Report by Area Property Officer in regard to the dome and clock tower, North Pier Building

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Wednesday 8 October 2003. Below is the council's own wording, with the papers it was decided on.

Item6a

Resolved

The Committee agreed that: (a) Area Property Officer to apply for Listed Planning Consent for repairs to the dome and the clock; (b) A further report on progress be submitted to the Area Committee meeting on 5 th November 2003, to include details of the clock movement. (Ref: Report by Strategic Director of Operational Services dated 22 nd September 2003)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Summary

1.1The purpose of this report is to provide Members with information on a procedure which may be used to bring about the creation of a Harbour Trust to operate all harbour installations and facilities within Oban Bay.

Recommendation

2.1That Members note the terms of this report.

2.2That Members, if in principle they wish to develop the idea of a single harbour operator further, appoint Development Services as lead department and request the Director to form a project group to consider and report to Members on the wider implications of taking the proposal forward including the financial and economic implications, staff implications, set up cost implications etc.

Background

3.1Reference is made to the Report presented to the Committee on 23rd July 2003. As that Report noted, there are several harbour installations within Oban Bay and no single body operates or controls all of the various installations.

3.2Even the Harbour Authority created in terms of the provisions of Callander and Oban Railway Act 1878 was not truly a Harbour Authority, in respect that the sole statutory power given to the specified bodies forming the Authority was to appoint a single general harbour master whose authority, unless the individual operators agreed otherwise, was limited to those specified areas of the Bay outwith the areas allocated to each of the individual authorities.

3.3The matter under consideration within this Report is how in terms of the existing law it might be possible to bring about the formation of a single harbour authority with responsibility for the provision and management of all the harbour and port facilities within Oban Bay. The mechanism for achieving such an outcome would appear to lie within the provisions of the Harbours Act 1964 as amended. Section 18 of the Act makes provisions in relation to Harbour Reorganisation Schemes and provides that, with a view to securing the efficient and economical development of a group of harbours each of which is being improved, maintained or managed by a harbour authority in the exercise and performance of statutory powers and duties, a Harbour Reorganisation Scheme may be submitted to the Scottish Ministers by all or any of the existing harbour authorities. The matters which may be included in such a Scheme include – transferring existing statutory powers to a body constituted under the Scheme; transferring property interests to such a body; transferring existing staff to such a body; transferring to such a body the property interests of a person carrying out harbour operations even if such a person is not managing a harbour in the exercise and performance of statutory powers and duties (provided compensation is to be paid to such a person).

3.4The procedure involved in the preparation of a Harbour Reorganisation Scheme is somewhat complex and will involve the promotion of Subordinate Legislation in the Scottish Parliament. The procedure will also involve satisfying the Scottish Ministers that the creation of the proposed trust and the transfer of piers to such a trust would secure “the efficient and economical development of a group of harbours”. It would appear likely that it will be necessary to produce a full business case for the proposed trust, along with details of its proposed composition and management arrangements, plans of properties affected etc.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report by Area Property Officer in regard to the dome and clock tower, North Pier BuildingReport 66 KB DownloadRead as text

At this meeting

Whole meeting
3aMinute of meeting of Oban Lorn and the Isles area committee held on 3rd September 2003On the agenda 3bMinute of site meeting in regard to planning application ref. 03/01130/OUT held on 3rd September 2003On the agenda 3cArea Capital Funding - Progress reportAgreed 3dReport by Senior Environmental Health Officer in regard to Oban Sewerage System - Contamination with petrolAgreed 3eReport by Area Corporate Services Manager in regard to local public holidays 2004Agreed 4aList of Building Warrants approved by the Director of Development & Environment Services since the last meetingOn the agenda 4bList of Delegated Decisions issued by the Director of Development and Environment Services since the last meetingOn the agenda 4cPlanning Application ref: 03/00678/DETAgreed 4dPlanning Application ref: 02/01783/DETAgreed 4ePlanning Application ref: 02/02213/VARCONRefused 4fPlanning Application ref: 03/00732/OUTApproved 4gPlanning Application ref. 03/00840/OUTOn the agenda 4hPlanning Application ref. 03/00984/DETApproved 4iPlanning Application ref: 03/01045/DETAgreed 4jPlanning Application ref: 03/01169/DETOn the agenda 4kPlanning Application ref: 03/01409/OUTAgreed 5aApplications for financial assistance under the Social Welfare Grants SchemeDecided 5bReport by Better Neighbourhood Services Manager in regard to Better Neighbourhood Services Fund - Development PlansAgreed
6aReport by Area Property Officer in regard to the dome and clock tower, North Pier BuildingThis decision
27Exclusion of PressOn the agenda

Who was there

0 of 33 attended
AM
Councillor Alistair MacDougallChair, expected
AM
Councillor Allan MacaskillMember, expected
IG
Councillor Ian GilliesVice-Chair, expected
RB
Councillor Robin BanksMember, expected
SM
Councillor Sidney MacDougallMember, expected
DC
David CraigOfficer, expected
LM
Lorna MacKinnonSecretary, expected
JB
Jillian BrownSecretary, expected
NB
Neil BrownOfficer, expected
SC
Sandra CampbellSecretary, expected
CE
Carol EvansOfficer, expected
JG
Jane GilliesOfficer, expected

All 33 on the meeting page

On this subject at Argyll and Bute

Search all
  1. Report by Area Property Officer in regard to the dome and clock tower, North Pier BuildingThis decision
  2. D hill property ltd: residential development comprising 101 dwellinghouses including formation of vehicular accesses, landscaping, open space and play areas: land west of alexander street, dunoon (ref: 19/01456/pp)Agreed

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies