Resolved
Decision Approved the revised rates and agreed that a review of the rates be undertaken each year in the annual charges as part of the budget process. (Reference: Report by Director of Operational Services dated 22 May 2007, submitted).
Executive approved this item on Wednesday 13 June 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Approved the revised rates and agreed that a review of the rates be undertaken each year in the annual charges as part of the budget process. (Reference: Report by Director of Operational Services dated 22 May 2007, submitted).
Road Bond values have not been reviewed since 1996. The road bond is a deposit which is lodged with the Council by developers prior to construction works commencing on site as part of their Planning Permission/Building Consent. The attached tables provide amended rates that will be used to calculate road bond values.
The Committee is asked to approve the revised rates and also instruct that a review of the rates is undertaken each year in the annual charges as part of the budget process.
3.1The Roads (Scotland) Act 1984 Section 21 requires developers to provide financial security to Local Authorities prior to development work commencing on a site for domestic or industrial use in which a new road is required to be constructed. This deposit would only be “called up” if the developer goes into receivership or where the developer refuses to complete the works.
3.2The current rates were set in 1996 by Strathclyde Regional Council and there has been no review since then. It is considered appropriate that a review is now undertaken. The current rates would be insufficient to complete any construction of a road based on current construction costs. Any negative balance would still have to be provided by the Council, but these revised rates would limit the liability or negate the possibility of the Council having to fund any additional works required.
4. DETAIL
4.1See Appendix 1 which provides details on the proposed rates. 4.2 See Appendix 2 which details the existing rates.
5. IMPLICATIONS
5.1Policy – None. 5.2 Financial – These amended rates will protect the Council should developers enter receivership or refuse to undertake road construction works.
1 5.3 Personnel – None.
5.4Equalities Impact Assessment – None. 5.5 Legal – None.
For further information, please contact Martin Gannon (Tel: 01546 604613).
Stewart Turner Head of Roads & Amenity Services 22 May 2007
2 APPENDIX 1 SCHEDULE OF ROAD CONSTRUCTION COSTS FOR ESTIMATING AMOUNT OF ROAD BOND
Price (£) per linear metre of road Item 7.3m 6.0m 5.5m 3.5m 2.0m Remarks Carriageway (flexible) 390 350 330 210 - Stage Construction Full Construction Stage 1 : Construction up to and including (Stages 1, 2 and 3) sub base, allowing for removal of up to 100mm unsuitable material and replacement with imported fill.
Stages 2 and 3 only 291 263 209 155 - Stage 2 : Construction from sub-base upwards including kerbs but excluding wearing course.
Stage 3 only 78 66 63 44 - Stage 3 : Wearing course only.
Shared Surface - - 400 275 - Includes for removal of up to 50mm (Block Paving) unsuitable material and replacement with imported fill.
Soft Verge (grassed) - - - - 15
Footway (flexible) - - - - 63 Includes provision of heel kerb (1 No.)
Footpath (flexible) - - - - 90 Includes provision of edge kerbs (2 No.) Footway and Footpath prices include for removal of up to 50mm unsuitable material and replacement with imported fill. Increased widths to be calculated pro-rata.
Lighting 44 38 38 39 39
Drainage Manhole depths not exceeding 1.5m Gullies at 20 m centres 130 130 130 130 - Includes for manhole at 80m centres. Gullies at 40 m centres 90 90 90 90 - Includes for manhole at 120m centre. Turning 'T' (Flexible) Residential Dimensions 3969 Cost is for the area in addition to the (Block Paving) Residential Dimensions 4382 normal road width. It does not include footways and it is a lump sum.
Turning 'O' (Flexible) Residential Dimensions 12787 7(Block Paving) Residential Dimensions 15157
NOTES :
(i) The costs are based on the Department carrying out all the work. In recognition that smaller works are more expensive to complete, an additional allowance shall be made as follows.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROAD BOND VALUESAgenda | 78 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.