Resolved
Decision To note the overall budgetary position and various matters identified in the submitted report. (Ref: Report by Director of Finance dated 12 December 2002, submitted)
Strategic Policy Committee noted this item on Thursday 12 December 2002. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the overall budgetary position and various matters identified in the submitted report. (Ref: Report by Director of Finance dated 12 December 2002, submitted)
2.1To note the overall budgetary position and various matters identified in this report
3 DETAIL
3.1General Overview
3.1.1 The overall budgetary position for the Department is in line with the approved budget.
3.2Forecast Outturn
3.2.1 The forecast outturn position is showing projected expenditure of £1.253m. This represents a decrease of £0.023m 1.8 % on the approved budget.
3.3Year To Date Position
3.3.1 Year to date expenditure is £1.603m. This compares to a year to date budget of £1.611m. Actual expenditure is under budget by £0.008m for the year to date. This represents 0.5% of the full year budget.
3.3.2 The Salaries and Wages Section favourable variance is due to expenditure on Computer Costs, Overtime and Training being less than the budget profile. The expenditure will be incurred as required. The Income Section favourable variance is due to staff vacancies but will be required to cover costs due to secondment of staff to the Education Team.
3.4Year To Date Underspend Or Additional Income
3.5Traffic Light Report
3.5.1 A traffic light approach to monitoring is in place. This means detailed variance explanations are collected for all costs centre where the year to date variance is more than +-£25,000 (red ). Amber variances are those between +-£5,000 and +-£24,999. These are drawn to the attention of budget holders and managers with an instruction for investigation and strict monitoring to bring expenditure back in line with budget. Green variances are those between -£4,999 and +£4,999. The table below summarises the position with red, amber and green variances.
Variance Favourable Variances Adverse Variances No Cost Value Of No Cost Value Of Centres Variances £m Centres Variances £m Red 2 0.066 0 0.000 Amber 3 0.039 7 0.103 Green 8 0.010 3 0.004 Total 13 0.115 10 0.107
Director Of Finance ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
REVENUE BUDGET MONITORING – PROJECTED OUTTURN VARIANCES -
SEPTEMBER 2002
1 INTRODUCTION
1.1This report details the projected outturn variances identified during the revenue budget monitoring exercise for September 2002.
1.2In addition to projected outturn variances the report identifies savings proposed to overcome variances in forecast outturn. Section 2 identifies the projected outturn variances
2 PROJECTED OUTTURN VARIANCES
2.1The undernoted table explains the variances in projected outturn reflected in the general ledger and financial reports for budget monitoring. Figures in brackets are adverse variances; those without are favourable.
Ledger code reference and Projected Projected Full year description Outturn Outturn effect on variance variance next years budget £ % £ CSTP Local Tax Collection
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Services Departmental Budgetary Review & Projected Outturn Variances: September 2002Report | 258 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.