Resolved
Decision To refer the matter, without recommendation, to the Council on 13 February 2003. (Ref: Report by Director of Transportation & Property Services dated 9 January 2003, submitted).
Strategic Policy Committee decided this item on Thursday 30 January 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To refer the matter, without recommendation, to the Council on 13 February 2003. (Ref: Report by Director of Transportation & Property Services dated 9 January 2003, submitted).
Due to the current restrictions at Campbeltown New Quay, Vestas Celtic has requested that the existing facilities are upgraded.
This report details the work required to ensure that larger loads are transported by sea rather than by road.
The Committee is asked to note the contents of the report and acknowledge that detailed design work should proceed to ensure that the draft Capital Programme for this scheme can be met.
3. DETAIL
3.1The Company Vestas-Celtic Wind Technology Ltd have established their business in Machrihanish and are currently manufacturing wind turbines for two UK projects. The commencement date for the initial delivery of these units is late March 2003.
3.2Originally it was anticipated that Vestas Celtic would utilise the New Quay to import raw materials and export completed wind turbines and their components.
3.3However, a review of the existing pier has indicated that there are limitations on the use of the facility. In particular the inner face has inadequate strength and the pier has insufficient width to allow the larger loads to be transported through Campbeltown New Quay.
3.4Increasing strength and width requirements at the New Quay will permit the safe transfer of raw materials, wind turbines and their component parts from low loaders to suitable vessels.
3.5Discussions with Vestas Celtic have concluded that the New Quay needs to be widened by 25 metres on the inner face along its entire length accompanied by dredging of the harbour area.
F:\moderngov\data\published\Intranet\C00000188\M00001026\AI00007527\CampbeltownNewQuay0.doc 1 of 3 29 January 2003 3.6 The estimated cost of this scheme is unlikely to exceed the £2 million allowance in the draft Capital Programme but until a detailed estimate is prepared the initial statement cannot be guaranteed. The anticipated design fee of £100,000 is included in the scheme cost.
3.7The Department has investigated the possibility of additional external funding including the Scottish Executive's Piers and Harbours Fund and Freight Facilities Grant and if this should prove insufficient to fund the scheme, European grant funding will also be investigated. In addition Argyll and the Isles Enterprise has indicated strong support for this scheme and they would be willing to co-fund this project. An approach to Vestas Celtic for a capital contribution in return for agreeing a commuted sum for landing dues could also be made but it is likely that they would wish to provide their contribution by means of landing dues. A possible funding profile is as follows:
Cost of Scheme £2,000,000
Funded by Argyll and Bute Council £300,000 Scottish Executive (Piers & Harbours & Freight Facilities Grant) £1,500,000 Yet to be agreed AIE £200,000 Yet to be agreed
3.8If upgrading work is not undertaken then the raw materials, wind turbines and their component parts would have to be transported to and from Machrihanish by road. The increased loads would be detrimental in terms of delay and also the damaging effects to the integrity of the roads.
3.9Improved facilities will be required at Campbeltown New Quay regardless of whether the Scottish Executive's intention that the new Campbeltown to Ballycastle Ferry Service commences in the Summer of 2003.
3.10The current draft Capital Programme profile is as follows:
Year
To 2003/04 £100,000 2004/05 £1,850,000 2005/06 £50,000
In order to meet this profile detailed design work should commence and if an appropriate level of external funding can be acquired then construction could commence in January or February 2004, subject to obtaining the necessary external funding.
4. IMPLICATIONS
4.1Policy - None.
4.2Financial - The draft Capital Programme has an allowance of £2 million for this scheme, which requires an income level of £1.7 million or 85% of the scheme cost. The scheme should only proceed if these guidelines can be met.
4.3Personnel - None.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAMPBELTOWN NEW QUAYReport | 63 KB | DownloadRead as text |
Follow Strategic Policy Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2007 | Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... | Noted | Open |
| 19 Apr 2007 | North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... | Agreed | Open |
| 19 Apr 2007 | Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... | Noted | Open |
| 19 Apr 2007 | Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... | Agreed | Open |
| 19 Apr 2007 | Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.