Decision 1. To employ the services of Risk Management partners together with Gallagher Bassett to facilitate a Risk Management exercise at a maximum total price of £12,000 plus outlays at a maximum £2,400. 2. That a supplementary estimate to the sum of £14,400 be charged to Sundry Services to cover this cost. 3. To approve a further contribution from the Insurance fund to the General fund to meet the cost of insurance premium being incurred in 2002-2003 of £14,400. This will ensure the supplementary estimate recommended above has no impact on the General Fund Reserve. (Ref: Joint Report by Directors of Corporate & Legal Services and Finance dated 12 December 2002, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1A formal assessment of business risks is required to be undertaken by the Council in accordance with Corporate Governance arrangements. It is proposed to utilise the services of our public liability insurers and claims handlers (Risk Management Partners and Gallagher Bassett) to facilitate this exercise and create a formal Risk Register.
Recommendation
2.1The services of Risk Management Partners together with Gallagher Bassett be employed to facilitate a Risk Management exercise at a maximum cost of $12,000 plus outlays at a maximum of 652,400.
2.2A cost identified above is charged to Sundry Services and a supplementary estimate to the value ofS14,400 be approved for Sundry Services to cover this cost.
2.3A further contribution is approved from the Insurance Fund to the General Fund to meet the cost of insurance premium being incurred in 2002-2003 of 334,400. This will ensure the supplementary estimate recommended above has no impact on the General Fund Reserve.
3. DETAIL
3.1An essential part of Council business is to ensure that major business risks are identified and covered as far as possible. A process has to be undertaken whereby such risks are identified by Management and Members with appropriate officers tasked to monitor such risks with pre- agreed timescales. This process is an essential part of Corporate Governance.
3.2In order to facilitate an exercise of formally identifying business risks and preparing a Risk Register, it is proposed to utilise the services of Risk Management Partners and Gallagher Bassett who are our public liability insurers and claims handlers respectively. We have obtained a proposal from them which sets out a framework to assist the Council with the carrying out of risk audits within Services, the development of risk profiles and the compilation of a Risk Register. The main elements are as follows:-
1 Presentation and Training for Senior Management Team- Elected members - P750, 2 Identification of Strategic Risks (a) Structured interviews and report - $6750, or (b) Facilitated workshops with senior management teadsenioi members plus preparation and presentation of report - $4500, 3 Training seminars for operational managers (say 5) -24500, or 6 risk control days. 4 Facilitated workshops on identification and assessment of operational risks ( say 5) $5,625 or 7.5 risk control days.
3.3As part of our insurance contract with Risk Management Partners and Gallagher Bassett, we have a balance of 6 risk control days remaining which could be applied to offset part of the cost of this exercise. By applying these days to item 4 of the proposal (through negotiation), the final cost would be either $12,000 if structured interviews are preferred at item 2 or $9750, if the workshops are elected. All these costs are exclusive of VAT.
3.4The cost outlined above exclude outlays eg travel and subsistence and out of pocket expenses. An allowance of 20% has been made for this for budgetary purposes. Based on $12,000 this amounts to $2,400.
3.5Our Internal Audit partners KPMG also submitted a proposal which was along similar lines to that suggested by Risk Management Partners and Gallagher Bassett. We carried out an assessment of both proposals and, apart from being slightly cheaper than KPMG, we are of the view that Risk Management Partners and Gallagher Bassett also offer the following benefits:- 1 They have a vested interest in identifying, controlling and minimising the Council’s risks. 2 By using available loss control days, it not only keeps the cost down but also ensures that we they are achieving value for money. 3 They will have a continuing relationship with the Council in respect of both operational and strategic risk management, at Ieast for the term of the current insurance contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.