Oban Lorn & The Isles Area Committee agreed this item on Wednesday 8 October 2003. Below is the council's own wording, with the papers it was decided on.
It was agreed that: (a) a column be added to the spreadsheet for date of completion of works; (b) as the £5000 funding is now available for signage it be allocated to Roads and Transportation; and (c) Area Transportation Manager to prepare a report for November area committee meeting on proposals for works to account for the remaining £15,187.50 of the additional £20,187.50 from the disposal of assets. Councillor Robertson intimated that Connel Community Council wished her to express their appreciation in regard to work being undertaken on the pavement in Connel village.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL- PROGRAMME OF CAPITAL EXPENDITURE - 2003-2004 COMPOSITE CAPITAL PROGRAMME - AREA COMMITTEE - LORN & THE ISLES For Year to Date: 18 September 2003
Start date Project Budget /commencement of Project Description Manager 2003/2004 YTD Actual on site works Comments £ Taynuilt Sports Club - Grant towards all- K Macdonald 6,000 6,000 weather sports facility (Ward 10) Community Councils (Wards 10 & 14) for I Welsh 6,800 Ongoing activity. Rate of spend dependent upon uptake by Community Councils amenity enhancement projects Cattle Grid Replacement (Wards 10 & 14) N Brown 7,000 Full assessment being carried out. Materials on order
Dunollie Footpath, Oban (Ward 11) I Welsh 6,100 Sep-03 Mossfield Stadium - structural works to I Welsh 16,800 Oct-03 changing area and entrances (Ward 12) Land Acquisition, Soroba (Ward 13) D Kelly 16,800 2,055 Report to Council 22/10/03 seeking approval of CPO recommendation
Road Safety Improvements (Ward 14) N Brown 9,500 In progress
Bonawe Footpath (Ward 15) N Brown 10,000 Sep-03 Programmed for September
Crossapol, Tiree Village enhancement I Welsh 16,800 In consultation with local community. scheme (Ward 17) Improvements to parking arrangements N Brown 10,700 Nov-03 Feasibility being assessed. (Ward 11) Improvements to Etive View playpark, North I Welsh 6,800 Connel (Ward 15) Upgrading public toilets (Ward 16) I Welsh 16,800 Nov-03 Feasibility study into a fixed link to provide a P Ward 15,000 Sep-03 Work in progress tidal power scheme - Luing / Seil Provision of road signs throughout Oban, N Brown 5,000 Schedule being prepared Lorn & the Isles * Road Improvements - Area Wide N Brown 30,853 Luing resurfacing - wk comm. 22/9/03 Blaran road end - follow on from Luing Connel Village footway - October start
GROSS SPEND PLANNED 180,953 8,055
* Subject to confirmation that this sum is available for allocation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.