Resolved
Members agreed to note the contents of the report. (Ref: Report by Acting Executive Director of Community Services, dated 1 February 2017, submitted.)
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 1 February 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Members agreed to note the contents of the report. (Ref: Report by Acting Executive Director of Community Services, dated 1 February 2017, submitted.)
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
1.2The project continues to make good progress. The roof to the main sports hall has been completed along with the secondary steelwork to this section of the school building. The steel frame for the main school building has been completed with the secondary steelwork, roofing works and the installation of the concrete floors now under construction.
1.3Progress on the construction of the new school building is illustrated in a series of photographs in Paragraph 4.3.
1.4The second quarterly newsletter was made available prior to the end of the last school term and a dedicated website provided by Morrison Construction is now available at www.cgsproject.co.uk
1.5The second Considerate Contractor inspection took place on 5th December 2016. The site gained an excellent inspection report, with the executive summary available for Members as Appendix 1 hereof.
It is recommended that Members note the content of this report.
1 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE
COMMUNITY SERVICES 1 February 2017 CUSTOMER SERVICES
NEW SCHOOLS REDEVELOPMENT PROJECT UPDATE CAMPBELTOWN GRAMMAR SCHOOL
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
It is recommended that Members note the content of this report.
4.0DETAIL
4.1The new Campbeltown Grammar School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as part of the Scottish Government’s Schools for the Future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates The key programme dates are:
Date Description Comment May 2016 – Phase 1 – Construction of February new school building 2018 Pupils/staff move February Campbeltown Grammar into new school 2018 School Decant building Demolition of existing school April – Phase 2 buildings and November External Works construction of 2018 new 3G pitch and car park All works completed November Phase 2 Completion and whole school 2018 availability At this stage in the Phase 1 construction period, there is no change to the intended programme. 2 4.3 Construction Update The construction of the new building is progressing well with the following works taking place since the previous update report provided to Members on 7 December 2016. Namely: The main steel frame and the pre-cast stairs installation have both been completed; Shuttering to perimeter beam; Tanking to service trenches; Erection of secondary steelwork (cladding supports)has commenced; and Roof installation ongoing. The photographs 1- 12 below illustrate the progress made since December 2016.
Previous photograph – December 2016
Photograph 1 Sports Hall Roof Complete Photograph 2 Roofing contractors progressed onto working on roof grid lines E to G
Photograph 3 Reinforcing installed to 1st and 2nd Photograph 4 Concrete slab won 2nd floor with floor up to grid point M edge protection in place
3 Photograph 5 1st Floor concrete slab complete up Photograph 6 Steel erector carrying out paint to grid point J remediation. When the steel is chained for lifting into position the paint protection is “rubbed” off. The paint is reapplied when the steel is in situ.
Photograph 7 – The South gable end of the new Photograph 8 – West elevation showing the school building. This marks the completion of the completed structural steelwork from Grid A to U structural steelwork.
Photograph 9 Perimeter formwork shutter being Photograph 10 Concrete placement now in installed for the ground floor slab between grid perimeter beam from Grid E to J point E and J(1)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New Schools Redevelopment Project: Campbeltown Grammar School UpdateReport | 1.5 MB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.