Decision 1. Approved the updated Capital Programme totals for 2003/2004. 2. Approved the overall changes to the Capital Programme highlighted in the Appendix to the report. 3. Approved the increase in expenditure and funding from the Scottish Executive for Rothesay Flood Prevention from £1m to £1.6m. 4. Agreed that the bridge strengthening programme be accelerated. (Ref: Report by Head of Accounting dated 30 June 2003, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL- DRAFT PLAN OF CAPITAL EXPENDITURE COMPOSITE CAPITAL PROGRAMME - SUMMARY SHEET
Alterations which Adjustment Adjustments Revised Approved Adjustment Adjustment for Yearend Still to be Departments require for Slippage to Budget April May June July August September October November December January February March Plan 2003/04 for Slippage Accelerations Journals Profiled approval by to later years programme 2003/04 Council £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £
£ Formula Allocation 13,799,000 Additional consents received 3,016,000 Less Virement Waste Management P.P.P (600,000) Consent returned from East Renfrewshire Council 1,600,000 17,815,000 Less Anticipation used in 2002-2003 (1,413,951) 16,401,049 + Sale of Assets Land & Buildings 331,930 + Sale of Vehicles 100,000 + Loan repayments 50,000 + Grants & Contributions 2,584,216 Estimated Available Consent 19,467,195 Under (Over) Commitment (1,324,633) Percentage commitment of Available Consent -6.80%
Flood Prevention Alterations which Adjustment Adjustments Revised Approved Adjustment Adjustment for Yearend Still to be Departments require for Slippage to Budget April May June July August September October November December January February March Plan 2003/04 for Slippage Accelerations Journals Profiled approval by to later years programme 2003/04 Council £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ £ Miscellaneous Flood Prevention 1,000,000 600,000 1,600,000 0 0 0 0 236,000 210,000 220,000 210,000 210,000 220,000 210,000 84,000 0
Profiling is in respect of the Rothesay Flood Prevention scheme. Consent approval of £1.6 million received.
Appendices for SPC 10 July 2003 - Summary run on 01/07/2003 @ 10:59 Project details for information and noting
Forecast Approved Budget Expenditure per Variance in Percentage Category Department Project per 3 Year Plan spreadsheet cost Variance Note
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.