Resolved
The Mid Argyll, Kintyre and the Islands Area Committee agreed to note the progress made on the Council’s Schools Redevelopment Project. (Ref: Report by Executive Director of Customer Services, dated 6 March 2019, submitted.)
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 6 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Mid Argyll, Kintyre and the Islands Area Committee agreed to note the progress made on the Council’s Schools Redevelopment Project. (Ref: Report by Executive Director of Customer Services, dated 6 March 2019, submitted.)
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
1.2Campbeltown Grammar achieved formal handover following sign off by the Independent Tester on 17 February and opened to pupils on 21st February 2018. Stage 2 is progressing well, with the demolition works all complete; the site cleared and levelled; the new bus drop off and parking areas nearing completion; landscaping works, spread across phase 2 are nearing completion and installation works for the new 3G pitch are ongoing.
Following the identification, and subsequent removal, of asbestos during the demolition phase, Hub and Morrison Construction advised of a potential delay of up to 8 weeks to Phase 2 of the programme and handover of this Phase is now advised as 18 March 2019.
1.3The tenth quarterly newsletter was issued in December, and was also made available through the dedicated Campbeltown Grammar School project website, hosted by Morrison Construction, at www.cgsproject.co.uk
1.4The Council’s Special Projects Team along with the FM company, FES, continue to hold regular meetings with the Head Teacher to discuss any issues within the school, along with ensuring all Health and Safety matters are addressed as contractually required.
It is recommended that Members consider the content of this report.
1 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE
CUSTOMER SERVICES 6 MARCH 2019
NEW SCHOOLS REDEVELOPMENT PROJECT UPDATE CAMPBELTOWN GRAMMAR SCHOOL
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
It is recommended that Members consider the content of this report.
4.0DETAIL
4.1The new Campbeltown Grammar School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as part of the Scottish Government’s Schools for the Future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates The key programme dates are:
Date Description Comment May 2016 – Phase 1 – Construction of February new school building 2018 Pupils/staff move February Campbeltown Grammar into new school 2018 School Decant building Demolition of existing school April 2018 – Phase 2 buildings and March 2019 External Works construction of new 3G pitch and car park All works completed March 2019 Phase 2 Completion and whole school availability At this stage in the Phase 2 construction period, there is an expected delay of up to 8 weeks to the intended programme taking completion to the early March. 2 4.3 Construction Update
The following works have been completed since the previous update report provided to Members: Preparatory works to allow the new 3G pitch installation are complete landscaping works, spread across phase 2 are nearing completion piping pavilion works are ongoing, with only internal decoration to be completed Outdoor store has been constructed New main gates and fencing installation have been completed Cedec path has been installed
Photographs illustrating progress made since December 2018.
Piping Pavilion in situ, with cladding works New main entrance gates installed complete
Carparking works ongoing Directional signage for pick up/drop off area
3 Cedec path External Landscaping works
Preparatory 3G pitch groundworks
4.4Future Works
Future works planned for the next period:
Progress internal Piping Pavilion decorative works 3G Pitch installation Complete soft landscaping works
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New School Redevelopment Project Update: Campbeltown Grammar SchoolReport | 2 MB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.