Decision 1. To note the allocation of the capital grant as detailed at Appendix 1 of the report; 2. To note the programme of internal property energy audits commissioned by the Property Services Energy Team as detailed at Appendix 2 of the report; and 3. Agreed that Drumlemble Primary School should be added to the list detailed at Appendix 2. (Reference: Report by Head of Facility Services dated 13 June 2007, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The Executive notes the allocation of the capital grant.
3. CAPITAL GRANT ALLOCATION
3.1The £2.3 Million capital grant allocation requires to be spent by 31 March 2008, although it is understood that some allowance will be made for projects to complete at the latest by June 2008. Bids for capital grant allocation were submitted for specific named projects by Community Services, Operational Services and IT.
3.2The allocation of capital grant is summarised at Appendix 1.
3.3As this grant allocation is in addition to the existing capital programme, in determining each Service allocation, it has been necessary to consider the deliverability of the proposed projects. In order to maximise delivery and minimise risk, the rationale employed has been to focus initially upon qualifying projects which are already within Service capital programmes.
3.4In determining the primary allocation, the following factors were taken into account:
• Payback period • Risk • Resourcing & capacity to deliver • Requirement for statutory permissions – e.g. planning
3.5Projects within existing Service programmes which qualify for the additional grant allocation amount to £1,066M 3.6 The remaining capital grant allocation of £1,234M has been divided proportionately against Service bids. These remaining projects are based upon estimated costs and have varied risks associated with them.
3.7This capital grant allocation represents an additional challenge for Service resources to deliver, and consequently, if the allocation is approved, there may be a requirement to adjust the phasing of the current capital programme to reflect the additional projects.
4. ENERGY AUDITS & SURVEYS
4.1Phase 1 The Property Services Energy Team has commissioned a programme of internal property energy audits which are programmed to report by the end of July. The properties targeted are at Appendix 2, and represent the highest energy users within the Council: half hourly electricity sites, non NPDO secondary schools, high fuel oil and gas usage sites and Leisure facilities. These audits will be funded from the Water Fund.
4.2The audits will identify energy savings measures at each location. It is proposed that Property Services provides a report to SMT in September 2007 to report on the outcome of these audits and to identify proposed works. It is proposed that at the same time a progress report is submitted by Services in receipt of the additional capital grant to establish progress with the completion of works. The SMT may at that stage wish to consider altering funding priorities to ensure that the benefit of the grant is maximised, and that programmes of work will complete within the required timescales.
4.3Phase 2 It is proposed to undertake a further programme of external energy audits in October/November on building fabric/thermal imaging. These external audits use thermal imaging technology to assess the external heat loss from buildings.
5. CEEF FUNDING
5.1The CEEF fund can only support projects which have a payback of five years or less. The CEEF fund at Year End is estimated at £200K approx. The fund can also be used to fund projects which arise from the Energy Audit programme. 6. APPENDICES
Appendix 1 Proposed Capital Grant Allocation Appendix 2 Energy Audit Programme - Internal
Sandy Mactaggart Head of Facility Services 13 June 2007
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.