Decision To recommend to the Council that approval be given to the allocation of £400,000 from the Strategic Housing Fund in support of this project, subject to Fyne Homes receiving all necessary permissions and complying with the criteria for drawdown set by the Council. (Reference: Report by Director of Community Services dated 23 August 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper outlines Fyne Homes’ proposals for the redevelopment of the former Council Chambers and neighbouring Sheriff Court building together with their adjacent property at 3 King Street, Rothesay. These have been developed over the past few years in full consultation with the Council and Communities Scotland.
1.2Fyne Homes have requested the allocation of £400,000 from the Council’s Strategic Housing Fund in support of the project. If allocated, this funding would then be used to secure Housing Association Grant from Communities Scotland together with the necessary private finance for the £4.4m project.
Recommendation
2.1Members are asked to agree to the allocation of £400,000 from the Strategic Housing Fund in support of this project, subject to Fyne Homes receiving all necessary permissions and complying with the criteria for drawdown set by the Council.
3. DETAIL
3.1Background: Over the past few years, Fyne Homes have been developing proposals for the conversion of the former Council Chambers and neighbouring Sheriff Court building in the centre of Rothesay. While these buildings remain in the ownership of the Council and the Courts’ Administration Service, the proposals have been developed in collaboration with the Council and Communities Scotland to ensure compliance with the Local Housing Strategy. In view of the prominence of the buildings within the townscape of Rothesay, close liaison has also been developed with local Development Control staff.
3.2Fyne Homes have already received planning permission for the redevelopment of these buildings but now intend to incorporate the refurbishment of their neighbouring property at 3 King Street within the project. This was destroyed by fire late in 2006, with only the shell of the building remaining. A planning application is about to be submitted for this element of the project. 3.3 Proposed development: Due to the poor condition of the King Street property and the Council owned building, the redevelopment proposals comprise demolition, façade retention and new build of this section. In contrast, subject to the satisfactory conclusion of negotiations with the Courts’ Administration Service, the former Sheriff Court will be refurbished.
3.4On completion, the following units of accommodation will be provided:
• King Street – 4 x 1 bedroom/2 person flats • Council building and Sheriff Court - 19 x 1 bedroom/2 person flats and 6 x 2 bedroom/4 person flats
• Total – 29 flats
Members are asked to note that the flats proposed for the Council and Sheriff Court buildings will be serviced by a lift so will be capable of accommodating clients of mixed needs.
3.5The current position: Communities Scotland have appraised the project in detail with Fyne Homes and have made the commitment to allocate a substantial funding package over the next 3 years to allow the project to proceed. This package has been developed within the context of their approved cost limits. In addition, Members may recall, that through our joint working with Communities Scotland, the Council has already committed £200,000 of Early Action Funding in support of the project. This has been used to finance the archaeological investigations that were required prior to the commencement of the development work.
3.6Project Costs: The anticipated costs of the project that have been appraised by Communities Scotland are as follows:
Demolition and façade retention £0.594m New build and refurbishment £3.809m Total cost of provision £4.403m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.