Resolved
Decision To approve the acceleration of £300,000 of funding to this financial year from the Infrastructure and Transport Block Allocation for 2009/2010. (Reference: Report by Director of Operational Services dated 22 May 2007, submitted).
Executive approved this item on Wednesday 13 June 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To approve the acceleration of £300,000 of funding to this financial year from the Infrastructure and Transport Block Allocation for 2009/2010. (Reference: Report by Director of Operational Services dated 22 May 2007, submitted).
The purpose of this report is to advise the Executive of the landslip at Kilbride Road in Dunoon and to seek approval for the allocation of funding from the Capital Programme to have area of the landslip reinstated and the road re- opened.
The Executive is asked to approve the acceleration of £300,000 of funding to this financial year from the Infrastructure & Transport Block Allocation for 2009/2010.
3.1On 13 December 2006, following a period of heavy rain, a landslip occurred on a section of the U46 Kilbride Road, Dunoon between Crochan Road and Kilbride Bridge. Several hundred tonnes of overburden slipped down the slope causing significant damage to 33 and 42 Broomfield Drive including the demolition of a conservatory and garage. The material came to rest against the houses to a depth of around 2 metres. Fortunately the owners of No. 33, the worst affected property, managed to escape from the house via the front windows and suffered no injury.
3.2Approximately two-thirds of the width of the carriageway was lost and a gas main and water main were left exposed spanning the slip. The slope above the carriageway was not affected.
3.3Between 20 and 22 December 2006, the material around the houses was cleared to allow access and an assessment of the damage to be made. There are several structural cracks evident at No.33 and some internal damage caused by the material entering the rear of the house. Apart from the loss of a conservatory and damage to a patio, No.42 appears to have experienced no structural damage. In order to assess the full extent of the damage to the slope, a full topographical survey was carried out on 20 and 21 December 2006.
3.4Since the slip occurred, there have been two points on the slope where a steady flow of water has been issuing. These points are about 2 to 2.5 metres below the road surface and well below any road drainage. However, there are no obvious watercourses on the hillside above the slip and it is assumed that this is groundwater passing down through a permeable layer in the slope. The quantity of flow does not seem to be dependent on weather conditions. The cause of the landslip appears to have been the flow of groundwater lubricating the soil below the overburden to such an extent that friction was lost and the material slid down the slope.
3.5In order to reinstate the damaged section of Kilbride Road, stabilise the slope and re-open the road, the following remedial works are required.
(i) Clearance of the toe of the slope and construction of a faced reinforced earth retaining wall
(ii) Removal of further soft material from the behind the area of the retaining wall
(iii) Installation of filter drains below the slope to catch the groundwater
(iv) Installation of a filter drain behind the retaining wall to collect all water draining from the slope and carry it to the nearby Balgaidh Burn
(v) Placing of fill behind the retaining wall to form a 1 to 2 slope;
(vi) Soiling and seeding of the finished slope including planting of shrubs
(vii) Reinstatement of road drainage in Kilbride Road, reconstruction of the carriageway and reconnection of water and gas mains.
3.6The current estimated project cost of the remedial works is £300,000. A review of the current capital programme in Roads & Amenity Services has failed to identify any current schemes where there is any anticipated slippage or underspend. The Capital Five Year Rolling Programme 2006/2011 has a Block Allocation in 2009/2010 for Infrastructure & Transport. It is proposed that £300,000 from this allocation is accelerated to this year to allow the works to be undertaken.
4 IMPLICATIONS
4.1Policy - None 4.2 Financial - Acceleration of £300,000 of funding from the 2009/2010 Block Allocation for Infrastructure & Transport is required. 4.3 Personnel - None 4.4 Equal Opportunities - None 4.5 Legal - None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LANDSLIP: U46 KILBRIDE ROAD, DUNOONAgenda | 252 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.