Decision 1) To note the Capital Plan position as at 31 December 2007; and 2) To note the position in respect of Rothesay Harbour. (Reference: Report by Head of Strategic Finance dated 1 February 2008, report by Head of ICT and Financial Services dated 16 January 2008, report by Head of Community Regeneration dated 31 January 2008, report by Head of Roads & Amenity Services dated 31 January 2008 and report by Head of Facility Services dated 31 January 2008, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The capital plan position report is noted. (Appendices 1-3).
3 DETAIL
3.1Appendix 1 summarises financial performance in terms of expenditure on the capital plan at 31 December 2007. Actual gross expenditure to 31 December 2007 amounted to £22.176m being 53% of the gross annual budget of £41.834m and 57% of the project outturn of £38.944m. Actual income to 31 December 2007 amounted to £9.426m being 46% of the annual income budget of £20.672m and 44% of the projected outturn of £21.457m. This translates into actual net expenditure of £12.750m being 60% of the annual budget of £21.162m and 73% of the December projected outturn of £17.487m.
3.2Appendix 2 summarises overall project performance in terms of cost, timescale, benefits and risk. Project performance is summarised based on a red, amber and green traffic light analysis, where red requires corrective action, amber is a warning that there are performance issues but these are manageable and green is no significant performance issues.
3.3The individual projects with red classifications are reported in the relevant head of service report with comments on what the red issue is, what has caused it, the action proposed to correct it and the implications of the action. These reports are presented in Appendix 3.
3.4The table below summarises the overall financial position on the capital plan.
Previous Years Full Year This Future Years Total Project Year Actual Budget Forecast Budget Forecast Budget Forecast Budget Variance £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s £000’s 55,972 55,958 17,487 21,162 86,788 76,913 160,247 154,033 -6214 3.5 Slippage of £2.878m was forecast as at 31 October. Given the lack of potential to accelerate projects, a report was submitted to the Executive Committee where it was agreed that the budget for net capital expenditure in 2007-08 be reduced by £2.878m and increase the budget for 2008-09 by an equivalent amount. The budgets have been changed to reflect the agreed course of action.
3.6As at 31 December, slippage of £3.675m has been forecast for this year. This is an increase of £797k on that previously reported and largely be attributed to the Schools Fund Grant noted below. The slippage can be attributed to the following projects: School Buildings Fund Reduced Class Sizes £780k – Condition of additional grant was to create slippage to meet Scottish Government’s proposal to reduce class sizes. Port Askaig £441k – Contractor has failed to meet programme, resulting in delays accepting Phase 3 Milton Burn Flood Prevention £335k – delays in progressing scheme design due to diversion of staff resources to other work Oban High Community Facility £330k – scope & timescale of surplus land sale to be considered Flood Prevention £264k – delayed start to scheme design due to revenue funding not being available, and loss of staff resources causing delays in progression of programme Kilbride Road Flood Prevention £206k – Further consultation needed with affected householders before scheme can be confirmed Glencruitten Hostel £150k – Increased asbestos removal and Fire Authority inspection has introduced additional pre-contract work Gortonvogie £150k – Increased workload caused by additional central government grant funding has diverted resources from this project Rationalisation of Social Work Offices £150k – Planning approval delayed by an objection
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.