expenditure within the amended budget. (Reference – Report by Director of Finance dated 5 November 2002, submitted)
2.1To note the budget monitoring report
2.2To instruct departments to contain expenditure within budget as amended above.
3 MAIN POINTS
3.1The financial statement reveals a projected surplus of £159,000
3.2The projected surplus of £159,000 is dependent upon achievement of the agreed Education savings package. It represents 0.1% of the projected net expenditure and offers no flexibility to the Council.
3.3An allowance was made in closing the accounts for 2001-2002 for repayment of housing benefit subsidy of £329,000. It has now been confirmed that repayment will not be required. This has not been reflected in the projected surplus.
3.4There are expenditure pressures on special education needs in Education. A supplementary estimate of £70,000 was approved at the Strategic Policy Committee on 14 November 2002.
3.5The addition of these to the projected surplus would result in an increase surplus from £159,000 to £418,000.
3.6The annual budget incorporates the approved transfer from capital to revenue agreed in August 2001. This proved not to be achievable. The projected outturn has been revised to reflect this. A further item on the agenda suggests a proposal to partially address this.
3.7The year to date approved expenditure is below budget by £3,518,000. The main elements of this are: £
Housing & Social Housing Benefit Subsidy – 124,000 Work Repayment of withheld subsidy
Transitional Housing Benefit held in 388,000 advance of invoicing by service provider
Resources transfer monies and grant 421,000 funding received but not yet spent
Transportation & Roads Maintenance – additional 848,000 Property allocation from year end flexibility outstanding
Central Services District Court fines – to be remitted 110,000 October
Grant Funding received in advance 169,000
Digital Communities grant for 3 year 380,000 received in advance
Capital Financing Savings projected in loan charges – year to date element. 300,000
Development & Economic Development mainly 216,000 Environment grants accrued but not paid
Other 562,000
Total Year To Date 3,518,000
3.8Due to a change in accounting policy the cost of unfunded pensions is now shown with surplus properties and treated as an unapportionable central overhead rather than being charged to individual departments. Departmental budgets and projected outturn have been reduced and unapportionable central overheads increased. There is no overall change to the net position.
Bruce West Head of Accounting 5 November 2002 5novbwrbm-corporateoverview Argyll Bute Council - Objective Summary
Period: September_02-03
YEAR TO DATE POSITION PROJECTED FINAL OUTTURN YTD YTD YTD YTD Projected App Annual Projected Proj Previous Variance Actual Budget Variance Var Outturn Budget Variance Var Outturn From Prev £000s £000s £000s % £000s £000s £000s % £000s £000s
Education 33,394 33,399 5 0% 71,776 71,776 0 0% 72,921 1,145
Housing & Social Work 11,207 12,599 1,392 11% 34,578 34,578 0 0% 34,743 165
Transport & Property Services 9,196 9,828 632 6% 21,604 21,604 0 0% 21,738 133
Development & Environment Services 8,768 8,995 227 3% 21,023 21,023 0 0% 21,137 113
Central Support Services 4,655 4,723 68 1% 142 92 (50) (55)% 269 128
Central Services To the Public 873 1,711 838 49% 3,693 3,715 23 1% 3,217 (475)
Corporate & Democratic Core 700 669 (31) (5)% 2,854 2,854 0 0% 2,777 (78)
Joint Boards 6,196 6,167 (29) 0% 12,357 12,357 0 0% 12,357 0
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Overview SPC 2Report | 301 KB | DownloadRead as text |
PDF |
REVENUE BUDGET MONITORING: CORPORATE OVERVIEW: SEPTEMBER 2002Report | 301 KB | Download |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.