A816 CARNASSERIE - PRELIMINARY STAGE COST ESTIMATE

Decided Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee decided this item on Wednesday 7 June 2006. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision To recommend to the Strategic Policy Committee that consideration be given to the use of reserves to carry out this work as it is an emergency road repair, which if not carried out could require the road to be closed and the costs to escalate. (Reference – Report by Head of Roads and Amenity Services, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Summary

This paper indicates the breakdown of the cost of carrying out repairs to the A816 road at Carnasserie.

Recommendations

It is recommended that the committee note these costs.

3. DETAILS

The breakdown of the estimated costs is as follows: -

Preliminaries £50,000 Safety Fencing £25,000 Drainage works £10,000 Earthworks (see note 1) £320,000 Structural work and bank stabilisation (see note 2) £100,000 Carriageway reconstruction £115,000 Minor miscellaneous works £15,000 Work for public utilities £25,000 Archaeological Works (see note 3) £10,000 Survey, temporary works design, preliminary design work, detailed Design, site supervision and committee reporting. £90,000 Land £1,000 Contingencies £152,200

TOTAL £913,200

Note 1. Main site cost is excavation and disposal Note 2. Cost and extent of stabilisation works to existing slope below the road will not be known until the contractor can move the road away from its present location. Note 3. An Archaeological site within the works will be investigated – cost may need to be revised depending on the outcome.

1 4. IMPLICATIONS

4.1Policy – None; 4.2 Financial – None; 4.3 Personnel – None; 4.4 Equal Opportunities – None; 4.5 Legal – None.

Stewart Turner, Head of Roads and Amenity Services

For further information, please contact D. McLeod, Area Manager Mid Argyll, Kintyre and Islay (01546 604671)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A816 CARNASSERIE: PRELIMINARY STAGE COST ESTIMATEReport 61 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 29 attended
AM
Councillor Alastair McKinlayChair, expected
BR
Councillor Bruce RobertsonMember, expected
DF
Deirdre ForsythSecretary, expected
SC
Sandra CampbellSecretary, expected
RC
Councillor Rory ColvilleMember, expected
RC
Councillor Robin CurrieMember, expected
JF
Councillor Jim FindlayVice-Chair, expected
MG
Martin GorringeOfficer, expected
GH
George HarperOfficer, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryOfficer, expected
DK
Councillor Donald KellyMember, expected

All 29 on the meeting page

On this subject at Argyll and Bute

Search all
  1. A816 CARNASSERIE - PRELIMINARY STAGE COST ESTIMATEThis decision
  2. A816 carnasserie - preliminary stage cost estimateAgreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies