Resolved
Decision The Motion received 4 votes and the Amendment received 5 votes and the Committee resolved accordingly. (Reference – Report by Director of Corporate Services dated 30 May 2006, submitted).
Mid Argyll, Kintyre & the Islands Area Committee decided this item on Wednesday 7 June 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Motion received 4 votes and the Amendment received 5 votes and the Committee resolved accordingly. (Reference – Report by Director of Corporate Services dated 30 May 2006, submitted).
1.1This report, which is brought before the Committee on the instruction of the Chair, describes the situation in regard to Dunaverty Village Hall which is currently progressing towards renovation. In view of the Council decision on 4 May 2006 that no further funding be awarded for village halls during the 2006/07 financial year unless it is funded by an area committee from its budget for leisure grants, in considering Dunaverty Hall the Area Committee will require to consider any funding from its budget for leisure grants as the only source of funding.
2.1It is recommended that in light of the Council decision on 4 May 2006 (including that relating to Tarbert Village Hall) and the implications set out in this report the Area Committee should note that it will not be possible to support Dunaverty Hall during the current financial year in addition to Tarbert Village Hall.
3.1Dunaverty Village Hall Committee decided in 2001 to commence work which would lead to the rebuild of the Hall.
3.2In August 2002, the Council’s Head of Corporate Policy advised that the Scottish Executive were favourably disposed towards the initial proposal from Southend for the rebuild of the Hall. The application from the Hall Committee for funding was considered in 2004, but not agreed as a priority for submission to the Scottish Executive. This was considered at the Strategic Policy Committee meeting on 4 November 2004, and the estimated cost of the project was shown as £500,000 with £25,000 in hand and £25,000 pledged.
3.3Current costs have been assessed at £631,000. To date it is understood funding of £338,000 has been raised or pledged.
F:\moderngov\data\published\Intranet\C00000243\M00002431\AI00029289\DunavertyHall0.doc 3.4 It is also understood, several potential funders have indicated to the Hall Committee that if there was a contribution from the Council, they would also be willing to make appropriate contributions to complete the package.
3.5In August 2005, the Hall Committee were advised by the Community Learning and Regeneration Manager that there would be no bidding round in 2005/2006 from the Scottish Rural Partnership Scheme which included the local capital grant scheme in support of village halls.
3.6Planning permission was granted for the project on 3 October 2003.
3.7The Hall Committee are a registered charity with 3 trustees who are the Council’s Chief Executive, the Sheriff and the Head Teacher of the Primary School. The latter is also a member of the Hall Committee.
3.8Had the Hall Committee known that this matter would be discussed at the last Council meeting on 4 May 2006 they would have asked that their application be included.
4. COUNCIL DECISION – 4 MAY 2006
4.1When on 4 May the Council dealt with applications for funding towards certain other halls they agreed the principle of awarding up to a maximum of £50,000 subject to the relevant Hall Committee obtaining any further necessary permissions, and their funding package being fully in place within a period of a specified number of months from the date of the Council Meeting, the funding to come from Reserves and that any free Revenue underspends in the revenue budgets within the Area Committee area for 2006/07 be directed to refund the relevant amount to the Reserves.
4.2However, the Council specifically decided on 4 May that that no further funding be awarded for village halls during the 2006/07 financial year unless it is funded by an area committee from its budget for leisure grants. In view of the Council decision it will be necessary in considering Dunaverty Hall for the Area Committee to consider any funding from its budget for leisure grants as the only source of funding. There is currently a balance of £3,975 available in this budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DUNAVERTY VILLAGE HALLReport | 81 KB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.