Decision To agree that the Director of Community Service pursue the proposal which has been received and report back to the Executive’s next meeting in March 2008. (Reference: Report by Director of Community Services dated 21 February 2008, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report outlines issues which have been raised in relation to current and proposed community facilities at Arrochar, and makes recommendations in respect of these.
Recommendation
2.1The Director of Community Services pursue the proposal which has been received, and report back to the Executive’s next meeting.
3. DETAIL
3.1The Council, at their 2007 Budget Meeting made a provision of £50,000 as a contribution to the cost of capital works towards the construction of a new village hall in Arrochar. The community group taking the village hall project forward have, it is understood, secured other funding towards this project but, as at the date of this report, a full statement of the financial position is not available.
The Council has been advised that, if an overall funding package for the project, understood to cost in excess of £1M, has not been agreed in principle by the end of February, other elements of the package which have been agreed will cease to be available.
There is a “funding gap” in respect of the whole cost of the proposed new village hall, and the Council has been asked to provide further assistance. Specifically, it has been suggested that the capital receipt which has accrued to the Council in respect of the disposal of the former Arrochar Outdoor Centre - £305,000 – should be specifically allocated towards the village hall project.
If Members were minded to pursue this proposal then it would be necessary to carry out a full assessment of the proposal as it currently stands, and the Council would require to be satisfied that the allocation of a further £305,000 to this project was (a) appropriate and (b) good use of public money.
4.1The proposal which has come forward is not specific enough to permit a formal determination by the Council. Further investigation requires to be carried out. If Members are minded to proceed on this basis, then it should be on the basis that these investigations are carried out and a further report brought back to the Executive’s next meeting.
5. IMPLICATIONS
Policy: Deviation from existing policy in regard to allocation/utilisation of capital receipts.
Finance: Possible contribution of £305K, in addition to £50K previously allocated as a contribution towards the cost of a new community facility in Arrochar.
Personnel: None
Legal: The Council would require to be satisfied any proposal agreed could be made.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.