Resolved
It was agreed, therefore, that in section 16 of the PID, and in any other part of the document relating thereto, the Initial Project Plan should detail stages up to and including ordering the pontoon, and should thereafter state ‘phased payments thereafter’. It was agreed that Nicola would circulate the amended documents when available. Peter Ward spoke to the Oban Development Road PID. It was noted that there is no direct Project Board involvement in the project until the final design and construction phase, although members of the Board would be advised of progress in respect of the earlier stages on a regular basis.. After discussion it was remitted to Nicola Debnam and Peter Ward to refine the details of the project definition.
Word for word from the decision Argyll and Bute published for this meeting.