CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Executive, Thursday 20 September 2007 at 10.00am

SCHOOL HOSTELS

Agreed Executive 1 paper

Executive agreed this item on Thursday 20 September 2007. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Decision 1. To agree to adopt Option 2 as detailed in the report which would lead to the closure of Dunoon School Hostel for a period of 1 year to enable the delivery of the necessary improvements; 2. To agree to the allocation to £1.236m by substituting the Block Allocation from the Education programme in 2009-2010 to fund the required improvements at both Dunoon and Glencruitten Hostels; 3. To note that a decision regarding the timetable for Glencruitten Hostel will be subject to further discussions with Strathclyde Fire and Rescue and that a further report will be brought to the Executive Committee. (Reference: Report by Director of Community Services dated 14 September 2007, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Executive

Summary

1.1Members will perhaps recall that I submitted a report to the Executive on the 16th August 2007, in relation to the Dunoon School Hostel. Arising from this, Members requested the creation of a Business Plan to investigate future options for the building.

1.2This report restates the building issues that are experienced at both the Dunoon and Glencruitten establishments. It also outlines the key findings of the Business Plan that has been developed with the assistance of the Head of Strategic Finance, for the future of the Dunoon Hostel. Finally, building on the Business Plan findings, together with the improvement regime required by the Care Commission and Strathclyde Fire & Rescue Service, it makes clear recommendations for future investment in both buildings.

Recommendation

2.1Members are asked to: a) agree to the adoption of Option 2 which would lead to the closure of the Dunoon School Hostel for a period of 1 year to enable the delivery of the necessary improvements. b) agree to the allocation of additional £1.236m from substitution within the existing capital plan to fund the required improvements at both Dunoon and Glencruitten hostels.

3. DETAIL

3.1BUILDING ISSUES: Members are reminded that the Dunoon and Glencruitten Hostels are built to the “Clasp System” design. This incorporates asbestos based material to provide fire protection.

3.2A recent Health & Safety Executive report has highlighted potential hazards associated with the asbestos. Much of this has already been removed at Glencruitten Hostel but it remains in situ in Dunoon. While the Care Commission has also highlighted the requirement to upgrade common areas, toilets etc at both hostels, more critically, utilising their powers under the Fire (Scotland) Act 2006, Strathclyde Fire & Rescue Service have presented the Council with a 7 point action plan specifically for the Dunoon Hostel. They have also indicated that it is their intention to serve an Enforcement Notice under this legislation to ensure compliance. It is understood that the Notice will contain the same requirements as the action plan as indicated in the following table: FIRE ACTION PLAN

1) Provision of a suitable and sufficient fire risk assessment specifically to the relevant premises. 2) Installation of a British Standard 5839 part 1: L1 automatic fire detection system. 3) All hazard rooms should be fitted with a FD 30S door with a self closing device. 4) Sub division of the corridors to ensure that the maximum travel distance should not exceed 9 metres where there is a single direction of travel. 5) Where the building or part of the building only has one escape route by way of an escape stair, access to the escape stair should be by way of a protected lobby. 6) To limit the severity of the fire, the building should be divided into different fire resisting compartments by fire resisting doors, walls and floors that will provide a physical barrier to fire. The premises should be examined to see if there are any easy paths through which smoke and fire could spread. 7) For an external escape stair, every part of an external wall (including a door, window or opening) not more than 2 metres from the external escape stair, should have a short duration (30 minutes) fire resistance.

3.3Business Plan for Dunoon: The total investment requirements for the Dunoon Hostel were incorporated within the Business Plan which was prepared utilising Net Present Value principles under which the capital cost associated with the upgrading proposals was discounted across the life cycle of the property attributes.

3.4In addition to the foregoing, option influencing factors such as the differing revenue costs and savings were incorporated. These include the transportation costs where they are required as an alternative to hostel provision, together with potential redundancy costs where there is the risk that staff may not be redeployed within the service.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SCHOOL HOSTELSReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 36 attended
CH
Charlotte HanburyMember, present
MA
Maureen ArthurMember, apologies
GC
Councillor Gordon ChalmersMember, in attendance
RC
Councillor Rory ColvilleMember, in attendance
RC
Councillor Robin CurrieMember, present
FF
Fiona FisherMember, absent
GF
Councillor George FreemanMember, apologies
GH
George HarperOfficer, in attendance
AH
Councillor Alison HayMember, present
DH
Douglas HendryOfficer, in attendance
DK
Councillor Donald KellyMember, present
AL
Andy LawOfficer, in attendance

All 36 on the meeting page

More from Argyll and Bute Executive

All decisions
MeetingDecisionOutcome
19 Apr 2012 Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) Noted Open
19 Apr 2012 EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) Noted Open
19 Apr 2012 European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) Noted Open
19 Apr 2012 Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... Noted Open
19 Apr 2012 Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies