Decision To note the Capital Plan position as at 30 June 2007. (Reference: Report by Head of Strategic Finance dated 24 July 2007; report by Head of ICT and Financial Services dated 16 July 2007; report by Head of Community Regeneration dated 17 July 2007; and report by Head of Roads and Amenity Services dated 20 July 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The capital plan position report is noted. (Appendices 1-3).
2.2To note the projected increases in total project costs at Appendix 4 and to consider whether an increase in budget should be approved.
3 DETAIL
3.1Appendix 1 summarises financial performance in terms of expenditure on the capital plan at 30 June 2007. Actual expenditure to 30 June 2007 amounted to £5.152m being 35% of the annual budget of £14.932m. The actual expenditure of £5.152m represents 37% of the June projected outturn of £14.040m. Appendix 2 summarises overall project performance in terms of cost, timescale, benefits and risk. Project performance is summarised based on a red, amber and green traffic light analysis, where red requires corrective action, amber is a warning that there are performance issues but these are manageable and green is no significant performance issues.
3.2The individual projects with red classifications are reported in the relevant head of service report with comments on what the red issue is, what has caused it, the action proposed to correct it and the implications of the action. These reports are presented in Appendix 3.
3.3The table below summarises the overall financial position on the capital plan.
Previous Years Full Year This Future Years Total Project Year Actual Budget Forecast Budget Forecast Budget Forecast Budget Variance £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s 55,845 55,557 14,040 14,932 85,974 84,271 155,859 154,760 -1,099
Slippage of £892k has been forecast for this year. The main projects contributing to this are Modernising Government £400k and Milton Burn Flood Prevention £235k. Delays on Modernising Government resulted from proposals being reviewed before moving on to implementation. The Milton Burn consultation process took over two years to complete, resulting in delays in the granting of planning permission. The main projects contributing to the £1.099m total project variance are Oban Airport £350k, Port Askaig £275k and Rothesay Harbour Ferry Berth Improvements £123k. The anticipated increased costs for Oban Airport have arisen from settlement of the civil contractor’s costs. Project costs have risen for Port Askaig due to the increased tender value of the Phase 2 works and detail design work of the Phase 3 pier buildings identifying higher than expected costs. Weather factors have delayed works on Rothesay Harbour resulting in difficulties completing critical parts of the works. A full list of projected increases to total project costs is shown at Appendix 4.
3.4The table below summarises project performance using traffic light analysis (Red, Amber, Green) in respect of cost, timescale, benefits and risk. The analysis shows the number of project lines and includes both expenditure and income lines. Of the 269 project lines, 21 project lines relate to 16 projects which are classified as red.
Spend This Project Total Project Project Project Risk Year Cost Timescale Benefits R A G R A G R A G R A G R A G 17 45 207 11 33 225 5 39 225 1 8 257 6 17 246
For further information please contact Bruce West, Head of Strategic Finance 01546- 604220
Bruce West Head of Strategic Finance 24 July 2007 CAPITAL PLAN MONITORING REPORT AT 30 JUNE 2007 - FINANCIAL SUMMARY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.