Decision 1. Noted the contents of the report and scorecards for financial quarter 3 2010/2011 including the revisions made to the Council scorecard; 2. Noted that the targets for sickness absence are being revised and will be based on the individual circumstances of each department; and 3. Noted that a training session will be delivered to Members on the new outcome based Scorecards being developed for the 2011/12 financial year. (Reference: Reports and Scorecards by Chief Executive and Executive Directors for the period October – December 2010, submitted) #
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL EXECUTIVE CHIEF EXECUTIVE’S UNIT 10 MARCH 2010
PERFORMANCE MANAGEMENT REPORT: FQ3 20010/11
Summary The Planning and Performance Management Framework (PPMF) and the Improvement Plan set out the structure and timescale for reporting the Council’s performance to Elected Members on a quarterly cycle.
The Chief Executive and Executive Directors will present the Council Scorecard and Departmental Scorecards to the Executive, using the Council’s performance management system, Pyramid. The presentation will focus on performance during the period October to December 2010, including a review of successes & key challenges and an outline of improvement actions for the coming period.
Directors’ reports and Scorecards are attached (large printed copies of Scorecards will be available at the meeting).
Sally Loudon Chief Executive
1 Performance Report for Development and Infrastructure Services period September – December 2010 Key Successes 1. Roads Operations, Fleet Maintenance and Streetscene winter maintenance performance throughout the early and prolonged extreme winter weather experienced during November and December. Some limited disruption to refuse collection but no refuse backlog. 2. The Roads Operations Service shortlisted as one of the best and most improved Highway Authorities for an APSE award. 3. Capital roads reconstruction programme completed to a high standard. 4. Bridge construction on Coll and bridge strengthening on Mull are progressing as planned. 5. Continued achievement of national recycling and composting targets. 6. Highest recorded performance of 75% achieved in planning applications determined within timescale - resulting in 18% above benchmark average and an improvement over last quarter of 15% points. 7. Continued good progress with key Economic Development priorities: Business Gateway supported 20 new business start ups taking the total to date to 134; the Employability Team’s performance in securing jobs for long term unemployed was 12.78% points ahead of target and the UK national average at 37.78%; LEADER programme awarded £417K to 16 community projects. 8. Continued achievement of all Regulatory statutory functions, including 100% of high risk food premises inspected. 9. Successful introduction of the Council’s new fuel management system and fleet hire desk.
Key Challenges 1. Addressing the impact that the severe winter weather and “frost heave” has had upon the condition of road network and managing the projected overspend of the winter maintenance budget as a direct result of the duration and severity of the early winter weather, and the procurement of salt supplies. 2. Local Development Plan (LDP) Main Issues Report delayed publication. 3. Achieving a satisfactorily outcome from the negotiations that will determine whether MBT Compost Like Output (CLO) will continue to be counted as composting affecting the Council’s overall recycling performance and containment of landfill charges. 4. Subject to necessary approvals, implementation of the four 2010 Service Reviews, whilst developing and delivering a further six new Service Reviews within Development and Infrastructure Services. 5. Appointing a PSO operator for Argyll Air Services. 6. Retaining the sole verifier status for Building Standards from May 2011. 7. Continuing to deliver high levels of departmental performance and improvement whilst undergoing and implementing ten Service Reviews.
Action Points to address the Challenges 1. Assessment of the roads network has been undertaken, permanent and temporary repairs will be made during FQ4 to maintain road safety with programmed works prioritised and undertaken during 2011/12 as capital budgets for roads reconstruction allow. 2. LDP Main Issues Report key evidence is being gathered to ensure alignment with revised corporate priorities. 3. Representations have been in person to SEPA and the Scottish Government aimed at maintaining CLO as a recyclable commodity. A
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.