CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 3 December 2003 at 10.00am

KILCHOMAN WATER SUPPLY

Agreed Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 3 December 2003. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Area Committee agreed to recommend that the cost of maintaining and repairing the water supply to various properties at Kilchoman, which is a Council obligation should not be funded from the HRA but be taken from general Council funds because it was unsatisfactory that the tenants of Council houses should be subsidising the water supply to private owners. (Reference – Report by Director of Community Services dated 3 December 2003)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Summary

1.1The purpose of this report is to advise Members of the proposals and costs relating to the maintenance and repair of the water supply to various properties at Kilchoman, Isle of Islay.

Recommendation

2.1That Members note the terms of this report

3. DETAILS

Background

3.1.1. As this supply, like most other non-mains supplies, fails microbiological tests, we installed, as part of a departmental policy during 1995, “point of use” filters in the Council property fed by the system. This ensured that our tenants had a potable water supply. It did not provide suitable water quality for any other users. Normally the improvement of such systems is dealt with via the Council’s Capital Programme. However, as a result of considerable pressure from our Environmental Services department, we agreed to carry out basic additional filtration works to try to improve the water quality going to all users. This would be done as a matter of urgency bearing in mind the representation from ES.

3.1.2. Arrangements were made with a specialised contractor, ATEC Water Treatment, to design and install a suitable system. This was done during May 2002. Initial tests on the water confirmed that the quality was meeting Environmental Services requirements. The system is a basic filtration unit that requires the water to go through a series of in-line filters and UV treatment. Due to the high peat and iron content the filters require changing at intervals more frequently than some other supplies and we have been organising this to ensure we maintain the water quality. It was always recognised that these measures were of a basic nature and constant monitoring and filter maintenance would be on going and additional work may be required in light of the monitoring results. To provide a system that could perform in a manner where little or no maintenance is required would involve a much more complex arrangement.

3.2Current Situation

3.2.1. Currently we are changing filters as required, which can be as often as once a week in inclement weather and will continue to do so. The cost of this is not being charged to the other consumers of the water. Continual monitoring of the system by our contractor and the proprietor of Kilchoman House confirmed that problems existed with the in-line filters blocking up and it was decided to install additional treatment works on the advice of our consultant.

3.3.2. As a result of the original work carried out, in place is a new service pipe from the source to a new storage tank which is situated near the source, new filters in-line (two mesh sizes) and new UV treatment. This replaced the original system, which consisted of a concrete storage tank, which had to be removed, and delivery pipework. No water treatment was present at that time. The new system was installed during 2002 and from a water quality perspective has been working successfully. However, due to the high content of peat etc in the water and the fluctuating usage, the filters can get blocked up regularly and require to be replaced to allow a reasonable flow. This can be problematic as it can occur at inconvenient times and does stop the supply to all users.

3.3Proposals

3.3.1 To alleviate this situation it is proposed that an additional filtration tank be installed between the water source and the storage tank. This tank will work on the principle of sand filtration and backwash and will filter out the debris prior to it reaching the storage tank and the downstream filters. This should greatly reduce in-line filter blockage and ensure continuity of supply as well as potable water.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KILCHOMAN WATER SUPPLYReport 104 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 23 attended
AM
Councillor Alastair McKinlayChair, expected
BR
Councillor Bruce RobertsonMember, expected
DF
Deirdre ForsythSecretary, expected
JG
Jolan GergelyOfficer, expected
RM
Roddy McDowellOfficer, expected
HB
Hugh BlakeOfficer, expected
SB
Shona BrechinSecretary, expected
RC
Councillor Rory ColvilleMember, expected
RC
Councillor Robin CurrieMember, expected
ID
Ian DownieOfficer, expected
IF
Ian FawcettOfficer, expected
JF
Councillor Jim FindlayVice-Chair, expected

All 23 on the meeting page

On this subject at Argyll and Bute

Search all
  1. KILCHOMAN WATER SUPPLYThis decision
  2. Kilchoman water supplyDecided
  3. Kilchoman water supplyNoted

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies