Decision 1. To note the position as at 31 December 2004. 2. To note that the poor performance referred to in respect of the works at Port Askaig Pier related to time and not quality of workmanship. (Ref: Report by Head of Strategic Finance dated 8 March 2005, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report outlines the progress with the composite capital programme as at 31 December 2004. Year to date expenditure is currently £8,006,093 below the profiled budget, but it is £5,585,252 more than the equivalent period in 2003-2004
1.2A reduction in forecast expenditure of £10,188,569 is projected for the full year. However this is offset by a reduction in expected income of £5,055,752 giving a net decrease in expenditure of £5,132,817 for the full year.
Recommendations
2.1To note the position at the 31 December 2004 (Appendix 1).
3 DETAIL
3.1Year to date gross expenditure at 31 December amounts to £15,920,812, which equates to 49.04% of the projected outturn. This is offset by a year to date income contribution of £5,701,939 giving a net expenditure of £10,218,873. This is 61.90% of net expenditure forecast for the year. In 2003-2004 the gross expenditure to 31 December was £10,335,560, which equated to 50.16% of the projected outturn.
3.2Committed gross expenditure at 31 December is £24,977,360. This is equivalent to 76.93% of the projected outturn. In 2003-2004 the committed expenditure to 31 December was £17,789,410, which equated to 86.33% of the projected outturn.
3.3Year to date expenditure is currently £8,006,093 below the profiled budget. As at 30 November 2004, year to date expenditure was £5,762,698 below the profiled budget. An analysis of the main variances in income or expenditure (+/- 10% and > £50,000) in respect of the year to date budget is included in Appendix 2. The main projects contributing to the change in variance from November are shown in Appendix 3.
3.4The main issues to note at 31 December relate to the forecast outturn position. In summary the forecast expenditure is down by £10,188,569. Forecast contribution from income is down by £5,055,752 giving a net decrease in net expenditure of £5,132,817 for the full year. As at 30 November 2004, the forecast expenditure was down by £8,683,261. Forecast contribution from income was down by £3,460,874 giving a net decrease in net expenditure of £5,222,387 for the full year. Therefore net expenditure forecast for the year has reduced by £325,604 since 30 November 2004. An analysis of the projects with significant increases or decreases in income or expenditure (+/- 10% and > £100,000) against full year budget is included in Appendix 4. The main projects contributing to the change in variance from November are shown in the following table:
NOV DEC CHANGE REASON PROJECT VARIANCE £ VARIANCE £ £ Campbeltown New 1,044,118 1,444,118 400,000 Full Council Quay approved acceptance of tender. Expected start March 2005 with approx. £200k payments to Contractor in March
Oban High School 0 163,710 163,710 Late tender issue
Achahoish Primary 100,000 200,000 100,000 Slippage – awaits School (New Build) agreed start date with contractor John Logie Baird 0 96,000 96,000 Work plan Primary School revised to reduce disruption to school Ardrishaig Primary 0 78,825 78,825 Design stage School taking longer than anticipated Ashfield Primary (44,900) (4,900) 40,000 Reprofiled spend School Campbeltown 0 40,000 40,000 Additional income Community Project - from Scottish income Water Tarbert Academy 0 36,600 36,600 Late design start Sandbank Primary 0 35,717 35,717 Late design start School Kilchattan Primary 0 34,550 34,550 Brief to be School reviewed Total 1,025,402
3.5The report to 31 January has recently been finalised. Based on the January report the year to date net expenditure is £10,477.331. This is an underspend against the budget profile of £8,006,093. The shortfall in projected outturn net expenditure at 31 January is £8,391,830. The projects reported in this report as contributing to the December underspends are the same projects as those contributing to the January position, although the amounts have increased.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.