Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 3 December 2003. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed to postpone discussion of the Playing Fields Strategy to a special meeting at 1:30 pm on Tuesday 6 January 2004 in the Council Chambers, Kilmory and to ask the Strategic Policy Committee to continue consideration of the document until after that meeting. (Reference – Report by Director of Operational Services dated 3 December 2003)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This report is intended to seek Area Committee Members views prior to presentation to the Strategic Policy Committee, as a first stage of consultation on the draft update of the Councils Playing Fields Development Strategy. This is required in order to bring it into line with the strategic policy of sports governing bodies and to reflect changes in the criteria for match funding of outdoor sports facilities by the major funding bodies. It also contains an update on progress since the previous report and recommendations to ensure the future success of the programme.
Recommendations
It is recommended that :
2.1The Committee endorse the attached “Playing Fields Strategic Review” and its appendices as a Draft Consultation Document for discussion with the appropriate groups and bodies scheduled in Appendices 8.1,8.2,8.3,8.4.
2.2Argyll and Bute Council adopt a vision of providing every community with access to “all weather sports facilities” centred round its secondary, larger or isolated primary schools, and social inclusion areas in recognition of the high level of rainfall, poor soil conditions and lack of alternative facilities available in the area.
2.3To maximise their use and durability, each new facility is of high quality and that arrangements are made to ensure these facilities are maintained to a level sufficient to allow their continued use for a period of 30 years or over.
2.4With the introduction of the Public Private Partnership / NPDO for schools, the specification for outdoor and indoor sports facilities at these locations are agreed urgently, and that the brief for the first phase of projects is compatible with the Playing Fields Strategy for School and Community Facilities.
2.5There is a continuation of Council funding for the development of Natural Grass Pitches, Synthetic Turf Pitches, Multi Use Games Areas, Changing Accommodation and other external sport and play facilities through the capital programme as adopted in the 1999 Playing Fields Strategic Review.
F:\moderngov\data\published\Intranet\C00000243\M00001209\AI00012011\AmendedDecemberAreaCtteReport 1 PlayingFieldsStrategicReview0.doc 2.6 Following feedback from the Areas the Stragic Policy Committee adopt the draft Three Year Capital programme for the development of outdoor sports facilities as shown in Appendix 7.2 attached. This programme to be updated on a regular basis as detailed information becomes available.
2.7In view of the very different lead-in times taken by each project partnership, the Playing Fields Development Unit adopts a flexible approach to the project prioritising and positioning detailed in Appendices 7.3 and 7.4 of the Strategic Review.
2.8The Council is willing, in line with the Local Government in Scotland Act 2003, to enter into partnership agreements, or working relationships with properly constituted groups and organisations, or project steering groups, in order to secure the funding and construction of outdoor sports facilities.
2.9The Council as a proposed “eligible body” is willing to act as lead partner in making direct applications to sportscotland in line with their “Lottery Fund Strategy Review” referred to in section 4.3 attached and that these applications should be on a prioritised basis.
2.10The Council is willing to support partners, such as sports clubs and community organisations, who wish to make direct applications to sportscotland’s “Awards for All” category, in conjunction with the Council as relevant major partners. Such applicants will require to demonstrate adequate organisation, demand and resources as it is unlikely that Council match funding will be available to lower priority projects.
3 SCOPE OF THE REPORT
3.1The “Playing Fields Strategic Review” will update the Strategic Policy Committee on progress since the original review was presented to members on the 10th November 1999.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.