Resolved
Unanimously refused in terms of the recommendation contained in Supplementary Report No.1 dated 18 th September 2003. (Ref: Report by Head of Planning dated 14 th August 2003 and Supplementary report No.1, dated 18 th September 2003)
Oban Lorn & The Isles Area Committee refused this item on Wednesday 8 October 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Unanimously refused in terms of the recommendation contained in Supplementary Report No.1 dated 18 th September 2003. (Ref: Report by Head of Planning dated 14 th August 2003 and Supplementary report No.1, dated 18 th September 2003)
DEVELOPMENT SERVICES Local Member - Councillor R Banks PLANNING APPLICATION REPORT Date of Validity - 22nd January 2003 OBAN, LORN AND THE ISLES Committee Date - 8th October 2003
14th August 2003
Reference Number: 02/02213/VARCON Applicants Name: Aldi Stores Ltd Application Type: Variation of Condition Application Description: To waive condition 5 of outline retail consent 00/00548/OUT in order to permit food retailing Location: Land at Lynn Road, Oban
(A ) THE APPLICATION
Development Requiring Express Planning Permission
To vary the terms of an unimplemented permission in order to permit food sales, in circumstances where a condition attached to that consent limits the range of goods to be sold to non-food items only.
(B ) RECOMMENDATION
It is recommended that this application be refused on retail policy grounds.
(C ) DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
This application seeks to vary a condition imposed on an unimplemented non-food retail consent in an ‘edge of centre’ location, in order to allow food sales. It is therefore necessary to consider whether the location of this site is appropriate for unrestricted Class 1 retail use.
Both the development plan and national planning policy seek to maintain compact and lively town centres, by supporting the retention of existing retailers, and encouraging the location of new retail developments, within defined town centre core areas. This policy presumption is implemented by a mechanism known as the ‘sequential test’. This requires that new developments should be located within the boundary of a town centre as defined by the development plan, where suitable sites are available. In the event that a defined town centre is unable to accommodate a prospective retail development (due to the lack of available sites for development, or the extent of the floorspace required by the particular retail use, for example), then favourable consideration may be given to less preferable ‘edge of centre sites,’ provided that the centre as a whole has sufficient expenditure available to sustain such new development without it impinging upon the viability of the more favourably located retail core. ‘Out of town’ retail sites are the locations of last resort, which ought only to be considered where it can be demonstrated that no sequentially preferable sites exist.
In November 2000, outline planning permission was granted for a non-food retail warehouse on this ‘edge of centre’ site (Ref. No. 00/00548/OUT), as a justified minor departure to planning policy. The Retail Impact Assessment, accompanying that application had demonstrated to the Council’s satisfaction that there was sufficient potential expenditure for comparison goods (non-food) retailing within the population to support that proposal, without any significant detrimental impact on the viability and vitality of the town centre as a whole. At that time, there were no suitable sites/premises identified as being available within the town centre. Accordingly, the sequential approach required by NPPG 8 was satisfied. As the circumstances pertaining to food sales were considered materially different to non-food sales, (where there is surplus expenditure available largely due to consumers travelling to higher order shopping centres to purchase durable goods), a condition was attached to the permission precluding food sales. Subsequent approval of reserved matters was given in February 2001 (Ref. No. 01/00086/REM).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Application ref: 02/02213/VARCONReport | 117 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.