CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 3 December 2003 at 10.00am

DEVELOPMENT CONTROL - SIX MONTHLY PERFORMANCE REPORT

Noted Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 3 December 2003. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Decision Members noted the contents of the report and congratulated Richard Kerr on achieving such excellent results. (Reference – Report by Head of Planning dated 3 December 2003)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Summary

2.1As detailed in my report, my Department is currently 1.7% behind the 90% target for processing all householder applications within two months and 3.6% behind the 72% target for processing all applications within two months.

2.2In terms of the decentralised areas the report highlights that:

• Bute and Cowal is 7% below its target of processing 77% of all applications in two months.

• Helensburgh and Lomond is 6% above its target of processing 78% of all applications within two months.

• Oban, Lorn and the Isles is 7% below its target of processing 65% of all applications in two months.

• Mid Argyll, Kintyre and Islay is 2% above its target of processing 66% of all applications in two months.

Recommendation

3.1It is recommended that Members:

(a) Note the contents of the report.

4.0COUNCIL WIDE DEVELOPMENT CONTROL PERFORMANCE SET AGAINST COUNCIL PERFORMANCE STATISTICS

4.1The Development Control function has recently completed the six monthly Scottish Executive return for the period 1st April to 30th September. This return shows that the Council has processed 88.3% of all householder applications within two months and 68.4% of all applications within two months.

4.2The six monthly monitoring exercise has therefore identified that there is a 1.7% shortfall in processing householder applications (target 90%) and a 3.6% shortfall in processing all applications (target 72%).

4.3With regards to the remainder of the statistical year, it is a matter of managing the process to attempt to overcome the target shortfalls. In this regard it should be noted that two planning officer posts have recently been filled, one each in Oban, Lorn and the Isles and Helensburgh and Lomond. Once the post holders have fully settled into the work practices and procedures there will be a benefit to the Council which should start to become apparent over the next six months. Additionally a further planning officers post has been advertised for the Oban, Lorn and the Isles area and interviews are likely to be carried out in late November although an appointee is unlikely to be in post until the start of January 2004. The benefits of this post are unlikely to be fully realised until after April 2004 although this post should significantly aid both the overall Council wide and local area performance.

5.0DECENTRALISED DEVELOPMENT CONTROL PERFORMANCE

5.1BUTE AND COWAL

As Members will recall, a target of processing 77% of all applications within two months was set by the Area Committee earlier this year.

5.2In this regard Bute and Cowal has:

• Processed 177 applications in the 6 monthly period. • Processed 124 of these within two months (70%), which represents a figure 7% below target. • Of the 177 applications, 67 were householder applications of which 63 were processed within two months (94%).

5.3With regards to the above, the Bute and Cowal area team has over the years consistently achieved a high performance within the Council wide area. In 2000/2001 and 2001/02 some 71% of all applications for the year were within the eight-week period.

The area team has a new target of 77% determination of applications within the eight-week period that represented a consolidation of performance. This also allowed for the loss of a small part of the area to the National Park and for the training of the new Area Planning Officer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DEVELOPMENT CONTROL: SIX MONTHLY PERFORMANCE REPORTReport 70 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 23 attended
AM
Councillor Alastair McKinlayChair, expected
BR
Councillor Bruce RobertsonMember, expected
DF
Deirdre ForsythSecretary, expected
JG
Jolan GergelyOfficer, expected
RM
Roddy McDowellOfficer, expected
HB
Hugh BlakeOfficer, expected
SB
Shona BrechinSecretary, expected
RC
Councillor Rory ColvilleMember, expected
RC
Councillor Robin CurrieMember, expected
ID
Ian DownieOfficer, expected
IF
Ian FawcettOfficer, expected
JF
Councillor Jim FindlayVice-Chair, expected

All 23 on the meeting page

On this subject at Argyll and Bute

Search all
  1. DEVELOPMENT CONTROL - SIX MONTHLY PERFORMANCE REPORTThis decision
  2. Registration of an economic development subsidy scheme to facilitate compliance with post-eu subsidy control legislationNoted
  3. Caravan sites and control of development act 1960 new licensing system for mobile home sites with permanent residentsAgreed
  4. Caravan sites and control of development act 1960 - new licensing system for mobile home sites with permanent residentsAgreed
  5. Fyne futures ltd: erection of 3 wind turbines (100 metres high to blade tip), control building, new and improved access tracks and ancillary development: land south of auchadaduie, barr glen, glenbarr, kintyre (ref: 11/02525/pp)Agreed
  6. A'chruach wind farm limited: windfarm comprising 21 turbines (126.5 metres high to blade tip), erection of 2 meteorological met masts, sub station, control building, construction compounds, access works and ancillary development (amended prAgreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies