Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 7 June 2006. Below is the council's own wording, with the papers it was decided on.
Decision The Committee thanked Jenny for her presentation and agreed: 1. the grant offer be accepted; 2. the sum of £235,000 in the Capital Programme , within Development Services current budget, be allocated to the Campbeltown CARS and for environmental improvements in Campbeltown Town Centre; 3. a steering group be formed, comprising members, representatives local groups and officers, to develop and manage the project; 4. a part-time Project Officer be recruited. (Reference – Report by Conservation Design Officer dated 11 May 2006, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1Argyll and Bute Council has been awarded £385,000 by Scottish Ministers through Historic Scotland from the Historic Environment Regeneration Fund. This grant award is for Campbeltown and is to be spent during the period 2006-2011.
Recommendations
2.1I recommend that: a) the grant offer be accepted; b) the sum of £200,000 be allocated to the Campbeltown CARS; c) a steering group be formed, comprising members, representatives local groups and officers, to develop and manage the project; d) a part-time Project Officer be recruited.
Background
3.1Last summer Historic Scotland announced a new funding stream, the Historic Environment Regeneration Fund with a budget of £8 million, inviting bids for conservation area regeneration schemes.
3.2I am delighted to be able to report that the bid for Campbeltown was successful and that Argyll and Bute Council has been offered £385,000 for a five-year project.
3.3The award is for a Conservation Area Regeneration Scheme (CARS), focused on the historic town centre, that will bring specific neglected historic buildings back into use, repair other significant historic buildings and set up a small projects grant scheme. 3.4 At the same time the project will seek to raise the profile of the historic built environment, celebrate local identity and promote the town centre. It is also expected to improve the standard of building repair and maintenance generally and provide training and new job opportunities.
3.5CARS are partnership schemes, delivered through local authority Conservation Officers and monitored nationally by Historic Scotland. Local authorities are required to provide partnership funding on a matching basis. The package being developed for Campbeltown requires a capital allocation of £200,000 from Argyll and Bute Council.
3.6It is important that we work with a wide variety of partners, using the money available as effectively as possible. We need to link this work to other funding streams, harnessing the activities of agencies such as Argyll and the Isles Enterprise (AIE) and Communities Scotland. The CARS and AIE’s painting scheme for shops in the town centre, for example, will work together.
3.7The project will be developed and delivered through a Local Steering Group. A locally based, part-time Project Officer will be required to manage the project.
3.8The target area is restricted to the Main Street and Longrow South parts of the town centre. The list of target buildings that will form the focus of the project includes: Bolgam Street Courthouse Old Post Office Former Free Church School Burnet Building Town Hall
3.9The small projects grant scheme is likely to concentrate on high level works, such as roof repairs and guttering but may also include sash and case window repairs and reinstatement. This scheme will be developed by the Local Steering Group to ensure its effectiveness. Grants will also be available for the repair and reinstatement of shopfronts and signage and will work in conjunction with AIE’s shopfront painting scheme.
3.10The Conservation Area boundary will be reviewed as part of the project, with an Appraisal and Management Plan drawn up locally. 4. CONCLUSION
4.1This grant award gives us a superb opportunity to work actively towards revitalising Campbeltown’s town centre. It provides national support for the activities of Argyll and Bute Council, other agencies and the local community.
5. IMPLICATIONS
Policy: Accords with current and emerging policy. Need to link with Area for Action work.
Financial: Allocation of resources required within existing development services budget
Personnel: Recruit Project Officer
Equal Opportunity: None
For further information contact: Jenny Carlile
Telephone 604277
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.