Resolved
Decision To note the contents of the report and agree the response as detailed in the report for submission to the Scottish Parliament. (Reference: Report by Director of Development Services dated 26 February 2008, submitted).
Executive noted this item on Thursday 20 March 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To note the contents of the report and agree the response as detailed in the report for submission to the Scottish Parliament. (Reference: Report by Director of Development Services dated 26 February 2008, submitted).
1.1The Scottish Parliament’s Transport, Infrastructure and Climate Change Committee is holding an inquiry into ferry services in Scotland. The Committee is keen to hear the views of ferry users and other interested parties to assist its inquiry. The deadline for views is the 31st March 2008 and this paper details the proposed response to the inquiry from Argyll and Bute Council.
2.1That member’s note the contents of the paper and propose any changes that they feel are necessary before it is submitted to the Scottish Parliament.
3. DETAIL
The following headings / questions are the points that the Committee are particularly interested in hearing views on. It is proposed that this forms the basis of Argyll and Bute Council’s response.
3.1Ferry Routes – how useful are current ferry routes and what potential is there for new routes?
3.1.1. Current ferry routes not only provide vital lifeline services for our islands, they also provide important commuter links for communities such as Dunoon and Rothesay. Life in these island and peninsular communities centres on the ferry service – for employment, for access to health care and for the local and tourism economy. Whilst the current routes are, in the main, fulfilling their purpose a review of the ferry network in Scotland is long overdue.
3.1.2. The National Transport Strategy, published in December 2006, stated that a long term strategy for ferry services should be developed, including “a detailed appraisal of routes to determine whether a better configuration could be developed in response to calls for new and faster connections serving isolated communities.” This detailed appraisal would reveal the potential for new routes and offer an excellent starting point in developing a sustainable ferry network across Scotland.
3.1.3. Difficult issues will need to be explored in this appraisal, e.g.:
• Where can shorter more frequent crossings be achieved? • In which locations are fixed links a viable, more sustainable option? • The cost of some ferry services is prohibitive to the user. If a wealthier and fairer Scotland is to flourish then these costs must also be reviewed.
Page 1 of 4 • Why are some local authorities in Scotland charged with operating ferry services when the majority are served by a national undertaking? • Climate change poses a serious risk to ferry services with rising sea levels and frequent storms. Are our ports and harbours in the best location to provide a connected transport network?
3.1.4. Without this kind of far reaching review the long term social and economic sustainability of island and peninsular communities is in jeopardy.
3.1.5. Argyll and Bute Council carried out a review of its Piers, Harbours and Ferries in 2005 which was aimed at:
• establishing appropriate maintenance and management techniques for our piers and harbours and exploring mechanisms to increase the income for future investment and maintenance work. • the provision of ferry services and the level to which the Council should be involved in this service delivery.
In addition, the Council has recently agreed to prepare a business plan for its piers and harbours which will detail the projected investment required on a lifecycle basis. This will ensure that the relevant piers and harbours are maintained in a "fit for purpose" state for both Council and other ferry services.
3.2Frequency and timetabling of services – are ferry services run at times which are convenient to users?
3.2.1. The frequency of services varies considerably across the ferry network. This can be attributed to the number of vessels currently in operation on the network and the varying journey times to islands. The frequency of services bears a close relationship to the remoteness of the community served.
3.2.2. Looking at some examples to illustrate:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Inquiry into Ferry Services in ScotlandReport | 85 KB | DownloadRead as text |
Follow Executive at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2012 | Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) | Noted | Open |
| 19 Apr 2012 | Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... | Noted | Open |
| 19 Apr 2012 | Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.